STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 1 OF 4

PLANT AREA : GENERATOR AUX SYSTEM


TESTING SCHEDULE : STATOR & ROTOR COOLING,EXCITATION,SEAL OIL INITIAL
CIRCULATION & GAS FILLING SYSTEMS

1. PLANT DETAILS
GENERATOR AUX SYSTEM CONSISTS OF EXCITATION,
GENERATOR STATOR & ROTOR COOLING,SEAL OIL INITIAL
CIRCULATION AND HYDROGEN GAS FILLING SYSTEM.
2. TESTING OBJECTIVE
TO MAKE GENERATOR SYSTEM READY FOR GENERATION AND
SYNCHRONISATION
3.PROPOSAL
I EXCITATION
THIS SYSTEM CONSISTS OF THREE PHASE PILOT EXCITER,THREE
PHASE MAIN EXCITER,COOLER,METERING,CONTROL AND SUPERVISORY
SYSTEM. AT STANDSTILL, INSULATION RESISTANCE AND WINDING
RESISTANCE OF PILOT AND MAIN EXCITER ARE TO BE MEASURED.
GROUND FAULT DETECTION TEST TO BE CARRIED OUT AND MADE READY
FOR ON LINE MONITORING. ROTOR IMPEDANCE MEASUREMENT TO BE
CARRIED OUT.INSULATION RESISTANCE OF POWER CABLES TO BE
MEASURED.CONTROL PANEL(DAVR) TO BE CHECKED AS PER TEST
REPORT SUPPLIED.AT THE FULL SPEED OF TURBINE,RATED VOLTAGE
AND CURRENT ARE TO BE CHECKED WITH GENERATOR TESTS.
II GENERATOR STATOR COOLING SYSTEM
STATOR CORE IS COOLED BY COLD GAS. THIS GAS IS
ABSORBING HEAT FROM THE CORE & RETURNED TO THE COOLERS VIA
AXIAL FLOW FAN. STATOR WINDINGS,PHASE CONNECTORS AND
BUSHINGS ARE COOLED BY TREATED(DM) WATER IN THE CLOSED
CIRCUIT.THIS WATER IS AGAIN COOLED BY SEA WATER SYSTEM.
III GENERATOR ROTOR COOLING SYSTEM
THE ROTOR WINDING IS SYMMETRICAL RELATIVE TO THE
GENERATOR CENTRE LINE AND POLE AXIS. EACH COIL QUARTER IS
DIVIDED INTO TWO COOLING ZONES. I COOLING ZONE COVERS ROTOR
END WINDINGS & II ZONE COVERS THE PORTION BETWEEN ROTOR BODY
END & THE MIDPOINT OF THE ROTOR. COOLING IS DONE BY HYDROGEN
GAS SYSTEM.
IV HYDROGEN GAS FILLING
MAY BE EXPLAINED BETTER BY MECHANICAL TEAM
V SEAL OIL INITIAL CIRCULATION SYSTEM
MAY BE EXPLAINED BETTER BY MECHANICAL TEAM
4.SERVICES REQUIRED

/var/www/apps/conversion/tmp/scratch_7/278935561.doc

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 2 OF 4

PLANT AREA : GENERATOR AUX SYSTEM


TESTING SCHEDULE : STATOR & ROTOR COOLING,EXCITATION,SEAL OIL INITIAL
CIRCULATION & GAS FILLING SYSTEMS

220 V DC SUPPLY,DM WATER, AUX COOLING WATER SYSTEM, CO2,


HYDROGEN GASES, MONITORING SYSTEM
5.0 SAFETY PRECAUTIONS
I)
VENT VALVES & WASTE GAS VALVES ARE PROVIDED TO KEEP
OPEN DURING STARTING
II) VAPOUR EXHAUSTER IS INSTALLED TO AVOID THE ESCAPE OF
SEAL OIL & FLOW IS MONITORED BY A FLOW TRANSMITTER WITH
A LIMIT SWITCH.
III) TO AVOID HYDROGEN LEAKING VIA SEAL OIL STORAGE TANK &
LOOP SEAL,LOOP OIL IS PERMANENTLY FILLED WITH OIL.
IV) CONTINOUS VENTILLATION OF THE SEAL OIL STORAGE TANK
PREVENTS THE FORMATION OF ANY EXPLOSIVE HYDROGEN-GAS
MIXTURE.
V)
ALL TEMPERATURES,PRESSURES AND FLOWS ARE MONITORED
SIMULTANEOUSLY AND TRIPS THE MACHINE IF ANY ABNORMAL
DEVIATION FOUND IN ANY ONE OR MORE PARAMETERS
6. EMERGENCY PROCEDURE
I)
CONTROL & LOCAL EMERGENCY PUSHBUTTONS PROVIDED FOR
SAFEGUARDING TURBINE ANDGENERATOR.
II) FORE EXTINGUISHERS ARE PROVIDED AROUND THE SYSTEM.
III) POWER SUPPLY TO THE SYSTEM CAN BE ISOLATED
IV) MANUAL COOLING/SEALING TO BE ENSURED IN CASE OF
BLACKOUT CONDITION
7. STATE OF THE PLANT
I EXCITATION SYSTEM
POWER CIRCUIT IS COMPLETED.CONTROL CIRCUIT
TERMINATIONS ARE UNDER PROGRESS. AVR TESTING TO BE CARRIED
OUT AT SITE AS PER TEST REPORT. RTDS OF EXCITER BEARINGS,
ROTOR OVERVOLTAGE & OTHER PROTECTIONS TO BE MADE THROUGH.
II GENERATOR STATOR & ROTOR COOLING SYSTEM
GENERATOR IS TO BE FILLED WITH CO2 AT FIRST & THEN
REPLACED BY HYDROGEN GAS. DM COOLING WATER PUMPS TO BE
COMMISSIONED. RTDS OF STATOR WINDINGS,TOOTH,CORE AND HOT &
COLD GAS ARE TO BE CONNECTED. WATER TEMPERATURE OF BOTH DMCW
AND ACW & GAS TEMPERATURE ARE TO BE MONITORED.
III & IV SEAL OIL AND GAS FILLING SYSTEM
TO BE GIVEN BY TEAM OF MECHANICAL ENGG.
SEAL OIL CIRCUIT IS TO BE MADE THROUGH AFTER FLUSING

/var/www/apps/conversion/tmp/scratch_7/278935561.doc

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 3 OF 4

PLANT AREA : GENERATOR AUX SYSTEM


TESTING SCHEDULE : STATOR & ROTOR COOLING,EXCITATION,SEAL OIL INITIAL
CIRCULATION & GAS FILLING SYSTEMS

8 COMMISSIONING PROCEDURE
I EXCITATION SYSTEM
AT STANDSTILL,ROTOR IMPEDANCE MEASUREMENT,GROUND FAULT
DETECTION MUST BE CARRIED OUT.IN AVR PANEL, AUTO & MANUAL
FIRING OUTPUTS,SMOOTH CHANGEOVER AND INTERLOCKS TO BE
CHECKED. REMOTE CONTROL PANEL COMMANDS AND RELAY PANEL
INTERLOCKS, PROTECTION TRIPPINGS ARE TO BE CHECKED.
DUMMY/LIGHT TEST TO BE CARRIED OUT. AT FULL SPEED NO LOAD,
PHASE SEQUENCE OF SYNCHRONOUS SUPPLY & GENERATOR SUPPLY
SHOULD BE IN POSITIVE SEQUENCE AND PHASE IN-PAHSE OUT TO BE
MATCHED WITH PERMISSIBLE LIMITS.
II GENERATOR COOLING SYSTEM
STATOR WINDING,CORE AND TOOTH TEMPERATURES ARE TO BE
MADE OK. HOT GAS & COLD GAS TEMPERATURES,PRIMARY WATER AND
BEARING TEMPERATURES ARE TO BE HOOKED UP IN THE CONTROL
ROOM.ALARM & TRIP VALUES TO BE SET TO PROTECT THE EQUIPMENT
IN CASE OF SUDDEN RISE ANY ONE OF THE PARAMETERS.
III SEAL OIL SYSTEM
SEAL OIL PUMP & VAPUR EXHAUSTER ARE TO BE COMMISSIONED.
RUNNING STATUS OF THESE DRIVES ARE TO BE MONITORED
CONTINUOUSLY .FAILURE OF RUNNING SHOULD GIVE ALARM OR TRIP
COMMAND AS REQUIRED.
IV HYDROGEN GAS FILLING
VOLUME,PRESSURE OF GAS TO BE MONITORED. FOR LIST OF
MONITORING PARAMETERS,REFER SEC 2.3 OF O & M MANUAL OF GEN.
9. COMPLETION CRETERIA
GENERATOR PARAMETERS ARE STABILISED AND WITHIN THE
ALLOWABLE LIMITS. AVR IS CAPABLE OF GIVING FULL LOAD
EXCITATION CURRENT DURING SHORT CIRCUIT TEST OF GENERATOR &
FOUND STABLE. ALL GENERATOR PARAMETERS ARE NORMAL UNDER
RUNNING CONDITIONS AND STABLE DURING GRID DISTURBANCES.
10. APPENDICES
MANUALS: O & M MANUAL OF GENERATOR,EXCITATION
SYSTEM
DRAWINGS:SCHEMATIC DRAWING OF DAVR,GENERATOR RTDS,
LOG SHEETS :

I)

IR ,WR VALUES OF PILOT AND MAIN


EXCITER

/var/www/apps/conversion/tmp/scratch_7/278935561.doc

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 4 OF 4

PLANT AREA : GENERATOR AUX SYSTEM


TESTING SCHEDULE : STATOR & ROTOR COOLING,EXCITATION,SEAL OIL INITIAL
CIRCULATION & GAS FILLING SYSTEMS

II)
III)
IV)
V)

DAVR TEST
GENERATOR
LIST OF
READINESS

REPORT(SITE)
PARAMETERS(LOCAL)
PROTECTIONS INCLUDED
OF AUX SYSTEMS