5.

Examples of external installation

1000 min.
1500 min.

Fig. 5

Fig. 5a

Fig.5b

1500 min.

Fig. 6

Fig. 5b

Fig.7

Fig. 5 5a 5b 5c
External installation with curve conveyor (optional) and roof for protection. In this case the air is
taken in and discharged outside.
Fig. 6 External installation with a T conveyor (optional) and roof for protection. In this case during winter time the air is
taken in and discharged inside; during summer time the air is collected inside and discharged outside.
In both situations air suction must exclusively come from the inside.
Fig. 7 External installation with galvanized version without air duct or roof.

5.4

Hydraulic connection in open circuit

On the basis of the installation requirements both of the users and Chillers, it is possible to arrange the following open
ring hydraulic lines solutions:
hydraulic line on the ground;
overhead hydraulic line.
The above mentioned solutions may be installed using two different layouts:
in line;
in closed ring.
The following recommendations are very important, too:

provide thermal insulation for the piping, to avoid condensation and considerable thermal losses;
plan the diameter of the pipes in relation to possible future enlargements, so as to avoid any future modifications of
the plant;
install the circulating pump in a well near the tank, if possible under hydrostatic head. Otherwise install a non-return
valve on the suction pipe;
install a wide surface net filter on the suction pipe to avoid the ingress of dirt inside the evaporator;