Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
15-Oct-14
13-Oct-16
15-Oct-14 A
13-Oct-16
19.13%
21.39%
MAJOR MILEST
MILESTONE
15-Oct-14
13-Oct-16
15-Oct-14 A
13-Oct-16
0%
0%
KEY MILESTONE
MILESTON
25-Jul-15
08-Sep-15
01-Aug-15
09-Sep-15
0%
0%
400
ENGINEERING
08-Apr-15
06-Dec-15
26-Mar-15 A
10-Nov-15
0%
0%
178
08-Apr-15
23-Nov-15
01-Apr-15 A
29-Oct-15
0%
0%
188
ARCHITECTURAL
ARCHITECTU
25-Jul-15
22-Oct-15
25-Jul-15 A
29-Oct-15
0%
0%
188
INTERNAL PAINT
PA
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
53
MATERIAL SUBMITTAL
SU
& APPROVAL
ENG.MS.AR.12
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
53
ENG.MS.AR.19
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
53
10-Aug-15
19-Sep-15
17-Aug-15
01-Oct-15
0%
0%
67
EPOXY PAINT
ENG.MS.AR.15
10-Aug-15
25-Aug-15
17-Aug-15
01-Sep-15
0%
0%
67
ENG.MS.AR.24
26-Aug-15
19-Sep-15
02-Sep-15
01-Oct-15
0%
0%
67
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
127
CARPET MATERIALS
MAT
ENG.MS.AR.40
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
101
ENG.MS.AR.42
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
127
22-Aug-15
06-Oct-15
29-Aug-15
13-Oct-15
0%
0%
150
22-Aug-15
06-Sep-15
29-Aug-15
13-Sep-15
0%
0%
91
ENG.MS.AR.53
07-Sep-15
06-Oct-15
14-Sep-15
13-Oct-15
0%
0%
150
07-Sep-15
22-Oct-15
14-Sep-15
29-Oct-15
0%
0%
146
07-Sep-15
22-Sep-15
14-Sep-15
05-Oct-15
0%
0%
146
ENG.MS.AR.61
29-Sep-15
22-Oct-15
06-Oct-15
29-Oct-15
0%
0%
146
07-Sep-15
22-Oct-15
25-Jul-15 A
18-Oct-15
0%
0%
198
CRUSHED LIMESTONE
LI
ENG.MS.AR.62
07-Sep-15
22-Sep-15
25-Jul-15 A
05-Oct-15
0%
0%
167
ENG.MS.AR.63
29-Sep-15
22-Oct-15
02-Aug-15 A
18-Oct-15
0%
0%
198
07-Sep-15
22-Sep-15
29-Sep-15
15-Oct-15
0%
0%
167
ROAD MARK
MARKING, SIGNAGES & ACCESSORIES
Date: 08-Aug-15 1/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
01-Aug-15
01-Aug-15,
23-Aug-15,
28-Aug-15,
31-Aug-15
09-Sep-15
09-Sep-15,
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
ENG.MS.AR.64
Activity Name
Baseline
Start
Baseline
Finish
07-Sep-15
MEP WORKS
M.V MATERIAL
MATERIA & ACCESSORIES
M.V PANELS
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
22-Sep-15
29-Sep-15
15-Oct-15
0%
0%
167
08-Apr-15
23-Nov-15
01-Apr-15 A
28-Oct-15
0%
0%
168
18-Apr-15
30-Sep-15
23-Apr-15 A
07-Oct-15
0%
0%
88
18-Apr-15
30-Sep-15
23-Apr-15 A
07-Oct-15
0%
0%
88
ENG.MS.MV.1
18-Apr-15
03-May-15
23-Apr-15 A
13-Aug-15
100%
0%
55
ENG.MS.MV.5
06-Aug-15
23-Aug-15
13-Aug-15
30-Aug-15
0%
0%
88
ENG.MS.MV.9
23-Aug-15
08-Sep-15
30-Aug-15
15-Sep-15
0%
0%
88
08-Sep-15
30-Sep-15
15-Sep-15
07-Oct-15
0%
0%
88
05-Jul-15
13-Sep-15
28-Jun-15 A
01-Sep-15
0%
0%
55
05-Jul-15
26-Jul-15
28-Jun-15 A
16-Aug-15
100%
0%
55
ENG.MS.MV.11
11-Aug-15
27-Aug-15
28-Jun-15 A
26-Aug-15
0%
0%
55
ENG.MS.MV.7
26-Jul-15
11-Aug-15
29-Jun-15 A
23-Aug-15
34.29%
0%
55
27-Aug-15
13-Sep-15
29-Jun-15 A
01-Sep-15
0%
0%
55
05-Sep-15
21-Oct-15
15-Jun-15 A
05-Sep-15
0%
0%
99
05-Sep-15
21-Sep-15
15-Jun-15 A
23-Aug-15
0%
0%
99
ENG.MS.AC.16
21-Sep-15
21-Oct-15
22-Jun-15 A
05-Sep-15
0%
0%
99
13-Oct-15
07-Nov-15
28-May-15
A
01-Sep-15
0%
0%
133
13-Oct-15
07-Nov-15
28-May-15
A
01-Sep-15
0%
0%
133
13-Oct-15
23-Nov-15
21-May-15
A
07-Sep-15
0%
0%
146
EXHAUST FAN
FA & ACCESSORIES
ENG.MS.AC.20
CHILLED WATER
WA
PRESSURIZATION UNIT
ENG.MS.AC.27
13-Oct-15
29-Oct-15
21-May-15
A
27-Aug-15
0%
0%
129
ENG.MS.AC.28
29-Oct-15
23-Nov-15
28-May-15
A
07-Sep-15
0%
0%
146
16-Aug-15
01-Oct-15
23-Aug-15
08-Oct-15
0%
0%
129
CHEMICAL DOSING
D
ENG.MS.AC.29
16-Aug-15
01-Sep-15
23-Aug-15
08-Sep-15
0%
0%
129
ENG.MS.AC.30
01-Sep-15
01-Oct-15
08-Sep-15
08-Oct-15
0%
0%
129
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
205
BUILDING MANAGEMENT
MA
SYSTEM
Date: 08-Aug-15 2/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
ENG.MS.AC.31
25-Jul-15
ENG.MS.AC.32
CHILLERS
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
56
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
205
22-Jun-15
05-Aug-15
16-Jun-15 A
31-Aug-15
0%
0%
56
ENG.MS.AC.22
22-Jun-15
07-Jul-15
16-Jun-15 A
22-Aug-15
100%
0%
56
ENG.MS.AC.25
08-Jul-15
05-Aug-15
23-Jun-15 A
31-Aug-15
76.19%
0%
56
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
96
SANITARY W
WARES FITTINGS & ACCESSORIES
ENG.MS.PL.13
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
96
ENG.MS.PL.14
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
96
16-Sep-15
15-Oct-15
14-Jun-15 A
22-Aug-15
0%
0%
112
16-Sep-15
15-Oct-15
14-Jun-15 A
22-Aug-15
0%
0%
112
10-Jun-15
26-Jul-15
27-Jun-15 A
19-Aug-15
0%
0%
101
10-Jun-15
27-Jun-15
27-Jun-15 A
06-Aug-15
100%
0%
101
ENG.MS.EE.29
27-Jun-15
26-Jul-15
04-Jul-15 A
19-Aug-15
100%
0%
101
25-May-15
22-Jul-15
07-May-15
A
19-Aug-15
0%
0%
72
LOW VOLTAGE
VOLTAG CABLE & ACCESSORIES
ENG.MS.EE.5
25-May-15
09-Jun-15
07-May-15
A
06-Aug-15
100%
0%
17
ENG.MS.EE.7
23-Jun-15
22-Jul-15
28-Jun-15 A
19-Aug-15
100%
0%
72
27-Jun-15
02-Sep-15
07-May-15
A
09-Sep-15
0%
0%
53
27-Jun-15
12-Jul-15
07-May-15
A
16-Aug-15
100%
0%
17
ENG.MS.EE.10
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
53
04-Jul-15
02-Aug-15
27-Jun-15 A
05-Sep-15
0%
0%
58
13-Jul-15
02-Aug-15
27-Jun-15 A
23-Aug-15
85.71%
0%
17
ENG.MS.EE.14
04-Jul-15
01-Aug-15
04-Jul-15 A
05-Sep-15
95.24%
0%
58
27-Jul-15
06-Sep-15
27-Jun-15 A
10-Sep-15
0%
0%
53
ACCESS CONTROL
CO
SYSTEM & ACCESSORIES
ENG.MS.EE.15
27-Jul-15
12-Aug-15
27-Jun-15 A
30-Aug-15
24.29%
0%
17
ENG.MS.EE.16
12-Aug-15
06-Sep-15
04-Jul-15 A
10-Sep-15
0%
0%
53
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
12-Aug-15
Schedule %
Complete
Cost %
Complete
Total
Float
22-Sep-15
21-Jun-15 A
17-Sep-15
0%
0%
47
ENG.MS.EE.17
12-Aug-15
29-Aug-15
21-Jun-15 A
05-Sep-15
0%
0%
17
ENG.MS.EE.19
29-Aug-15
22-Sep-15
28-Jun-15 A
17-Sep-15
0%
0%
47
29-Aug-15
14-Oct-15
27-Jun-15 A
29-Sep-15
0%
0%
42
29-Aug-15
14-Sep-15
27-Jun-15 A
12-Sep-15
0%
0%
17
ENG.MS.EE.21
14-Sep-15
14-Oct-15
04-Jul-15 A
29-Sep-15
0%
0%
42
05-Sep-15
21-Oct-15
12-Sep-15
28-Oct-15
0%
0%
17
LIGHT FITTINGS
FITTIN
& ACCESSORIES
ENG.MS.EE.20
05-Sep-15
21-Sep-15
12-Sep-15
04-Oct-15
0%
0%
17
ENG.MS.EE.23
21-Sep-15
21-Oct-15
04-Oct-15
28-Oct-15
0%
0%
17
08-Apr-15
18-May-15
01-Apr-15 A
15-Aug-15
0%
0%
101
FIRE FIGHTING
FIGHTIN VALVES & FITTINGS
ENG.MS.FF.13
08-Apr-15
23-Apr-15
01-Apr-15 A
11-Aug-15
100%
0%
101
ENG.MS.FF.14
25-Apr-15
18-May-15
16-Jun-15 A
15-Aug-15
100%
0%
101
09-Jun-15
16-Jul-15
09-Jun-15 A
19-Aug-15
0%
0%
165
09-Jun-15
24-Jun-15
09-Jun-15 A
06-Aug-15
100%
0%
104
ENG.MS.FF.16
22-Jun-15
16-Jul-15
16-Jun-15 A
19-Aug-15
100%
0%
165
22-Jun-15
06-Aug-15
09-Jun-15 A
25-Aug-15
0%
0%
131
22-Jun-15
08-Jul-15
09-Jun-15 A
13-Aug-15
100%
0%
104
ENG.MS.FF.4
08-Jul-15
06-Aug-15
16-Jun-15 A
25-Aug-15
72.86%
0%
131
08-Jul-15
23-Aug-15
09-Jun-15 A
01-Sep-15
0%
0%
126
FIRE BRIGADE
BRIGAD VALVE & FITTINGS
ENG.MS.FF.5
08-Jul-15
29-Jul-15
09-Jun-15 A
19-Aug-15
100%
0%
104
ENG.MS.FF.6
29-Jul-15
23-Aug-15
16-Jun-15 A
01-Sep-15
6.19%
0%
126
29-Jul-15
08-Sep-15
09-Jun-15 A
07-Sep-15
0%
0%
104
FIRE HOSE R
REEL CABINET & ACCESSORIES
ENG.MS.FF.7
29-Jul-15
15-Aug-15
09-Jun-15 A
26-Aug-15
9.29%
0%
104
ENG.MS.FF.8
15-Aug-15
08-Sep-15
16-Jun-15 A
07-Sep-15
0%
0%
104
08-Sep-15
25-Oct-15
09-Jun-15 A
01-Oct-15
0%
0%
104
FIRE EXTING
EXTINGUISHER
Date: 08-Aug-15 4/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
ENG.MS.FF.9
08-Sep-15
14-Sep-15
0%
0%
104
ENG.MS.FF.10
16-Jun-15 A
01-Oct-15
0%
0%
104
06-Dec-15
02-Apr-15 A
10-Nov-15
0%
0%
146
21-May-15
06-Jul-15
02-Apr-15 A
08-Aug-15
0%
0%
30
21-May-15
06-Jul-15
02-Apr-15 A
08-Aug-15
0%
0%
30
21-May-15
07-Jun-15
02-Apr-15 A
01-Aug-15
100%
0%
30
13-Jun-15
06-Jul-15
30-Jun-15 A
08-Aug-15
100%
0%
30
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
156
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
58
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
58
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
58
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
105
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
105
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
105
03-Sep-15
19-Oct-15
10-Sep-15
26-Oct-15
0%
0%
53
03-Sep-15
19-Sep-15
10-Sep-15
01-Oct-15
0%
0%
53
20-Sep-15
19-Oct-15
03-Oct-15
26-Oct-15
0%
0%
53
20-Sep-15
11-Oct-15
03-Oct-15
18-Oct-15
0%
0%
67
20-Sep-15
11-Oct-15
03-Oct-15
18-Oct-15
0%
0%
67
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
128
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
128
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
128
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
131
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
131
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
131
METHOD STATEMENT
STAT
SUBMITTAL & APPROVAL
STRUCTURAL
STEEL STRUCTURE
STRU
& METAL DECKING
ARCHITECTURAL
ARCHITECTU
WOOD VENEERED
VENE
MDF PANEL
WOOD PARQUET
PARQ
FLOORING
INTERNAL PAINT
PA
EPOXY PAINT
ENG.MSS.AR.10 Method Statement Submittal - Epoxy Paint
PANTRY CABINET
CAB
& BASE CABINET
TOILET CUBICLE
CUB
Start
Finish
30-Sep-15
09-Jun-15 A
30-Sep-15
25-Oct-15
21-May-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
03-Sep-15
26-Oct-15
0%
0%
127
10-Sep-15
01-Oct-15
0%
0%
127
19-Oct-15
03-Oct-15
26-Oct-15
0%
0%
127
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
148
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
148
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
148
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
105
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
105
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
105
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
119
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
127
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
119
25-Jul-15
17-Aug-15
01-Aug-15
24-Aug-15
0%
0%
112
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
112
25-Jul-15
17-Aug-15
01-Aug-15
24-Aug-15
28.57%
0%
112
07-Sep-15
22-Oct-15
14-Sep-15
29-Oct-15
0%
0%
105
07-Sep-15
22-Sep-15
14-Sep-15
05-Oct-15
0%
0%
105
29-Sep-15
22-Oct-15
06-Oct-15
29-Oct-15
0%
0%
105
07-Sep-15
22-Oct-15
14-Sep-15
29-Oct-15
0%
0%
91
07-Sep-15
22-Sep-15
14-Sep-15
05-Oct-15
0%
0%
91
29-Sep-15
22-Oct-15
06-Oct-15
29-Oct-15
0%
0%
91
SOFT LANDSCAPE
LANDS
(PLANT, TREES, SHRUBS, GRAS 07-Sep-15 22-Oct-15
14-Sep-15
29-Oct-15
0%
0%
156
CARPET
WOODEN DO
DOORS INCLUDING SUBFRAMES & ARC
IRON MONGERY
MONG
STEEL DOORS
DOOR INCLUDING SUBFRAMES & ARCHIT
GRC WORKS
Start
Finish
19-Oct-15
10-Sep-15
03-Sep-15
19-Sep-15
20-Sep-15
07-Sep-15
22-Sep-15
14-Sep-15
05-Oct-15
0%
0%
156
29-Sep-15
22-Oct-15
06-Oct-15
29-Oct-15
0%
0%
156
29-Aug-15
06-Dec-15
01-Jun-15 A
10-Nov-15
0%
0%
86
MEP WORKS
Date: 08-Aug-15 6/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
20-Sep-15
21-Oct-15
0%
0%
104
16-Jul-15 A
08-Oct-15
0%
0%
104
04-Nov-15
30-Jul-15 A
21-Oct-15
0%
0%
104
29-Aug-15
14-Oct-15
16-Jul-15 A
29-Sep-15
0%
0%
123
29-Aug-15
14-Sep-15
16-Jul-15 A
10-Sep-15
0%
0%
123
14-Sep-15
14-Oct-15
30-Jul-15 A
29-Sep-15
0%
0%
123
19-Nov-15
06-Dec-15
01-Jun-15 A
10-Nov-15
0%
0%
17
19-Nov-15
06-Dec-15
01-Jun-15 A
10-Nov-15
0%
0%
17
11-Apr-15
02-Dec-15
26-Mar-15 A
26-Oct-15
0%
0%
175
11-Apr-15
28-Jul-15
11-Apr-15 A
20-Aug-15
0%
0%
20
11-Apr-15
27-Jul-15
11-Apr-15 A
20-Aug-15
0%
0%
17
11-Apr-15
02-Jul-15
11-Apr-15 A
03-Aug-15
0%
0%
32
FIRE FIGHTIN
FIGHTING WORKS
HVAC WORKS
WORK
ELECTRICAL WORKS
ENG.MSS.MEP.9 Method Statement Submittal - Electrical Works
SHOP DRAWING
DRAWIN SUBMITTAL & APPROVAL
STRUCTURAL
STRUCTURAL LAYOUT & DETAILS
STRUCTURA
WALL DETAILS 1-3 (BUILDING-2)
Start
Finish
04-Nov-15
16-Jul-15 A
20-Sep-15
11-Oct-15
12-Oct-15
ENG.SD.ST.28
11-Apr-15
26-Apr-15
11-Apr-15 A
01-Aug-15
100%
0%
17
ENG.SD.ST.36
08-Jun-15
02-Jul-15
25-Jun-15 A
03-Aug-15
100%
0%
32
31-May-15
06-Jul-15
16-May-15
A
04-Aug-15
0%
0%
31
31-May-15
16-Jun-15
16-May-15
A
02-Aug-15
100%
0%
17
ENG.SD.ST.46
11-Jun-15
06-Jul-15
25-Jun-15 A
04-Aug-15
100%
0%
31
08-Jun-15
14-Jul-15
16-May-15
A
12-Aug-15
0%
0%
24
08-Jun-15
24-Jun-15
16-May-15
A
10-Aug-15
100%
0%
17
ENG.SD.ST.55
20-Jun-15
14-Jul-15
25-Jun-15 A
12-Aug-15
100%
0%
24
16-Jun-15
27-Jul-15
16-May-15
A
20-Aug-15
0%
0%
17
16-Jun-15
02-Jul-15
16-May-15
A
18-Aug-15
100%
0%
17
ENG.SD.ST.58
28-Jun-15
27-Jul-15
25-Jun-15 A
20-Aug-15
100%
0%
17
29-Jun-15
28-Jul-15
08-Jun-15 A
02-Aug-15
0%
0%
37
29-Jun-15
28-Jul-15
08-Jun-15 A
02-Aug-15
100%
0%
37
STEEL STRUCTURE
STRU
& METAL DECKING
ENG.SD.ST.57
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
ARCHITECTURAL
ARCHITECTU
BLOCKWORK & OTHER ARCHITECTURAL
BLOCKWOR
BUILDING SEC
SECTION (BUILDING-1)
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
11-Jul-15
19-Oct-15
19-May-15
A
26-Oct-15
0%
0%
130
25-Jul-15
25-Aug-15
26-Jul-15 A
30-Aug-15
0%
0%
120
25-Jul-15
25-Aug-15
26-Jul-15 A
30-Aug-15
0%
0%
120
ENG.SD.AR.34
25-Jul-15
09-Aug-15
26-Jul-15 A
13-Aug-15
42.86%
0%
120
ENG.SD.AR.37
10-Aug-15
25-Aug-15
13-Aug-15
30-Aug-15
0%
0%
120
03-Sep-15
19-Oct-15
10-Sep-15
26-Oct-15
0%
0%
58
WOOD VENEERED
VENE
MDF PANEL
ENG.SD.AR.51
03-Sep-15
19-Sep-15
10-Sep-15
01-Oct-15
0%
0%
58
ENG.SD.AR.55
20-Sep-15
19-Oct-15
03-Oct-15
26-Oct-15
0%
0%
58
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
120
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
120
ENG.SD.AR.57
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
120
11-Jul-15
25-Aug-15
19-May-15
A
19-Aug-15
0%
0%
125
600x600 PER
PERFORATED METAL PAN CEILING
ENG.SD.AR.56
11-Jul-15
01-Aug-15
19-May-15
A
06-Aug-15
96.29%
0%
125
ENG.SD.AR.61
01-Aug-15
25-Aug-15
26-May-15
A
19-Aug-15
0%
0%
125
11-Jul-15
25-Aug-15
19-May-15
A
19-Aug-15
0%
0%
184
11-Jul-15
01-Aug-15
19-May-15
A
06-Aug-15
96.29%
0%
184
ENG.SD.AR.64
01-Aug-15
25-Aug-15
26-May-15
A
19-Aug-15
0%
0%
184
09-Aug-15
19-Sep-15
19-May-15
A
19-Aug-15
0%
0%
145
09-Aug-15
25-Aug-15
19-May-15
A
06-Aug-15
0%
0%
145
ENG.SD.AR.66
25-Aug-15
19-Sep-15
26-May-15
A
19-Aug-15
0%
0%
145
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
105
WOOD PARQUET
PARQ
FLOORING
ENG.SD.AR.67
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
105
ENG.SD.AR.70
10-Aug-15
02-Sep-15
17-Aug-15
09-Sep-15
0%
0%
105
25-Jul-15
02-Sep-15
01-Aug-15
09-Sep-15
0%
0%
105
25-Jul-15
09-Aug-15
01-Aug-15
16-Aug-15
42.86%
0%
105
WOODEN DO
DOORS INCLUDING SUBFRAMES & ARC
ENG.SD.AR.79
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Schedule %
Complete
Cost %
Complete
Total
Float
09-Sep-15
0%
0%
105
26-Mar-15 A
26-Oct-15
0%
0%
175
29-Aug-15
10-Jun-15 A
25-Aug-15
0%
0%
170
28-Jun-15
12-Aug-15
10-Jun-15 A
19-Aug-15
0%
0%
176
28-Jun-15
14-Jul-15
10-Jun-15 A
06-Aug-15
100%
0%
119
14-Jul-15
12-Aug-15
17-Jun-15 A
19-Aug-15
49.52%
0%
176
14-Jul-15
29-Aug-15
10-Jun-15 A
25-Aug-15
0%
0%
170
14-Jul-15
04-Aug-15
10-Jun-15 A
13-Aug-15
74.29%
0%
119
04-Aug-15
29-Aug-15
17-Jun-15 A
25-Aug-15
0%
0%
170
15-Jun-15
15-Jul-15
15-Jun-15 A
19-Aug-15
0%
0%
115
ENG.SD.AR.81
Activity Name
Baseline
Start
Baseline
Finish
10-Aug-15
MEP WORKS
DRAINAGE SHOP
S
DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)
Start
Finish
02-Sep-15
17-Aug-15
09-May-15
02-Dec-15
15-Jun-15
ENG.SD.DR.8
15-Jun-15
30-Jun-15
15-Jun-15 A
06-Aug-15
100%
0%
109
ENG.SD.DR.11
22-Jun-15
15-Jul-15
22-Jun-15 A
19-Aug-15
100%
0%
115
22-Jun-15
05-Aug-15
15-Jun-15 A
25-Aug-15
0%
0%
109
22-Jun-15
07-Jul-15
15-Jun-15 A
13-Aug-15
100%
0%
109
08-Jul-15
05-Aug-15
22-Jun-15 A
25-Aug-15
76.19%
0%
109
09-May-15
03-Aug-15
09-May-15
A
25-Aug-15
0%
0%
137
06-Jun-15
15-Jul-15
29-Jun-15 A
19-Aug-15
0%
0%
143
06-Jun-15
21-Jun-15
29-Jun-15 A
06-Aug-15
100%
0%
143
22-Jun-15
15-Jul-15
05-Jul-15 A
19-Aug-15
100%
0%
143
09-May-15
13-Jul-15
09-May-15
A
19-Aug-15
0%
0%
90
WATER SUPPLY
SUPP SHOP DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)
GROUND FLOOR
FLOO LEVEL (BUILDING-2)
ENG.SD.WS.4
09-May-15
24-May-15
09-May-15
A
06-Aug-15
100%
0%
90
ENG.SD.WS.7
18-Jun-15
13-Jul-15
17-Jun-15 A
19-Aug-15
100%
0%
90
04-Jul-15
03-Aug-15
04-Jul-15 A
25-Aug-15
0%
0%
109
04-Jul-15
23-Jul-15
04-Jul-15 A
13-Aug-15
100%
0%
109
05-Jul-15
03-Aug-15
11-Jul-15 A
25-Aug-15
89.52%
0%
109
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
POWER SHOP
SHO DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)
Baseline
Start
Baseline
Finish
Start
Finish
09-May-15
Schedule %
Complete
Cost %
Complete
Total
Float
01-Oct-15
04-Jun-15 A
08-Oct-15
0%
0%
45
08-Jul-15
22-Aug-15
18-Jul-15 A
19-Aug-15
0%
0%
84
ENG.SD.PO.15
08-Jul-15
28-Jul-15
18-Jul-15 A
06-Aug-15
100%
0%
78
ENG.SD.PO.18
29-Jul-15
22-Aug-15
25-Jul-15 A
19-Aug-15
9.52%
0%
84
29-Jul-15
07-Sep-15
18-Jul-15 A
25-Aug-15
0%
0%
78
29-Jul-15
13-Aug-15
18-Jul-15 A
13-Aug-15
14.29%
0%
78
ENG.SD.PO.21
15-Aug-15
07-Sep-15
25-Jul-15 A
25-Aug-15
0%
0%
78
09-May-15
14-Jul-15
04-Jun-15 A
19-Aug-15
0%
0%
73
GROUND FLOOR
FLOO LEVEL (BUILDING-2)
ENG.SD.PO.4
09-May-15
24-May-15
04-Jun-15 A
06-Aug-15
100%
0%
45
ENG.SD.PO.7
20-Jun-15
14-Jul-15
11-Jun-15 A
19-Aug-15
100%
0%
73
30-Jul-15
09-Sep-15
06-Aug-15
16-Sep-15
0%
0%
59
30-Jul-15
16-Aug-15
06-Aug-15
23-Aug-15
2.86%
0%
45
ENG.SD.PO.11
16-Aug-15
09-Sep-15
23-Aug-15
16-Sep-15
0%
0%
59
16-Aug-15
01-Oct-15
23-Aug-15
08-Oct-15
0%
0%
45
16-Aug-15
01-Sep-15
23-Aug-15
08-Sep-15
0%
0%
45
ENG.SD.PO.16
01-Sep-15
01-Oct-15
08-Sep-15
08-Oct-15
0%
0%
45
09-May-15
04-Aug-15
08-Jun-15 A
25-Aug-15
0%
0%
120
09-May-15
14-Jul-15
15-Jul-15 A
19-Aug-15
0%
0%
75
LIGHTING SH
SHOP DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)
ENG.SD.LI.15
09-May-15
24-May-15
15-Jul-15 A
06-Aug-15
100%
0%
69
ENG.SD.LI.18
20-Jun-15
14-Jul-15
22-Jul-15 A
19-Aug-15
100%
0%
75
20-Jun-15
04-Aug-15
15-Jul-15 A
25-Aug-15
0%
0%
69
20-Jun-15
06-Jul-15
15-Jul-15 A
13-Aug-15
100%
0%
69
ENG.SD.LI.21
06-Jul-15
04-Aug-15
22-Jul-15 A
25-Aug-15
82.86%
0%
69
09-May-15
14-Jul-15
08-Jun-15 A
19-Aug-15
0%
0%
115
09-May-15
24-May-15
08-Jun-15 A
06-Aug-15
100%
0%
115
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
ENG.SD.LI.11
Activity Name
Baseline
Start
Baseline
Finish
20-Jun-15
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
14-Jul-15
15-Jun-15 A
19-Aug-15
100%
0%
115
20-Jun-15
04-Aug-15
08-Jun-15 A
25-Aug-15
0%
0%
120
ENG.SD.LI.12
20-Jun-15
06-Jul-15
08-Jun-15 A
13-Aug-15
100%
0%
120
ENG.SD.LI.16
06-Jul-15
04-Aug-15
15-Jun-15 A
25-Aug-15
82.86%
0%
120
06-Jun-15
18-Oct-15
07-Jul-15 A
25-Oct-15
0%
0%
176
06-Jun-15
15-Jul-15
07-Jul-15 A
19-Aug-15
0%
0%
75
21-Jun-15
07-Jul-15 A
06-Aug-15
100%
0%
35
15-Jul-15
14-Jul-15 A
19-Aug-15
100%
0%
75
05-Aug-15
07-Jul-15 A
25-Aug-15
0%
0%
95
07-Jul-15
07-Jul-15 A
13-Aug-15
100%
0%
75
05-Aug-15
14-Jul-15 A
25-Aug-15
76.19%
0%
95
06-Aug-15
16-Sep-15
13-Aug-15
29-Sep-15
0%
0%
84
23-Aug-15
13-Aug-15
30-Aug-15
0%
0%
75
16-Sep-15
30-Aug-15
29-Sep-15
0%
0%
84
08-Oct-15
30-Aug-15
15-Oct-15
0%
0%
75
08-Sep-15
30-Aug-15
15-Sep-15
0%
0%
75
08-Oct-15
15-Sep-15
15-Oct-15
0%
0%
75
30-Sep-15
17-Oct-15
07-Oct-15
24-Oct-15
0%
0%
142
17-Oct-15
07-Oct-15
24-Oct-15
0%
0%
142
08-Sep-15
30-Sep-15
15-Sep-15
07-Oct-15
0%
0%
98
30-Sep-15
15-Sep-15
07-Oct-15
0%
0%
98
30-Jul-15
09-Sep-15
06-Aug-15
16-Sep-15
0%
0%
69
16-Aug-15
06-Aug-15
23-Aug-15
2.86%
0%
69
09-Sep-15
23-Aug-15
16-Sep-15
0%
0%
69
01-Oct-15
23-Aug-15
08-Oct-15
0%
0%
76
22-Jun-15
SECOND FLOO
FLOOR LEVEL (BUILDING-1)
23-Aug-15
GROUND FLOOR
FLOO LEVEL (BUILDING-2)
16-Aug-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
01-Sep-15
23-Aug-15
08-Sep-15
0%
0%
76
01-Oct-15
08-Sep-15
08-Oct-15
0%
0%
76
01-Sep-15
18-Oct-15
08-Sep-15
25-Oct-15
0%
0%
176
17-Sep-15
08-Sep-15
30-Sep-15
0%
0%
162
18-Oct-15
30-Sep-15
25-Oct-15
0%
0%
176
17-Sep-15
10-Oct-15
30-Sep-15
17-Oct-15
0%
0%
162
10-Oct-15
30-Sep-15
17-Oct-15
0%
0%
162
02-Dec-15
07-Jul-15 A
21-Oct-15
0%
0%
107
22-Jun-15
05-Aug-15
07-Jul-15 A
13-Aug-15
0%
0%
71
DRAWING DETAILS
DET
(BUILDING-2)
GROUND FLOOR
FLOO LEVEL (BUILDING-1)
ENG.SD.TEL.1
22-Jun-15
07-Jul-15
07-Jul-15 A
08-Aug-15
100%
0%
35
ENG.SD.TEL.3
08-Jul-15
05-Aug-15
14-Jul-15 A
13-Aug-15
76.19%
0%
71
08-Jul-15
22-Aug-15
07-Jul-15 A
15-Aug-15
0%
0%
104
08-Jul-15
28-Jul-15
07-Jul-15 A
10-Aug-15
100%
0%
104
ENG.SD.TEL.5
29-Jul-15
22-Aug-15
14-Jul-15 A
15-Aug-15
9.52%
0%
104
12-Aug-15
22-Sep-15
20-Jul-15 A
29-Aug-15
0%
0%
105
SECOND FLOO
FLOOR LEVEL (BUILDING-1)
ENG.SD.TEL.6
12-Aug-15
29-Aug-15
20-Jul-15 A
16-Aug-15
0%
0%
105
ENG.SD.TEL.9
29-Aug-15
22-Sep-15
03-Aug-15 A 29-Aug-15
0%
0%
105
29-Aug-15
14-Oct-15
20-Jul-15 A
05-Sep-15
0%
0%
105
29-Aug-15
14-Sep-15
20-Jul-15 A
23-Aug-15
0%
0%
105
14-Sep-15
14-Oct-15
03-Aug-15 A 05-Sep-15
0%
0%
105
14-Sep-15
31-Oct-15
20-Jul-15 A
10-Sep-15
0%
0%
137
14-Sep-15
06-Oct-15
20-Jul-15 A
30-Aug-15
0%
0%
107
06-Oct-15
31-Oct-15
03-Aug-15 A 10-Sep-15
0%
0%
137
06-Oct-15
16-Nov-15
20-Jul-15 A
17-Sep-15
0%
0%
131
06-Oct-15
22-Oct-15
20-Jul-15 A
05-Sep-15
0%
0%
107
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
22-Oct-15
16-Nov-15
22-Oct-15
02-Dec-15
05-Sep-15
22-Oct-15
08-Nov-15
08-Nov-15
DRAWING DETAILS
DET
(BUILDING-1)
GROUND FLOOR
FLOO LEVEL (BUILDING-2)
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
0%
0%
131
21-Oct-15
0%
0%
107
05-Sep-15
21-Sep-15
0%
0%
107
02-Dec-15
21-Sep-15
21-Oct-15
0%
0%
107
06-Aug-15
16-Sep-15
20-Jul-15 A
27-Aug-15
0%
0%
87
03-Aug-15 A 17-Sep-15
ENG.SD.TEL.4
06-Aug-15
23-Aug-15
20-Jul-15 A
15-Aug-15
0%
0%
87
ENG.SD.TEL.7
23-Aug-15
16-Sep-15
03-Aug-15 A 27-Aug-15
0%
0%
87
23-Aug-15
08-Oct-15
20-Jul-15 A
02-Sep-15
0%
0%
102
23-Aug-15
08-Sep-15
20-Jul-15 A
22-Aug-15
0%
0%
96
08-Sep-15
08-Oct-15
03-Aug-15 A 02-Sep-15
0%
0%
102
08-Sep-15
25-Oct-15
20-Jul-15 A
09-Sep-15
0%
0%
96
08-Sep-15
30-Sep-15
20-Jul-15 A
27-Aug-15
0%
0%
96
30-Sep-15
25-Oct-15
03-Aug-15 A 09-Sep-15
0%
0%
96
30-Sep-15
10-Nov-15
27-Aug-15
13-Oct-15
0%
0%
114
30-Sep-15
17-Oct-15
27-Aug-15
13-Sep-15
0%
0%
114
17-Oct-15
10-Nov-15
13-Sep-15
13-Oct-15
0%
0%
114
06-Aug-15
31-Oct-15
09-Aug-15
26-Oct-15
0%
0%
55
12-Aug-15
22-Sep-15
09-Aug-15
17-Sep-15
0%
0%
83
DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.FA.10
12-Aug-15
29-Aug-15
09-Aug-15
24-Aug-15
0%
0%
55
ENG.SD.FA.13
29-Aug-15
22-Sep-15
25-Aug-15
17-Sep-15
0%
0%
83
29-Aug-15
14-Oct-15
25-Aug-15
10-Oct-15
0%
0%
69
29-Aug-15
14-Sep-15
25-Aug-15
09-Sep-15
0%
0%
55
ENG.SD.FA.18
14-Sep-15
14-Oct-15
10-Sep-15
10-Oct-15
0%
0%
69
14-Sep-15
31-Oct-15
10-Sep-15
26-Oct-15
0%
0%
55
14-Sep-15
06-Oct-15
10-Sep-15
01-Oct-15
0%
0%
55
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
ENG.SD.FA.21
Activity Name
Baseline
Start
Baseline
Finish
06-Oct-15
GROUND FLOOR
FLOO LEVEL (BUILDING-2)
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
31-Oct-15
03-Oct-15
26-Oct-15
0%
0%
55
06-Aug-15
16-Sep-15
09-Aug-15
17-Sep-15
0%
0%
68
ENG.SD.FA.4
06-Aug-15
23-Aug-15
09-Aug-15
24-Aug-15
0%
0%
41
ENG.SD.FA.7
23-Aug-15
16-Sep-15
25-Aug-15
17-Sep-15
0%
0%
68
23-Aug-15
08-Oct-15
25-Aug-15
10-Oct-15
0%
0%
69
23-Aug-15
08-Sep-15
25-Aug-15
09-Sep-15
0%
0%
41
ENG.SD.FA.11
08-Sep-15
08-Oct-15
10-Sep-15
10-Oct-15
0%
0%
69
08-Sep-15
25-Oct-15
10-Sep-15
26-Oct-15
0%
0%
55
08-Sep-15
30-Sep-15
10-Sep-15
01-Oct-15
0%
0%
41
ENG.SD.FA.16
30-Sep-15
25-Oct-15
03-Oct-15
26-Oct-15
0%
0%
55
30-Sep-15
17-Oct-15
03-Oct-15
18-Oct-15
0%
0%
41
30-Sep-15
17-Oct-15
03-Oct-15
18-Oct-15
0%
0%
41
28-May-15
07-Nov-15
26-Mar-15 A
07-Oct-15
0%
0%
71
03-Jun-15
28-Jun-15
26-Mar-15 A
12-Aug-15
0%
0%
103
03-Jun-15
28-Jun-15
26-Mar-15 A
12-Aug-15
100%
0%
103
10-Jun-15
25-Jul-15
27-Apr-15 A
27-Aug-15
0%
0%
91
DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.FA.14
FIRE FIGHTIN
FIGHTING SHOP DRAWINGS
FIRST FLOOR LEVEL (BUILDING-1)
ENG.SD.FF.5
SECOND FLOO
FLOOR LEVEL (BUILDING-1)
ENG.SD.FF.6
10-Jun-15
25-Jun-15
27-Apr-15 A
15-Aug-15
100%
0%
79
ENG.SD.FF.9
27-Jun-15
25-Jul-15
28-Apr-15 A
27-Aug-15
100%
0%
91
27-Jun-15
18-Aug-15
27-Apr-15 A
08-Sep-15
0%
0%
91
27-Jun-15
12-Jul-15
27-Apr-15 A
22-Aug-15
100%
0%
79
ENG.SD.FF.16
26-Jul-15
18-Aug-15
28-Apr-15 A
08-Sep-15
23.81%
0%
91
26-Jul-15
05-Sep-15
09-Jun-15 A
09-Sep-15
0%
0%
90
26-Jul-15
11-Aug-15
09-Jun-15 A
27-Aug-15
34.29%
0%
79
ENG.SD.FF.18
11-Aug-15
05-Sep-15
16-Jun-15 A
09-Sep-15
0%
0%
90
11-Aug-15
21-Sep-15
09-Jun-15 A
15-Sep-15
0%
0%
84
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
ENG.SD.FF.19
11-Aug-15
ENG.SD.FF.21
DRAWING DETAILS
DET
(BUILDING-1)
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
27-Aug-15
09-Jun-15 A
03-Sep-15
0%
0%
79
27-Aug-15
21-Sep-15
16-Jun-15 A
15-Sep-15
0%
0%
84
21-Sep-15
07-Nov-15
23-Jul-15 A
07-Oct-15
0%
0%
71
ENG.SD.FF.20
21-Sep-15
13-Oct-15
23-Jul-15 A
09-Sep-15
0%
0%
79
ENG.SD.FF.22
13-Oct-15
07-Nov-15
30-Jul-15 A
07-Oct-15
0%
0%
71
28-May-15
22-Jun-15
06-Apr-15 A
11-Aug-15
0%
0%
115
28-May-15
22-Jun-15
06-Apr-15 A
11-Aug-15
100%
0%
115
08-Jul-15
22-Aug-15
09-Jun-15 A
27-Aug-15
0%
0%
101
GROUND FLOOR
FLOO LEVEL (BUILDING-2)
ENG.SD.FF.7
08-Jul-15
28-Jul-15
09-Jun-15 A
15-Aug-15
100%
0%
71
ENG.SD.FF.11
29-Jul-15
22-Aug-15
16-Jun-15 A
27-Aug-15
9.52%
0%
101
29-Jul-15
07-Sep-15
09-Jun-15 A
02-Sep-15
0%
0%
95
29-Jul-15
13-Aug-15
09-Jun-15 A
22-Aug-15
14.29%
0%
71
ENG.SD.FF.15
15-Aug-15
07-Sep-15
16-Jun-15 A
02-Sep-15
0%
0%
95
19-Aug-15
05-Oct-15
22-Aug-15
07-Oct-15
0%
0%
71
DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.FF.13
19-Aug-15
05-Sep-15
22-Aug-15
07-Sep-15
0%
0%
71
ENG.SD.FF.17
05-Sep-15
05-Oct-15
07-Sep-15
07-Oct-15
0%
0%
71
08-Jul-15
29-Sep-15
16-Jun-15 A
30-Sep-15
0%
0%
35
08-Jul-15
22-Aug-15
27-Jun-15 A
27-Aug-15
0%
0%
60
08-Jul-15
28-Jul-15
27-Jun-15 A
15-Aug-15
100%
0%
48
ENG.SD.AC.18
29-Jul-15
22-Aug-15
04-Jul-15 A
27-Aug-15
9.52%
0%
60
29-Jul-15
07-Sep-15
27-Jun-15 A
02-Sep-15
0%
0%
54
29-Jul-15
13-Aug-15
27-Jun-15 A
22-Aug-15
14.29%
0%
48
ENG.SD.AC.21
15-Aug-15
07-Sep-15
04-Jul-15 A
02-Sep-15
0%
0%
54
15-Aug-15
29-Sep-15
16-Jun-15 A
09-Sep-15
0%
0%
48
15-Aug-15
30-Aug-15
16-Jun-15 A
27-Aug-15
0%
0%
48
DRAWING DETAILS
DET
(BUILDING-1)
ENG.SD.AC.20
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
ENG.SD.AC.22
Activity Name
Baseline
Start
Baseline
Finish
31-Aug-15
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
29-Sep-15
23-Jun-15 A
09-Sep-15
0%
0%
48
08-Jul-15
22-Aug-15
22-Jun-15 A
27-Aug-15
0%
0%
60
ENG.SD.AC.8
08-Jul-15
28-Jul-15
22-Jun-15 A
15-Aug-15
100%
0%
35
ENG.SD.AC.11
29-Jul-15
22-Aug-15
29-Jun-15 A
27-Aug-15
9.52%
0%
60
12-Aug-15
22-Sep-15
15-Aug-15
30-Sep-15
0%
0%
35
12-Aug-15
29-Aug-15
15-Aug-15
31-Aug-15
0%
0%
35
ENG.SD.AC.16
29-Aug-15
22-Sep-15
31-Aug-15
30-Sep-15
0%
0%
35
15-Aug-15
29-Sep-15
22-Jun-15 A
30-Sep-15
0%
0%
35
DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.AC.14
15-Aug-15
30-Aug-15
22-Jun-15 A
07-Sep-15
0%
0%
40
ENG.SD.AC.17
31-Aug-15
29-Sep-15
29-Jun-15 A
30-Sep-15
0%
0%
35
06-Jun-15
07-Nov-15
28-May-15
A
29-Oct-15
0%
0%
238
25-Jul-15
21-Aug-15
01-Aug-15
28-Aug-15
0%
0%
111
25-Jul-15
21-Aug-15
01-Aug-15
28-Aug-15
0%
0%
111
25-Jul-15
21-Aug-15
01-Aug-15
28-Aug-15
0%
0%
111
PROCUREMENT
SUBCONTRACTOR/SUPPLIER PREQUALIFICATION
SUBCONTRAC
ARCHITECTURAL
ARCHITECTU
MIRRORS
PRO.SS.AR.21
25-Jul-15
07-Aug-15
01-Aug-15
14-Aug-15
50%
0%
111
PRO.SS.AR.22
08-Aug-15
21-Aug-15
15-Aug-15
28-Aug-15
0%
0%
111
06-Jun-15
07-Nov-15
28-May-15
A
29-Oct-15
0%
0%
238
07-Jul-15
22-Oct-15
28-May-15
A
29-Oct-15
0%
0%
151
07-Jul-15
30-Sep-15
28-May-15
A
07-Oct-15
0%
0%
35
07-Jul-15
30-Sep-15
28-May-15
A
07-Oct-15
0%
0%
35
07-Jul-15
19-Sep-15
28-May-15
A
07-Oct-15
33.33%
0%
35
07-Oct-15
0%
0%
35
MANUFACTURE/PURCHASE/DELIVERY
MANUFACTUR
LONG LEAD ITEMS
I
STRUCTURAL
STEEL STRUC
STRUCTURE & METAL DECKING
PRO.PD.ST.20
PRO.PD.ST.32
ARCHITECTURAL
ARCHITECTU
WOOD PARQUET
PARQU
FLOORING
PRO.PD.AR.012 Manufacture & Delivery Period - Wood Parquet
Flooring
Date: 08-Aug-15 16/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
30-Sep-15
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
151
10-Aug-15
18-Oct-15
17-Aug-15
25-Oct-15
0%
0%
128
10-Aug-15
18-Oct-15
17-Aug-15
25-Oct-15
0%
0%
128
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
07-Oct-15, , 07-Oct-15
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
18-Oct-15
PRO.PD.AR.03
PRO.PD.AR.04
Cost %
Complete
Total
Float
25-Oct-15
0%
0%
128
01-Aug-15
29-Sep-15
0%
0%
125
25-Jul-15
22-Sep-15
01-Aug-15
29-Sep-15
11.67%
0%
125
29-Sep-15
0%
0%
125
22-Sep-15
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
112
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
7.78%
0%
112
29-Oct-15
0%
0%
112
22-Oct-15
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
140
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
7.78%
0%
140
29-Oct-15
0%
0%
140
PANTRY CABINET
CABIN
& BASE CABINET
Schedule %
Complete
22-Sep-15
MOSAIC TILES
Finish
25-Jul-15
MARBLE TILES
Start
22-Oct-15
10-Aug-15
18-Oct-15
17-Aug-15
25-Oct-15
0%
0%
155
10-Aug-15
18-Oct-15
17-Aug-15
25-Oct-15
0%
0%
155
25-Oct-15
0%
0%
155
18-Oct-15
06-Jun-15
07-Nov-15
06-Jun-15 A
29-Oct-15
0%
0%
238
06-Jun-15
22-Oct-15
06-Jun-15 A
29-Oct-15
0%
0%
122
WATER PROO
PROOFING WORKS
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
122
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
79
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
7.78%
0%
79
29-Oct-15
0%
0%
79
22-Oct-15
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
0%
0%
122
25-Jul-15
22-Oct-15
01-Aug-15
29-Oct-15
7.78%
0%
122
29-Oct-15
0%
0%
122
REINFORCING STEEL
THIRD FLOOR ((BUILDING-1)
22-Oct-15
06-Jun-15
07-Sep-15
06-Jun-15 A
14-Sep-15
0%
0%
110
06-Jun-15
15-Aug-15
06-Jun-15 A
22-Aug-15
0%
0%
38
05-Jul-15
06-Jun-15 A
15-Aug-15
100%
0%
38
PRO.PD.ST.24 Manufacture & Delivery Period - Third Floor Slab & 06-Jun-15
Verticals
Date: 08-Aug-15 17/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
25-Oct-15, , 25-Oct-15
29-Sep-15, , 29-Sep-15
29-Oct-15, , 29-Oct-15
29-Oct-15, , 29-Oct-15
25-Oct-15, , 25-Oct-15
29-Oct-15, , 29-Oct-15
29-Oct-15, , 29-Oct-15
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
15-Aug-15
16-Aug-15
22-Aug-15
0%
0%
38
25-Jul-15
30-Aug-15
01-Aug-15
06-Sep-15
0%
0%
58
PRO.PD.ST.27 Manufacture & Delivery Period - Roof Floor Slab & 25-Jul-15
Verticals
23-Aug-15
01-Aug-15
30-Aug-15
23.33%
0%
58
24-Aug-15
30-Aug-15
31-Aug-15
06-Sep-15
0%
0%
58
25-Jul-15
30-Aug-15
01-Aug-15
06-Sep-15
0%
0%
104
25-Jul-15
23-Aug-15
01-Aug-15
30-Aug-15
23.33%
0%
104
24-Aug-15
30-Aug-15
31-Aug-15
06-Sep-15
0%
0%
104
25-Jul-15
07-Sep-15
01-Aug-15
14-Sep-15
0%
0%
23
PRO.PD.ST.17 Manufacture & Delivery Period - Roof Floor Slab & 25-Jul-15
Verticals
23-Aug-15
01-Aug-15
30-Aug-15
23.33%
0%
23
24-Aug-15
07-Sep-15
31-Aug-15
14-Sep-15
0%
0%
23
25-Jul-15
07-Sep-15
01-Aug-15
14-Sep-15
0%
0%
110
25-Jul-15
07-Sep-15
01-Aug-15
14-Sep-15
15.56%
0%
110
14-Sep-15
0%
0%
110
UPPER ROOF F
FLOOR (BUILDING-1)
UPPER ROOF F
FLOOR (BUILDING-2)
Baseline
Start
Baseline
Finish
09-Aug-15
ARCHITECTURAL
ARCHITECTU
INTERNAL PAINT
PAI
PRO.PD.AR.1
PRO.PD.AR.5
PRO.PD.AR.37
07-Sep-15
12-Aug-15
19-Oct-15
19-Aug-15
26-Oct-15
0%
0%
197
20-Sep-15
19-Oct-15
27-Sep-15
26-Oct-15
0%
0%
62
20-Sep-15
19-Oct-15
27-Sep-15
26-Oct-15
0%
0%
62
26-Oct-15
0%
0%
62
19-Oct-15
12-Aug-15
26-Sep-15
19-Aug-15
03-Oct-15
0%
0%
221
12-Aug-15
26-Sep-15
19-Aug-15
03-Oct-15
0%
0%
221
03-Oct-15
0%
0%
221
26-Sep-15
25-Jul-15
07-Nov-15
01-Aug-15
24-Oct-15
0%
0%
243
ELECTRICAL M
MATERIALS
25-Jul-15
02-Oct-15
01-Aug-15
03-Oct-15
0%
0%
159
25-Jul-15
07-Sep-15
01-Aug-15
14-Sep-15
0%
0%
130
25-Jul-15
07-Sep-15
01-Aug-15
14-Sep-15
15.56%
0%
130
14-Sep-15
0%
0%
130
MEP WORKS
PRO.PD.EE.3
PRO.PD.EE.6
07-Sep-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
14-Sep-15, , 14-Sep-15
26-Oct-15, , 26-Oct-15
03-Oct-15, , 03-Oct-15
14-Sep-15, , 14-Sep-15
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
LOW VOLTAGE CABLE
PRO.PD.EE.8
Baseline
Start
Baseline
Finish
18-Aug-15
18-Aug-15
Start
Finish
02-Oct-15
19-Aug-15
02-Oct-15
19-Aug-15
02-Oct-15
Schedule %
Complete
Cost %
Complete
Total
Float
03-Oct-15
0%
0%
159
03-Oct-15
0%
0%
159
03-Oct-15
0%
0%
159
18-Aug-15
02-Oct-15
19-Aug-15
03-Oct-15
0%
0%
100
PRO.PD.EE.2
02-Oct-15
19-Aug-15
03-Oct-15
0%
0%
100
PRO.PD.EE.5
02-Oct-15
03-Oct-15
0%
0%
100
08-Oct-15
07-Nov-15
07-Sep-15
07-Oct-15
0%
0%
160
SPRINKLER PIPES
PIP
& FITTINGS
08-Oct-15
07-Nov-15
07-Sep-15
07-Oct-15
0%
0%
160
PRO.PD.FF.1
07-Nov-15
07-Sep-15
07-Oct-15
0%
0%
160
PRO.PD.FF.6
07-Nov-15
07-Oct-15
0%
0%
160
18-Aug-15
17-Oct-15
25-Aug-15
24-Oct-15
0%
0%
243
03-Sep-15
17-Oct-15
10-Sep-15
24-Oct-15
0%
0%
243
17-Oct-15
10-Sep-15
24-Oct-15
0%
0%
243
17-Oct-15
24-Oct-15
0%
0%
243
PLUMBING MATERIALS
MA
GRP WATER TANK
TA
PRO.PD.PL.8
18-Aug-15
02-Oct-15
25-Aug-15
09-Oct-15
0%
0%
179
18-Aug-15
02-Oct-15
25-Aug-15
09-Oct-15
0%
0%
179
09-Oct-15
0%
0%
179
PRO.PD.PL.7
02-Oct-15
18-Aug-15
02-Oct-15
25-Aug-15
09-Oct-15
0%
0%
179
18-Aug-15
02-Oct-15
25-Aug-15
09-Oct-15
0%
0%
133
09-Oct-15
0%
0%
179
HVAC MATERIALS
MATERI
CHILLED WATER PIPE INSULATION
02-Oct-15
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
144
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
144
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
144
24-Oct-15
0%
0%
144
24-Oct-15
0%
0%
115
VOLUME CONTR
CONTROL DAMPER (VCD)
22-Oct-15
22-Oct-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
09-Sep-15
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
03-Oct-15, , 03-Oct-15
03-Oct-15, , 03-Oct-15
07-Oct-15, , 07-Oct-15
24-Oct-15, , 24-Oct-15
09-Oct-15, , 09-Oct-15
09-Oct-15, , 09-Oct-15
24-Oct-15, , 24-Oct-15
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
PRO.PD.AC.2
Baseline
Start
Baseline
Finish
PRO.PD.AC.7
PRO.PD.AC.5
Finish
09-Sep-15
22-Oct-15
Schedule %
Complete
Cost %
Complete
Total
Float
24-Oct-15
0%
0%
115
24-Oct-15
0%
0%
115
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
115
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
115
24-Oct-15
0%
0%
115
22-Oct-15
Start
22-Oct-15
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
99
07-Sep-15
22-Oct-15
09-Sep-15
24-Oct-15
0%
0%
99
24-Oct-15
0%
0%
99
22-Oct-15
CONSTRUCTION
CONSTRUCTIO
15-Oct-14
13-Oct-16
15-Oct-14 A
13-Oct-16
19.13%
21.39%
PRELIMINARIES
PRELIMINARIE
15-Oct-14
13-Oct-16
15-Oct-14 A
13-Oct-16
39.73%
39.9%
C1-OFFICERS BUILDING-1
14-Jul-15
06-Nov-15
14-Jul-15 A
30-Oct-15
3.67%
6.8%
156
SUBSTRUCTURE WORK
SUBSTRUCTU
25-Jul-15
28-Jul-15
01-Aug-15
04-Aug-15
100%
0%
30
25-Jul-15
28-Jul-15
01-Aug-15
04-Aug-15
100%
0%
30
AREA-1 (EARTHWORKS
(EART
& CONCRETE WORKS)
25-Jul-15
28-Jul-15
01-Aug-15
04-Aug-15
100%
0%
30
AREA-2 (EARTHWORKS
(EART
& CONCRETE WORKS)
25-Jul-15
28-Jul-15
01-Aug-15
04-Aug-15
100%
0%
30
AREA-3 (EARTHWORKS
(EART
& CONCRETE WORKS)
25-Jul-15
28-Jul-15
01-Aug-15
04-Aug-15
100%
0%
30
14-Jul-15
06-Nov-15
14-Jul-15 A
30-Oct-15
3.94%
7.54%
34
17-Aug-15
10-Sep-15
16-Jul-15 A
25-Aug-15
0%
75.52%
39
17-Aug-15
10-Sep-15
16-Jul-15 A
25-Aug-15
0%
75.52%
39
17-Aug-15
23-Aug-15
26-Jul-15 A
14-Aug-15
0%
70.75%
34
17-Aug-15
21-Aug-15
26-Jul-15 A
12-Aug-15
0%
80%
34
18-Aug-15
22-Aug-15
27-Jul-15 A
13-Aug-15
0%
72%
34
22-Aug-15
23-Aug-15
30-Jul-15 A
14-Aug-15
0%
60%
34
01-Sep-15
10-Sep-15
16-Jul-15 A
25-Aug-15
0%
83.35%
39
06-Sep-15
10-Sep-15
16-Jul-15 A
24-Aug-15
0%
97%
39
CIVIL WORKS
SUPERSTRUCTURE WORKS
SUPERSTRUC
GROUND FLOOR
FL
LEVEL
STAIRCASE
STAIRCASE-01
STAIRCASE-02
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
24-Oct-15, , 24-Oct-15
24-Oct-15, , 24-Oct-15
24-Oct-15, , 24-Oct-15
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Schedule %
Complete
Cost %
Complete
Total
Float
25-Aug-15
0%
70%
39
14-Jul-15 A
21-Oct-15
13.08%
26.52%
12
17-Sep-15
14-Jul-15 A
10-Sep-15
14.99%
35.08%
15
14-Jul-15
20-Aug-15
14-Jul-15 A
20-Aug-15
61.9%
79.55%
16
14-Jul-15
28-Jul-15
14-Jul-15 A
01-Aug-15
100%
95%
01-Aug-15
22-Jul-15 A
03-Aug-15
92.5%
95%
30-Jul-15
23-Jul-15 A
03-Aug-15
100%
0%
03-Aug-15
01-Aug-15 A 03-Aug-15
0%
50%
03-Aug-15
20-Aug-15
03-Aug-15
20-Aug-15
0%
0%
16
14-Jul-15
27-Aug-15
14-Jul-15 A
25-Aug-15
38.59%
50.95%
13
14-Jul-15
27-Jul-15
14-Jul-15 A
01-Aug-15
100%
90%
27-Jul-15
03-Aug-15
21-Jul-15 A
04-Aug-15
56.67%
60%
05-Aug-15
25-Jul-15 A
06-Aug-15
23.33%
60%
09-Aug-15
26-Jul-15 A
06-Aug-15
0%
0%
10-Aug-15
06-Aug-15
08-Aug-15
0%
0%
10-Aug-15
27-Aug-15
08-Aug-15
25-Aug-15
0%
0%
13
30-Jul-15
03-Sep-15
30-Jul-15 A
30-Aug-15
0.14%
15.98%
17
30-Jul-15
09-Aug-15
30-Jul-15 A
04-Aug-15
0.63%
70%
09-Aug-15
15-Aug-15
04-Aug-15
10-Aug-15
0%
0%
16-Aug-15
05-Aug-15
11-Aug-15
0%
0%
16-Aug-15
10-Aug-15
11-Aug-15
0%
0%
17-Aug-15
11-Aug-15
12-Aug-15
0%
0%
17-Aug-15
03-Sep-15
12-Aug-15
30-Aug-15
0%
0%
17
05-Aug-15
03-Sep-15
14-Jul-15 A
30-Aug-15
0%
67.3%
17
05-Aug-15
15-Aug-15
14-Jul-15 A
04-Aug-15
0%
95%
14
FIRST FLOOR
FLOO LEVEL
BEAMS & SLABS
SLA
AREA-3 - BEAMS
BEAM & SLAB
AREA-4 - BEAMS
BEAM & SLAB
AREA-5 - BEAMS
BEAM & SLAB
AREA-6 - BEAMS
BEAM & SLAB
Baseline
Start
Baseline
Finish
Start
Finish
01-Sep-15
02-Sep-15
22-Jul-15 A
14-Jul-15
21-Oct-15
14-Jul-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
16-Aug-15
21-Jul-15 A
05-Aug-15
0%
90%
19
17-Aug-15
22-Jul-15 A
06-Aug-15
0%
90%
19
15-Aug-15
25-Jul-15 A
06-Aug-15
0%
0%
19
16-Aug-15
06-Aug-15
08-Aug-15
0%
0%
19
17-Aug-15
03-Sep-15
12-Aug-15
30-Aug-15
0%
0%
17
13-Aug-15
09-Sep-15
23-Jul-15 A
02-Sep-15
0%
6.85%
14
15-Aug-15
24-Aug-15
23-Jul-15 A
11-Aug-15
0%
30%
14
13-Aug-15
19-Aug-15
06-Aug-15
12-Aug-15
0%
0%
14
22-Aug-15
09-Aug-15
15-Aug-15
0%
0%
14
22-Aug-15
13-Aug-15
15-Aug-15
0%
0%
14
23-Aug-15
15-Aug-15
16-Aug-15
0%
0%
14
23-Aug-15
09-Sep-15
16-Aug-15
02-Sep-15
0%
0%
14
18-Aug-15
17-Sep-15
11-Aug-15
10-Sep-15
0%
0%
15
18-Aug-15
27-Aug-15
11-Aug-15
20-Aug-15
0%
0%
15
23-Aug-15
29-Aug-15
16-Aug-15
22-Aug-15
0%
0%
15
30-Aug-15
17-Aug-15
23-Aug-15
0%
0%
15
30-Aug-15
22-Aug-15
23-Aug-15
0%
0%
15
31-Aug-15
23-Aug-15
24-Aug-15
0%
0%
15
31-Aug-15
17-Sep-15
24-Aug-15
10-Sep-15
0%
0%
15
15-Jul-15
06-Oct-15
14-Jul-15 A
06-Oct-15
9.49%
8.19%
15-Jul-15
27-Jul-15
14-Jul-15 A
01-Aug-15
100%
86.36%
15-Jul-15
26-Jul-15
14-Jul-15 A
01-Aug-15
100%
90%
26-Jul-15
27-Jul-15
16-Jul-15 A
01-Aug-15
100%
80%
03-Aug-15
11-Aug-15
03-Aug-15
11-Aug-15
0%
0%
03-Aug-15
09-Aug-15
03-Aug-15
09-Aug-15
0%
0%
AREA-7 - BEAMS
BEAM & SLAB
AREA-8 - BEAMS
BEAM & SLAB
COLUMNS, WALLS
WA
& COREWALLS
AREA-2 - COLU
COLUMNS
AREA-3 - COLUMNS
COLU
& WALLS
Baseline
Start
Baseline
Finish
10-Aug-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
04-Aug-15
10-Aug-15
04-Aug-15
10-Aug-15
0%
0%
10-Aug-15
11-Aug-15
10-Aug-15
11-Aug-15
0%
0%
09-Aug-15
18-Aug-15
09-Aug-15
18-Aug-15
0%
0%
09-Aug-15
13-Aug-15
09-Aug-15
13-Aug-15
0%
0%
11-Aug-15
17-Aug-15
11-Aug-15
17-Aug-15
0%
0%
17-Aug-15
18-Aug-15
17-Aug-15
18-Aug-15
0%
0%
13-Aug-15
23-Aug-15
13-Aug-15
23-Aug-15
0%
0%
13-Aug-15
18-Aug-15
13-Aug-15
18-Aug-15
0%
0%
16-Aug-15
22-Aug-15
16-Aug-15
22-Aug-15
0%
0%
22-Aug-15
23-Aug-15
22-Aug-15
23-Aug-15
0%
0%
18-Aug-15
26-Aug-15
18-Aug-15
26-Aug-15
0%
0%
18-Aug-15
24-Aug-15
18-Aug-15
24-Aug-15
0%
0%
19-Aug-15
25-Aug-15
19-Aug-15
25-Aug-15
0%
0%
25-Aug-15
26-Aug-15
25-Aug-15
26-Aug-15
0%
0%
24-Aug-15
01-Sep-15
24-Aug-15
01-Sep-15
0%
0%
10
24-Aug-15
30-Aug-15
24-Aug-15
30-Aug-15
0%
0%
25-Aug-15
31-Aug-15
25-Aug-15
31-Aug-15
0%
0%
10
31-Aug-15
01-Sep-15
31-Aug-15
01-Sep-15
0%
0%
10
30-Aug-15
07-Sep-15
30-Aug-15
07-Sep-15
0%
0%
30-Aug-15
05-Sep-15
30-Aug-15
05-Sep-15
0%
0%
31-Aug-15
06-Sep-15
31-Aug-15
06-Sep-15
0%
0%
06-Sep-15
07-Sep-15
06-Sep-15
07-Sep-15
0%
0%
05-Sep-15
13-Sep-15
05-Sep-15
13-Sep-15
0%
0%
10
05-Sep-15
10-Sep-15
05-Sep-15
10-Sep-15
0%
0%
06-Sep-15
12-Sep-15
06-Sep-15
12-Sep-15
0%
0%
10
AREA-4 - COLUMNS
COLU
& WALLS
AREA-5 - COLUMNS
COLU
& CORE WALL
AREA-6 - COLUMNS
COLU
& WALLS
AREA-7 - COLUMNS
COLU
& WALLS
AREA-8 - COLUMNS
COLU
& WALLS
AREA-9 - COLUMNS
COLU
& WALLS
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
13-Sep-15
12-Sep-15
13-Sep-15
0%
0%
10
10-Sep-15
19-Sep-15
10-Sep-15
19-Sep-15
0%
0%
10-Sep-15
16-Sep-15
10-Sep-15
16-Sep-15
0%
0%
12-Sep-15
17-Sep-15
12-Sep-15
17-Sep-15
0%
0%
17-Sep-15
19-Sep-15
17-Sep-15
19-Sep-15
0%
0%
16-Sep-15
30-Sep-15
16-Sep-15
30-Sep-15
0%
0%
16-Sep-15
22-Sep-15
16-Sep-15
22-Sep-15
0%
0%
17-Sep-15
29-Sep-15
17-Sep-15
29-Sep-15
0%
0%
29-Sep-15
30-Sep-15
29-Sep-15
30-Sep-15
0%
0%
22-Sep-15
06-Oct-15
22-Sep-15
06-Oct-15
0%
0%
22-Sep-15
04-Oct-15
22-Sep-15
04-Oct-15
0%
0%
29-Sep-15
05-Oct-15
29-Sep-15
05-Oct-15
0%
0%
05-Oct-15
06-Oct-15
05-Oct-15
06-Oct-15
0%
0%
16-Aug-15
21-Oct-15
18-Aug-15
21-Oct-15
0%
0%
12
13-Sep-15
19-Sep-15
14-Sep-15
19-Sep-15
0%
0%
35
13-Sep-15
17-Sep-15
14-Sep-15
17-Sep-15
0%
0%
35
14-Sep-15
18-Sep-15
15-Sep-15
18-Sep-15
0%
0%
35
18-Sep-15
19-Sep-15
19-Sep-15
19-Sep-15
0%
0%
35
15-Oct-15
21-Oct-15
16-Oct-15
21-Oct-15
0%
0%
12
15-Oct-15
19-Oct-15
16-Oct-15
19-Oct-15
0%
0%
12
16-Oct-15
20-Oct-15
17-Oct-15
20-Oct-15
0%
0%
12
20-Oct-15
21-Oct-15
21-Oct-15
21-Oct-15
0%
0%
12
16-Aug-15
22-Aug-15
18-Aug-15
23-Aug-15
0%
0%
43
16-Aug-15
20-Aug-15
18-Aug-15
21-Aug-15
0%
0%
43
17-Aug-15
21-Aug-15
19-Aug-15
22-Aug-15
0%
0%
43
AREA-11 - COLUMNS
COLU
& WALLS
AREA-12 - COLUMNS
COLU
& WALLS
STAIRCASE
STAIRCASE-01
STAIRCASE-02
STAIRCASE-03
Baseline
Start
Baseline
Finish
12-Sep-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Schedule %
Complete
Cost %
Complete
Total
Float
23-Aug-15
0%
0%
43
03-Aug-15
27-Oct-15
1%
0%
19
24-Oct-15
03-Aug-15
24-Oct-15
1.35%
0%
27-Jul-15
25-Aug-15
03-Aug-15
31-Aug-15
10.77%
0%
25
27-Jul-15
04-Aug-15
03-Aug-15
10-Aug-15
45.71%
0%
30-Jul-15
05-Aug-15
06-Aug-15
11-Aug-15
4%
0%
06-Aug-15
08-Aug-15
12-Aug-15
0%
0%
06-Aug-15
12-Aug-15
12-Aug-15
0%
0%
08-Aug-15
13-Aug-15
13-Aug-15
0%
0%
08-Aug-15
25-Aug-15
15-Aug-15
31-Aug-15
0%
0%
25
04-Aug-15
02-Sep-15
06-Aug-15
03-Sep-15
0%
0%
22
04-Aug-15
12-Aug-15
06-Aug-15
13-Aug-15
0%
0%
08-Aug-15
13-Aug-15
10-Aug-15
15-Aug-15
0%
0%
15-Aug-15
11-Aug-15
16-Aug-15
0%
0%
15-Aug-15
16-Aug-15
16-Aug-15
0%
0%
16-Aug-15
17-Aug-15
17-Aug-15
0%
0%
16-Aug-15
02-Sep-15
18-Aug-15
03-Sep-15
0%
0%
22
12-Aug-15
12-Sep-15
15-Aug-15
13-Sep-15
0%
0%
22
12-Aug-15
22-Aug-15
15-Aug-15
23-Aug-15
0%
0%
17-Aug-15
23-Aug-15
19-Aug-15
24-Aug-15
0%
0%
24-Aug-15
20-Aug-15
25-Aug-15
0%
0%
24-Aug-15
25-Aug-15
25-Aug-15
0%
0%
25-Aug-15
26-Aug-15
26-Aug-15
0%
0%
25-Aug-15
12-Sep-15
27-Aug-15
13-Sep-15
0%
0%
22
23-Aug-15
21-Sep-15
24-Aug-15
21-Sep-15
0%
0%
15
SECOND FLOOR
FLO
LEVEL
BEAMS & SLABS
SLA
AREA-1 - BEAMS
BEAM & SLAB
AREA-2 - BEAMS
BEAM & SLAB
AREA-3 - BEAMS
BEAM & SLAB
AREA-4 - BEAMS
BEAM & SLAB
Baseline
Start
Baseline
Finish
Start
Finish
21-Aug-15
22-Aug-15
23-Aug-15
27-Jul-15
26-Oct-15
27-Jul-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
23-Aug-15
31-Aug-15
24-Aug-15
31-Aug-15
0%
0%
26-Aug-15
01-Sep-15
27-Aug-15
01-Sep-15
0%
0%
02-Sep-15
29-Aug-15
02-Sep-15
0%
0%
02-Sep-15
02-Sep-15
02-Sep-15
0%
0%
03-Sep-15
03-Sep-15
03-Sep-15
0%
0%
03-Sep-15
21-Sep-15
05-Sep-15
21-Sep-15
0%
0%
15
31-Aug-15
06-Oct-15
01-Sep-15
06-Oct-15
0%
0%
15
31-Aug-15
09-Sep-15
01-Sep-15
09-Sep-15
0%
0%
05-Sep-15
10-Sep-15
06-Sep-15
10-Sep-15
0%
0%
12-Sep-15
07-Sep-15
12-Sep-15
0%
0%
12-Sep-15
12-Sep-15
12-Sep-15
0%
0%
13-Sep-15
13-Sep-15
13-Sep-15
0%
0%
13-Sep-15
06-Oct-15
14-Sep-15
06-Oct-15
0%
0%
15
09-Sep-15
15-Oct-15
10-Sep-15
15-Oct-15
0%
0%
09-Sep-15
19-Sep-15
10-Sep-15
19-Sep-15
0%
0%
14-Sep-15
20-Sep-15
15-Sep-15
20-Sep-15
0%
0%
21-Sep-15
16-Sep-15
21-Sep-15
0%
0%
21-Sep-15
21-Sep-15
21-Sep-15
0%
0%
22-Sep-15
22-Sep-15
22-Sep-15
0%
0%
22-Sep-15
15-Oct-15
29-Sep-15
15-Oct-15
0%
0%
19-Sep-15
24-Oct-15
20-Sep-15
24-Oct-15
0%
0%
19-Sep-15
03-Oct-15
20-Sep-15
03-Oct-15
0%
0%
22-Sep-15
04-Oct-15
29-Sep-15
04-Oct-15
0%
0%
05-Oct-15
30-Sep-15
05-Oct-15
0%
0%
05-Oct-15
05-Oct-15
05-Oct-15
0%
0%
AREA-5 - BEAMS
BEAM & SLAB
AREA-6 - BEAMS
BEAM & SLAB
AREA-7 - BEAMS
BEAM & SLAB
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
06-Oct-15
06-Oct-15
06-Oct-15
0%
0%
06-Oct-15
24-Oct-15
07-Oct-15
24-Oct-15
0%
0%
03-Oct-15
15-Oct-15
04-Oct-15
15-Oct-15
0%
0%
03-Oct-15
12-Oct-15
04-Oct-15
12-Oct-15
0%
0%
07-Oct-15
13-Oct-15
08-Oct-15
13-Oct-15
0%
0%
14-Oct-15
10-Oct-15
14-Oct-15
0%
0%
14-Oct-15
14-Oct-15
14-Oct-15
0%
0%
15-Oct-15
15-Oct-15
15-Oct-15
0%
0%
10-Aug-15
26-Oct-15
17-Aug-15
27-Oct-15
0%
0%
10-Aug-15
18-Aug-15
17-Aug-15
24-Aug-15
0%
0%
11
10-Aug-15
16-Aug-15
17-Aug-15
22-Aug-15
0%
0%
11-Aug-15
17-Aug-15
18-Aug-15
23-Aug-15
0%
0%
11
17-Aug-15
18-Aug-15
24-Aug-15
24-Aug-15
0%
0%
11
16-Aug-15
24-Aug-15
23-Aug-15
30-Aug-15
0%
0%
12
16-Aug-15
22-Aug-15
23-Aug-15
27-Aug-15
0%
0%
17-Aug-15
23-Aug-15
24-Aug-15
29-Aug-15
0%
0%
12
23-Aug-15
24-Aug-15
30-Aug-15
30-Aug-15
0%
0%
12
25-Aug-15
02-Sep-15
29-Aug-15
05-Sep-15
0%
0%
13
25-Aug-15
31-Aug-15
29-Aug-15
02-Sep-15
0%
0%
26-Aug-15
01-Sep-15
30-Aug-15
03-Sep-15
0%
0%
13
01-Sep-15
02-Sep-15
05-Sep-15
05-Sep-15
0%
0%
13
31-Aug-15
08-Sep-15
03-Sep-15
10-Sep-15
0%
0%
24
31-Aug-15
06-Sep-15
03-Sep-15
08-Sep-15
0%
0%
01-Sep-15
07-Sep-15
05-Sep-15
09-Sep-15
0%
0%
24
07-Sep-15
08-Sep-15
10-Sep-15
10-Sep-15
0%
0%
24
AREA-8 - BEAMS
BEAM & SLAB
COLUMNS, WALLS
WA
& COREWALLS
AREA-1 - COLU
COLUMNS
AREA-2 - COLU
COLUMNS
AREA-3 - COLUMNS
COLU
& WALLS
AREA-4 - COLUMNS
COLU
& WALLS
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
06-Sep-15
14-Sep-15
09-Sep-15
16-Sep-15
0%
0%
06-Sep-15
12-Sep-15
09-Sep-15
14-Sep-15
0%
0%
07-Sep-15
13-Sep-15
10-Sep-15
15-Sep-15
0%
0%
13-Sep-15
14-Sep-15
16-Sep-15
16-Sep-15
0%
0%
13-Sep-15
21-Sep-15
15-Sep-15
22-Sep-15
0%
0%
13-Sep-15
19-Sep-15
15-Sep-15
20-Sep-15
0%
0%
14-Sep-15
20-Sep-15
16-Sep-15
21-Sep-15
0%
0%
20-Sep-15
21-Sep-15
22-Sep-15
22-Sep-15
0%
0%
19-Sep-15
03-Oct-15
21-Sep-15
04-Oct-15
0%
0%
22
19-Sep-15
30-Sep-15
21-Sep-15
01-Oct-15
0%
0%
20-Sep-15
01-Oct-15
22-Sep-15
03-Oct-15
0%
0%
22
01-Oct-15
03-Oct-15
04-Oct-15
04-Oct-15
0%
0%
22
30-Sep-15
08-Oct-15
03-Oct-15
10-Oct-15
0%
0%
30-Sep-15
06-Oct-15
03-Oct-15
07-Oct-15
0%
0%
01-Oct-15
07-Oct-15
04-Oct-15
08-Oct-15
0%
0%
07-Oct-15
08-Oct-15
10-Oct-15
10-Oct-15
0%
0%
06-Oct-15
14-Oct-15
08-Oct-15
15-Oct-15
0%
0%
12
06-Oct-15
12-Oct-15
08-Oct-15
13-Oct-15
0%
0%
07-Oct-15
13-Oct-15
10-Oct-15
14-Oct-15
0%
0%
12
13-Oct-15
14-Oct-15
15-Oct-15
15-Oct-15
0%
0%
12
12-Oct-15
20-Oct-15
14-Oct-15
21-Oct-15
0%
0%
12-Oct-15
18-Oct-15
14-Oct-15
19-Oct-15
0%
0%
13-Oct-15
19-Oct-15
15-Oct-15
20-Oct-15
0%
0%
19-Oct-15
20-Oct-15
21-Oct-15
21-Oct-15
0%
0%
18-Oct-15
26-Oct-15
20-Oct-15
27-Oct-15
0%
0%
AREA-5 - COLUMNS
COLU
& CORE WALL
AREA-6 - COLUMNS
COLU
& WALLS
AREA-7 - COLUMNS
COLU
& WALLS
AREA-8 - COLUMNS
COLU
& WALLS
AREA-9 - COLUMNS
COLU
& WALLS
AREA-10 - COLU
COLUMNS & CORE WALL
AREA-11 - COLUMNS
COLU
& WALLS
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
18-Oct-15
25-Oct-15
0%
0%
21-Oct-15
26-Oct-15
0%
0%
26-Oct-15
27-Oct-15
27-Oct-15
0%
0%
13-Sep-15
12-Oct-15
11-Sep-15
11-Oct-15
0%
0%
35
06-Oct-15
12-Oct-15
06-Oct-15
11-Oct-15
0%
0%
35
06-Oct-15
10-Oct-15
06-Oct-15
09-Oct-15
0%
0%
35
07-Oct-15
11-Oct-15
07-Oct-15
10-Oct-15
0%
0%
35
11-Oct-15
12-Oct-15
11-Oct-15
11-Oct-15
0%
0%
35
13-Sep-15
19-Sep-15
11-Sep-15
16-Sep-15
0%
0%
50
13-Sep-15
17-Sep-15
11-Sep-15
14-Sep-15
0%
0%
50
14-Sep-15
18-Sep-15
12-Sep-15
15-Sep-15
0%
0%
50
18-Sep-15
19-Sep-15
16-Sep-15
16-Sep-15
0%
0%
50
27-Aug-15
04-Nov-15
25-Aug-15
30-Oct-15
0%
0%
34
27-Aug-15
29-Oct-15
25-Aug-15
30-Oct-15
0%
0%
16
27-Aug-15
21-Sep-15
25-Aug-15
18-Sep-15
0%
0%
39
27-Aug-15
03-Sep-15
25-Aug-15
31-Aug-15
0%
0%
13
30-Aug-15
04-Sep-15
28-Aug-15
01-Sep-15
0%
0%
32
05-Sep-15
29-Aug-15
02-Sep-15
0%
0%
32
05-Sep-15
02-Sep-15
02-Sep-15
0%
0%
32
06-Sep-15
03-Sep-15
03-Sep-15
0%
0%
32
06-Sep-15
21-Sep-15
04-Sep-15
18-Sep-15
0%
0%
39
03-Sep-15
28-Sep-15
01-Sep-15
25-Sep-15
0%
0%
41
03-Sep-15
10-Sep-15
01-Sep-15
07-Sep-15
0%
0%
13
06-Sep-15
11-Sep-15
04-Sep-15
08-Sep-15
0%
0%
30
12-Sep-15
05-Sep-15
09-Sep-15
0%
0%
30
STAIRCASE
STAIRCASE-01
STAIRCASE-03
THIRD FLOOR
FLOO LEVEL
BEAMS & SLABS
SLA
AREA-1 - BEAMS
BEAM & SLAB
AREA-2 - BEAMS
BEAM & SLAB
Start
Finish
24-Oct-15
20-Oct-15
19-Oct-15
25-Oct-15
25-Oct-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
12-Sep-15
09-Sep-15
09-Sep-15
0%
0%
30
13-Sep-15
10-Sep-15
10-Sep-15
0%
0%
30
13-Sep-15
28-Sep-15
11-Sep-15
25-Sep-15
0%
0%
41
10-Sep-15
06-Oct-15
08-Sep-15
03-Oct-15
0%
0%
33
10-Sep-15
18-Sep-15
08-Sep-15
15-Sep-15
0%
0%
13
14-Sep-15
19-Sep-15
12-Sep-15
16-Sep-15
0%
0%
27
20-Sep-15
13-Sep-15
17-Sep-15
0%
0%
27
20-Sep-15
17-Sep-15
17-Sep-15
0%
0%
27
21-Sep-15
18-Sep-15
18-Sep-15
0%
0%
27
21-Sep-15
06-Oct-15
19-Sep-15
03-Oct-15
0%
0%
33
18-Sep-15
13-Oct-15
17-Sep-15
11-Oct-15
0%
0%
25
18-Sep-15
25-Sep-15
17-Sep-15
23-Sep-15
0%
0%
12
21-Sep-15
26-Sep-15
20-Sep-15
24-Sep-15
0%
0%
25
27-Sep-15
21-Sep-15
25-Sep-15
0%
0%
25
27-Sep-15
25-Sep-15
25-Sep-15
0%
0%
25
28-Sep-15
26-Sep-15
26-Sep-15
0%
0%
25
28-Sep-15
13-Oct-15
27-Sep-15
11-Oct-15
0%
0%
25
25-Sep-15
21-Oct-15
24-Sep-15
20-Oct-15
0%
0%
26
25-Sep-15
03-Oct-15
24-Sep-15
01-Oct-15
0%
0%
12
29-Sep-15
04-Oct-15
28-Sep-15
02-Oct-15
0%
0%
26
05-Oct-15
29-Sep-15
03-Oct-15
0%
0%
26
05-Oct-15
03-Oct-15
03-Oct-15
0%
0%
26
06-Oct-15
05-Oct-15
05-Oct-15
0%
0%
25
06-Oct-15
21-Oct-15
06-Oct-15
20-Oct-15
0%
0%
26
08-Oct-15
19-Oct-15
11-Oct-15
21-Oct-15
0%
0%
10
AREA-3 - BEAMS
BEAM & SLAB
AREA-4 - BEAMS
BEAM & SLAB
AREA-5 - BEAMS
BEAM & SLAB
AREA-6 - BEAMS
BEAM & SLAB
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
08-Oct-15
16-Oct-15
11-Oct-15
18-Oct-15
0%
0%
12-Oct-15
17-Oct-15
15-Oct-15
19-Oct-15
0%
0%
10
18-Oct-15
16-Oct-15
20-Oct-15
0%
0%
10
18-Oct-15
20-Oct-15
20-Oct-15
0%
0%
10
19-Oct-15
21-Oct-15
21-Oct-15
0%
0%
10
20-Oct-15
29-Oct-15
22-Oct-15
30-Oct-15
0%
0%
20-Oct-15
27-Oct-15
22-Oct-15
28-Oct-15
0%
0%
23-Oct-15
28-Oct-15
25-Oct-15
29-Oct-15
0%
0%
29-Oct-15
26-Oct-15
30-Oct-15
0%
0%
29-Oct-15
30-Oct-15
30-Oct-15
0%
0%
06-Sep-15
26-Oct-15
04-Sep-15
28-Oct-15
0%
0%
31
06-Sep-15
13-Sep-15
04-Sep-15
10-Sep-15
0%
0%
32
06-Sep-15
11-Sep-15
04-Sep-15
08-Sep-15
0%
0%
32
07-Sep-15
12-Sep-15
05-Sep-15
09-Sep-15
0%
0%
32
12-Sep-15
13-Sep-15
10-Sep-15
10-Sep-15
0%
0%
32
13-Sep-15
20-Sep-15
11-Sep-15
17-Sep-15
0%
0%
32
13-Sep-15
18-Sep-15
11-Sep-15
15-Sep-15
0%
0%
30
14-Sep-15
19-Sep-15
12-Sep-15
16-Sep-15
0%
0%
32
19-Sep-15
20-Sep-15
17-Sep-15
17-Sep-15
0%
0%
32
21-Sep-15
28-Sep-15
19-Sep-15
25-Sep-15
0%
0%
31
21-Sep-15
26-Sep-15
19-Sep-15
23-Sep-15
0%
0%
27
22-Sep-15
27-Sep-15
20-Sep-15
24-Sep-15
0%
0%
31
27-Sep-15
28-Sep-15
25-Sep-15
25-Sep-15
0%
0%
31
26-Sep-15
03-Oct-15
24-Sep-15
30-Sep-15
0%
0%
48
26-Sep-15
01-Oct-15
24-Sep-15
28-Sep-15
0%
0%
27
AREA-7 - BEAMS
BEAM & SLAB
COLUMNS, WALLS
WA
& COREWALLS
AREA-1 - COLU
COLUMNS
AREA-2 - COLU
COLUMNS
AREA-3 - COLUMNS
COLU
& WALLS
AREA-4 - COLUMNS
COLU
& WALLS
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
27-Sep-15
02-Oct-15
25-Sep-15
29-Sep-15
0%
0%
48
02-Oct-15
03-Oct-15
30-Sep-15
30-Sep-15
0%
0%
48
01-Oct-15
08-Oct-15
29-Sep-15
05-Oct-15
0%
0%
29
01-Oct-15
06-Oct-15
29-Sep-15
03-Oct-15
0%
0%
27
02-Oct-15
07-Oct-15
30-Sep-15
04-Oct-15
0%
0%
29
07-Oct-15
08-Oct-15
05-Oct-15
05-Oct-15
0%
0%
29
06-Oct-15
13-Oct-15
06-Oct-15
12-Oct-15
0%
0%
29
06-Oct-15
11-Oct-15
06-Oct-15
10-Oct-15
0%
0%
25
07-Oct-15
12-Oct-15
07-Oct-15
11-Oct-15
0%
0%
29
12-Oct-15
13-Oct-15
12-Oct-15
12-Oct-15
0%
0%
29
11-Oct-15
18-Oct-15
11-Oct-15
17-Oct-15
0%
0%
42
11-Oct-15
16-Oct-15
11-Oct-15
15-Oct-15
0%
0%
25
12-Oct-15
17-Oct-15
12-Oct-15
16-Oct-15
0%
0%
42
17-Oct-15
18-Oct-15
17-Oct-15
17-Oct-15
0%
0%
42
19-Oct-15
26-Oct-15
22-Oct-15
28-Oct-15
0%
0%
21
19-Oct-15
24-Oct-15
22-Oct-15
26-Oct-15
0%
0%
19
20-Oct-15
25-Oct-15
23-Oct-15
27-Oct-15
0%
0%
21
25-Oct-15
26-Oct-15
28-Oct-15
28-Oct-15
0%
0%
21
29-Oct-15
04-Nov-15
23-Oct-15
28-Oct-15
0%
0%
36
29-Oct-15
04-Nov-15
23-Oct-15
28-Oct-15
0%
0%
36
29-Oct-15
02-Nov-15
23-Oct-15
26-Oct-15
0%
0%
36
30-Oct-15
03-Nov-15
24-Oct-15
27-Oct-15
0%
0%
36
03-Nov-15
04-Nov-15
28-Oct-15
28-Oct-15
0%
0%
36
12-Oct-15
06-Nov-15
06-Oct-15
30-Oct-15
0%
0%
25
12-Oct-15
06-Nov-15
06-Oct-15
30-Oct-15
0%
0%
25
AREA-5 - COLUMNS
COLU
& CORE WALL
AREA-6 - COLUMNS
COLU
& WALLS
AREA-7 - COLUMNS
COLU
& WALLS
AREA-8 - COLUMNS
COLU
& WALLS
STAIRCASE
STAIRCASE-03
ROOF FLOOR
FLOO LEVEL
BEAMS & SLABS
SLA
Date: 08-Aug-15 32/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
12-Oct-15
30-Oct-15
0%
0%
25
06-Oct-15
12-Oct-15
0%
0%
20-Oct-15
09-Oct-15
13-Oct-15
0%
0%
25
21-Oct-15
10-Oct-15
14-Oct-15
0%
0%
25
21-Oct-15
14-Oct-15
14-Oct-15
0%
0%
25
22-Oct-15
15-Oct-15
15-Oct-15
0%
0%
25
22-Oct-15
06-Nov-15
16-Oct-15
30-Oct-15
0%
0%
25
19-Oct-15
29-Oct-15
13-Oct-15
22-Oct-15
0%
0%
27
19-Oct-15
26-Oct-15
13-Oct-15
19-Oct-15
0%
0%
22-Oct-15
27-Oct-15
16-Oct-15
20-Oct-15
0%
0%
27
28-Oct-15
17-Oct-15
21-Oct-15
0%
0%
27
28-Oct-15
21-Oct-15
21-Oct-15
0%
0%
27
29-Oct-15
22-Oct-15
22-Oct-15
0%
0%
27
26-Oct-15
06-Nov-15
20-Oct-15
30-Oct-15
0%
0%
19
26-Oct-15
03-Nov-15
20-Oct-15
27-Oct-15
0%
0%
30-Oct-15
04-Nov-15
24-Oct-15
28-Oct-15
0%
0%
19
05-Nov-15
25-Oct-15
29-Oct-15
0%
0%
19
05-Nov-15
29-Oct-15
29-Oct-15
0%
0%
19
06-Nov-15
30-Oct-15
30-Oct-15
0%
0%
19
25-Jul-15
02-Nov-15
25-Jul-15 A
28-Oct-15
0.35%
2.56%
135
25-Jul-15
02-Nov-15
25-Jul-15 A
27-Oct-15
0.43%
3.12%
137
25-Jul-15
25-Oct-15
25-Jul-15 A
26-Oct-15
0.95%
6.86%
137
25-Jul-15
25-Oct-15
25-Jul-15 A
26-Oct-15
1.27%
9.17%
64
25-Jul-15
25-Oct-15
25-Jul-15 A
26-Oct-15
1.27%
9.17%
64
30-Jul-15
17-Aug-15
25-Jul-15 A
12-Aug-15
2.67%
30%
34
AREA-1 - BEAMS
BEAM & SLAB
AREA-2 - BEAMS
BEAM & SLAB
AREA-3 - BEAMS
BEAM & SLAB
FINISHES
GROUND FLOOR
FL
LEVEL
AREA-1
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER
Start
Finish
06-Nov-15
06-Oct-15
12-Oct-15
19-Oct-15
15-Oct-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
25-Jul-15
02-Aug-15
25-Jul-15 A
08-Aug-15
75%
20%
27
B1CCG1.MA.04Lintel Beams
11-Aug-15
23-Aug-15
12-Aug-15
24-Aug-15
0%
0%
64
23-Aug-15
09-Sep-15
24-Aug-15
10-Sep-15
0%
0%
64
B1CCG1.MA.06Sub-Frame to Opennings
09-Sep-15
15-Sep-15
10-Sep-15
16-Sep-15
0%
0%
66
16-Sep-15
17-Sep-15
17-Sep-15
19-Sep-15
0%
0%
64
17-Sep-15
07-Oct-15
19-Sep-15
08-Oct-15
0%
0%
64
07-Oct-15
25-Oct-15
08-Oct-15
26-Oct-15
0%
0%
64
30-Aug-15
13-Oct-15
31-Aug-15
14-Oct-15
0%
0%
148
ELECTRICAL S
SYSTEM
30-Aug-15
13-Oct-15
31-Aug-15
14-Oct-15
0%
0%
86
30-Aug-15
13-Oct-15
31-Aug-15
14-Oct-15
0%
0%
86
16-Sep-15
31-Aug-15
17-Sep-15
0%
0%
64
03-Oct-15
13-Oct-15
03-Oct-15
14-Oct-15
0%
0%
86
PLUMBING SYSTEM
SYS
30-Aug-15
10-Oct-15
31-Aug-15
29-Sep-15
0%
0%
160
30-Aug-15
10-Oct-15
31-Aug-15
29-Sep-15
0%
0%
160
30-Aug-15
16-Sep-15
31-Aug-15
17-Sep-15
0%
0%
117
16-Sep-15
10-Oct-15
06-Sep-15
29-Sep-15
0%
0%
160
27-Aug-15
28-Oct-15
25-Aug-15
26-Oct-15
0%
0%
94
27-Aug-15
28-Oct-15
25-Aug-15
26-Oct-15
0%
0%
41
27-Aug-15
28-Oct-15
25-Aug-15
26-Oct-15
0%
0%
41
27-Aug-15
29-Aug-15
25-Aug-15
26-Aug-15
0%
0%
20
27-Aug-15
06-Sep-15
25-Aug-15
03-Sep-15
0%
0%
13
29-Aug-15
15-Sep-15
26-Aug-15
13-Sep-15
0%
0%
20
B1CCG2.MA.04Lintel Beams
15-Sep-15
03-Oct-15
13-Sep-15
30-Sep-15
0%
0%
41
03-Oct-15
20-Oct-15
30-Sep-15
18-Oct-15
0%
0%
41
B1CCG2.MA.06Sub-Frame to Opennings
20-Oct-15
26-Oct-15
18-Oct-15
24-Oct-15
0%
0%
43
MEP WORKS
AREA-2
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
28-Oct-15
25-Oct-15
26-Oct-15
0%
0%
41
10-Oct-15
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
95
ELECTRICAL S
SYSTEM
10-Oct-15
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
41
10-Oct-15
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
41
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
41
PLUMBING SYSTEM
SYS
10-Oct-15
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
95
10-Oct-15
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
95
10-Oct-15
27-Oct-15
07-Oct-15
25-Oct-15
0%
0%
95
09-Sep-15
02-Nov-15
03-Sep-15
27-Oct-15
0%
0%
37
09-Sep-15
02-Nov-15
03-Sep-15
27-Oct-15
0%
0%
37
09-Sep-15
02-Nov-15
03-Sep-15
27-Oct-15
0%
0%
37
09-Sep-15
10-Sep-15
03-Sep-15
05-Sep-15
0%
0%
21
09-Sep-15
19-Sep-15
03-Sep-15
13-Sep-15
0%
0%
13
10-Sep-15
04-Oct-15
05-Sep-15
22-Sep-15
0%
0%
21
B1CCG3.MA.04Lintel Beams
04-Oct-15
15-Oct-15
22-Sep-15
10-Oct-15
0%
0%
37
15-Oct-15
02-Nov-15
10-Oct-15
27-Oct-15
0%
0%
37
21-Sep-15
29-Oct-15
15-Sep-15
28-Oct-15
0%
0%
39
21-Sep-15
21-Oct-15
15-Sep-15
15-Oct-15
0%
0%
51
21-Sep-15
21-Oct-15
15-Sep-15
15-Oct-15
0%
0%
51
21-Sep-15
21-Oct-15
15-Sep-15
15-Oct-15
0%
0%
51
21-Sep-15
06-Oct-15
15-Sep-15
30-Sep-15
0%
0%
13
03-Oct-15
04-Oct-15
21-Sep-15
22-Sep-15
0%
0%
13
04-Oct-15
21-Oct-15
22-Sep-15
15-Oct-15
0%
0%
13
10-Oct-15
21-Oct-15
04-Oct-15
15-Oct-15
0%
0%
51
06-Oct-15
29-Oct-15
30-Sep-15
24-Oct-15
0%
0%
13
AREA-3
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER
FIRST FLOOR
FLOO LEVEL
AREA-1
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER
AREA-2
Date: 08-Aug-15 35/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16
Baseline
Start
Baseline
Finish
27-Oct-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
29-Oct-15
30-Sep-15
24-Oct-15
0%
0%
13
06-Oct-15
29-Oct-15
30-Sep-15
24-Oct-15
0%
0%
13
06-Oct-15
15-Oct-15
30-Sep-15
10-Oct-15
0%
0%
13
10-Oct-15
11-Oct-15
04-Oct-15
05-Oct-15
0%
0%
14
12-Oct-15
29-Oct-15
06-Oct-15
24-Oct-15
0%
0%
13
27-Oct-15
28-Oct-15
28-Oct-15
28-Oct-15
0%
0%
27-Oct-15
28-Oct-15
28-Oct-15
28-Oct-15
0%
0%
27-Oct-15
28-Oct-15
28-Oct-15
28-Oct-15
0%
0%
27-Oct-15
28-Oct-15
28-Oct-15
28-Oct-15
0%
0%
F1-OFFICERS BUILDING-2
03-Jun-15
27-Oct-15
16-May-15
A
29-Oct-15
6.63%
11.57%
21
SUBSTRUCTURE WORK
SUBSTRUCTU
03-Jun-15
07-Sep-15
16-May-15
A
09-Sep-15
21.29%
37.2%
12-Jul-15
07-Sep-15
15-Jul-15 A
09-Sep-15
2.54%
2.21%
12-Jul-15
07-Sep-15
15-Jul-15 A
09-Sep-15
2.54%
2.21%
12-Jul-15
22-Aug-15
15-Jul-15 A
26-Aug-15
7.65%
6.67%
12-Jul-15
28-Jul-15
15-Jul-15 A
03-Aug-15
100%
70%
13-Jul-15
29-Jul-15
15-Jul-15 A
04-Aug-15
100%
70%
29-Jul-15
05-Aug-15
21-Jul-15 A
05-Aug-15
28.57%
70%
30-Jul-15
06-Aug-15
03-Aug-15
11-Aug-15
14.29%
0%
01-Aug-15
11-Aug-15
04-Aug-15
16-Aug-15
0%
0%
02-Aug-15
12-Aug-15
05-Aug-15
17-Aug-15
0%
0%
06-Aug-15
15-Aug-15
10-Aug-15
19-Aug-15
0%
0%
08-Aug-15
16-Aug-15
11-Aug-15
20-Aug-15
0%
0%
17-Aug-15
20-Aug-15
20-Aug-15
25-Aug-15
0%
0%
18-Aug-15
22-Aug-15
22-Aug-15
26-Aug-15
0%
0%
20-Aug-15
07-Sep-15
22-Aug-15
09-Sep-15
0%
0%
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER
AREA-3
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER
AREA-1 (EARTHWORK
(EAR
& CONCRETE)
CIVIL WORKS
GROUND BEAMS
SLAB ON GRADE
Baseline
Start
Baseline
Finish
06-Oct-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
20-Aug-15
29-Aug-15
22-Aug-15
31-Aug-15
0%
0%
26-Aug-15
30-Aug-15
27-Aug-15
01-Sep-15
0%
0%
27-Aug-15
31-Aug-15
29-Aug-15
02-Sep-15
0%
0%
29-Aug-15
01-Sep-15
30-Aug-15
03-Sep-15
0%
0%
30-Aug-15
02-Sep-15
31-Aug-15
05-Sep-15
0%
0%
30-Aug-15
05-Sep-15
31-Aug-15
07-Sep-15
0%
0%
03-Sep-15
05-Sep-15
05-Sep-15
07-Sep-15
0%
0%
05-Sep-15
05-Sep-15
06-Sep-15
07-Sep-15
0%
0%
06-Sep-15
07-Sep-15
07-Sep-15
09-Sep-15
0%
0%
03-Jun-15
19-Aug-15
16-May-15
A
24-Aug-15
41.57%
75.03%
03-Jun-15
19-Aug-15
02-Jun-15 A
24-Aug-15
40.79%
74.7%
03-Jun-15
09-Jul-15
02-Jun-15 A
04-Aug-15
100%
96.13%
03-Jun-15
20-Jun-15
02-Jun-15 A
01-Aug-15
100%
97%
06-Jun-15
17-Jun-15
20-Jun-15 A
01-Aug-15
100%
0%
17-Jun-15
29-Jun-15
20-Jun-15 A
01-Aug-15
100%
95%
29-Jun-15
07-Jul-15
25-Jun-15 A
02-Aug-15
100%
95%
01-Jul-15
09-Jul-15
26-Jun-15 A
04-Aug-15
100%
95%
02-Jul-15
19-Aug-15
26-Jun-15 A
24-Aug-15
19.15%
66.88%
02-Jul-15
30-Jul-15
26-Jun-15 A
09-Aug-15
100%
75%
16-Jul-15
08-Aug-15
30-Jun-15 A
17-Aug-15
54.67%
70%
16-Jul-15
09-Aug-15
30-Jun-15 A
18-Aug-15
51.25%
70%
02-Aug-15
10-Aug-15
01-Jul-15 A
19-Aug-15
0%
65%
03-Aug-15
11-Aug-15
08-Jul-15 A
20-Aug-15
0%
65%
03-Aug-15
17-Aug-15
08-Jul-15 A
23-Aug-15
0%
65%
15-Aug-15
17-Aug-15
08-Jul-15 A
23-Aug-15
0%
65%
AREA-2 (EARTHWORK
(EAR
& CONCRETE)
CIVIL WORKS
GROUND BEAMS
SLAB ON GRADE
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
16-Aug-15
23-Aug-15
0%
0%
08-Jul-15 A
24-Aug-15
0%
65%
22-Jun-15
16-May-15
A
01-Aug-15
100%
99%
20
04-Jun-15
22-Jun-15
16-May-15
A
01-Aug-15
100%
99%
20
20-Aug-15
27-Oct-15
24-Aug-15
29-Oct-15
0%
0%
21
08-Sep-15
27-Oct-15
09-Sep-15
29-Oct-15
0%
0%
21
08-Sep-15
20-Oct-15
09-Sep-15
22-Oct-15
0%
0%
10
08-Sep-15
17-Sep-15
09-Sep-15
20-Sep-15
0%
0%
08-Sep-15
15-Sep-15
09-Sep-15
17-Sep-15
0%
0%
09-Sep-15
16-Sep-15
10-Sep-15
19-Sep-15
0%
0%
16-Sep-15
17-Sep-15
19-Sep-15
20-Sep-15
0%
0%
16-Sep-15
01-Oct-15
17-Sep-15
04-Oct-15
0%
0%
10
16-Sep-15
29-Sep-15
17-Sep-15
01-Oct-15
0%
0%
10
17-Sep-15
30-Sep-15
19-Sep-15
03-Oct-15
0%
0%
10
30-Sep-15
01-Oct-15
03-Oct-15
04-Oct-15
0%
0%
10
11-Oct-15
20-Oct-15
13-Oct-15
22-Oct-15
0%
0%
10
11-Oct-15
20-Oct-15
13-Oct-15
22-Oct-15
0%
0%
10
11-Oct-15
18-Oct-15
13-Oct-15
20-Oct-15
0%
0%
10
13-Oct-15
19-Oct-15
15-Oct-15
21-Oct-15
0%
0%
10
19-Oct-15
20-Oct-15
21-Oct-15
22-Oct-15
0%
0%
10
17-Sep-15
27-Oct-15
20-Sep-15
29-Oct-15
0%
0%
21
17-Sep-15
22-Oct-15
20-Sep-15
25-Oct-15
0%
0%
17-Sep-15
22-Oct-15
20-Sep-15
25-Oct-15
0%
0%
17-Sep-15
29-Sep-15
20-Sep-15
01-Oct-15
0%
0%
21-Sep-15
30-Sep-15
29-Sep-15
03-Oct-15
0%
0%
MEP WORKS
B2CMS2.PL.01 Under Ground Utilities to Officer's Building-2
SUPERSTRUCTURE WORKS
SUPERSTRUC
PHASE-1 CONCRETE
CO
WORKS
GROUND FLOOR
FLOO LEVEL
AREA-6 (COLUMNS
(COLUM
& WALLS)
AREA-7 (COLUMNS
(COLUM
& WALLS)
STAIRCASE
STAIRCASE-1,2&3
STAIRCASE-1,2
Start
Finish
17-Aug-15
08-Jul-15 A
17-Aug-15
19-Aug-15
04-Jun-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
21-Sep-15
03-Oct-15
29-Sep-15
05-Oct-15
0%
0%
01-Oct-15
03-Oct-15
04-Oct-15
05-Oct-15
0%
0%
03-Oct-15
04-Oct-15
05-Oct-15
06-Oct-15
0%
0%
05-Oct-15
22-Oct-15
07-Oct-15
25-Oct-15
0%
0%
29-Sep-15
14-Oct-15
01-Oct-15
17-Oct-15
0%
0%
29-Sep-15
11-Oct-15
01-Oct-15
13-Oct-15
0%
0%
03-Oct-15
12-Oct-15
05-Oct-15
14-Oct-15
0%
0%
04-Oct-15
13-Oct-15
06-Oct-15
15-Oct-15
0%
0%
13-Oct-15
14-Oct-15
15-Oct-15
0%
0%
13-Oct-15
14-Oct-15
15-Oct-15
17-Oct-15
0%
0%
11-Oct-15
27-Oct-15
13-Oct-15
29-Oct-15
0%
0%
11-Oct-15
22-Oct-15
13-Oct-15
25-Oct-15
0%
0%
15-Oct-15
25-Oct-15
18-Oct-15
27-Oct-15
0%
0%
15-Oct-15
27-Oct-15
18-Oct-15
29-Oct-15
0%
0%
22-Oct-15
27-Oct-15
25-Oct-15
29-Oct-15
0%
0%
07-Oct-15
17-Oct-15
10-Oct-15
19-Oct-15
0%
0%
07-Oct-15
14-Oct-15
10-Oct-15
17-Oct-15
0%
0%
08-Oct-15
15-Oct-15
11-Oct-15
18-Oct-15
0%
0%
15-Oct-15
17-Oct-15
18-Oct-15
19-Oct-15
0%
0%
17-Oct-15
26-Oct-15
19-Oct-15
28-Oct-15
0%
0%
17-Oct-15
24-Oct-15
19-Oct-15
26-Oct-15
0%
0%
18-Oct-15
25-Oct-15
20-Oct-15
27-Oct-15
0%
0%
25-Oct-15
26-Oct-15
27-Oct-15
28-Oct-15
0%
0%
25-Oct-15
27-Oct-15
27-Oct-15
29-Oct-15
0%
0%
21
25-Oct-15
27-Oct-15
27-Oct-15
29-Oct-15
0%
0%
21
AREA-6b: (BEAMS
(BEA
& SLABS)
AREA-7: (BEAMS)
(BEAM
AREA-6: (COLUMNS)
(COLU
STAIRCASE
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Start
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
25-Oct-15
24-Aug-15
28-Oct-15
0%
0%
17
20-Aug-15
05-Oct-15
24-Aug-15
08-Oct-15
0%
0%
34
20-Aug-15
31-Aug-15
24-Aug-15
03-Sep-15
0%
0%
20
20-Aug-15
29-Aug-15
24-Aug-15
01-Sep-15
0%
0%
22-Aug-15
30-Aug-15
25-Aug-15
02-Sep-15
0%
0%
20
30-Aug-15
31-Aug-15
02-Sep-15
03-Sep-15
0%
0%
20
29-Aug-15
06-Sep-15
01-Sep-15
09-Sep-15
0%
0%
16
29-Aug-15
03-Sep-15
01-Sep-15
07-Sep-15
0%
0%
30-Aug-15
05-Sep-15
02-Sep-15
08-Sep-15
0%
0%
16
05-Sep-15
06-Sep-15
08-Sep-15
09-Sep-15
0%
0%
16
03-Sep-15
13-Sep-15
07-Sep-15
16-Sep-15
0%
0%
11
03-Sep-15
10-Sep-15
07-Sep-15
14-Sep-15
0%
0%
05-Sep-15
12-Sep-15
08-Sep-15
15-Sep-15
0%
0%
11
12-Sep-15
13-Sep-15
15-Sep-15
16-Sep-15
0%
0%
11
10-Sep-15
21-Sep-15
14-Sep-15
30-Sep-15
0%
0%
10-Sep-15
19-Sep-15
14-Sep-15
22-Sep-15
0%
0%
12-Sep-15
20-Sep-15
15-Sep-15
29-Sep-15
0%
0%
20-Sep-15
21-Sep-15
29-Sep-15
30-Sep-15
0%
0%
19-Sep-15
03-Oct-15
22-Sep-15
06-Oct-15
0%
0%
19-Sep-15
30-Sep-15
22-Sep-15
04-Oct-15
0%
0%
20-Sep-15
01-Oct-15
29-Sep-15
05-Oct-15
0%
0%
01-Oct-15
03-Oct-15
05-Oct-15
06-Oct-15
0%
0%
20-Sep-15
05-Oct-15
29-Sep-15
08-Oct-15
0%
0%
34
20-Sep-15
05-Oct-15
29-Sep-15
08-Oct-15
0%
0%
34
20-Sep-15
03-Oct-15
29-Sep-15
06-Oct-15
0%
0%
34
PHASE-2 CONCRETE
CO
WORKS
GROUND FLOOR
FLOO LEVEL
AREA-1 (COLUMNS
(COLUM
& WALLS)
AREA-2 (COLUMNS
(COLUM
& WALLS)
AREA-3 (COLUMNS
(COLUM
& WALLS)
AREA-4 (COLUMNS
(COLUM
& WALLS)
AREA-5 (COLUMNS
(COLUM
& WALLS)
STAIRCASE
STAIRCASE-1,2&3
STAIRCASE-1,2
Baseline
Start
Baseline
Finish
20-Aug-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
22-Sep-15
07-Oct-15
0%
0%
34
07-Oct-15
08-Oct-15
0%
0%
34
25-Oct-15
03-Sep-15
28-Oct-15
0%
0%
17
31-Aug-15
06-Oct-15
03-Sep-15
10-Oct-15
0%
0%
33
31-Aug-15
09-Sep-15
03-Sep-15
13-Sep-15
0%
0%
25
05-Sep-15
10-Sep-15
08-Sep-15
14-Sep-15
0%
0%
25
06-Sep-15
12-Sep-15
09-Sep-15
15-Sep-15
0%
0%
25
12-Sep-15
14-Sep-15
15-Sep-15
0%
0%
25
12-Sep-15
13-Sep-15
15-Sep-15
16-Sep-15
0%
0%
25
13-Sep-15
06-Oct-15
16-Sep-15
10-Oct-15
0%
0%
33
06-Sep-15
11-Oct-15
09-Sep-15
14-Oct-15
0%
0%
29
06-Sep-15
13-Sep-15
09-Sep-15
16-Sep-15
0%
0%
22
08-Sep-15
14-Sep-15
12-Sep-15
17-Sep-15
0%
0%
22
09-Sep-15
15-Sep-15
13-Sep-15
19-Sep-15
0%
0%
22
15-Sep-15
17-Sep-15
19-Sep-15
0%
0%
22
15-Sep-15
16-Sep-15
19-Sep-15
20-Sep-15
0%
0%
22
17-Sep-15
11-Oct-15
21-Sep-15
14-Oct-15
0%
0%
29
13-Sep-15
19-Oct-15
16-Sep-15
22-Oct-15
0%
0%
22
13-Sep-15
21-Sep-15
16-Sep-15
30-Sep-15
0%
0%
15
16-Sep-15
22-Sep-15
20-Sep-15
01-Oct-15
0%
0%
15
17-Sep-15
29-Sep-15
21-Sep-15
03-Oct-15
0%
0%
15
29-Sep-15
01-Oct-15
03-Oct-15
0%
0%
15
29-Sep-15
30-Sep-15
03-Oct-15
04-Oct-15
0%
0%
15
01-Oct-15
19-Oct-15
05-Oct-15
22-Oct-15
0%
0%
22
21-Sep-15
12-Oct-15
30-Sep-15
15-Oct-15
0%
0%
Start
Finish
04-Oct-15
01-Oct-15
04-Oct-15
05-Oct-15
31-Aug-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil
Activity ID
Activity Name
Baseline
Start
Baseline
Finish
Schedule %
Complete
Cost %
Complete
Total
Float
21-Sep-15
12-Oct-15
0%
0%
06-Oct-15
13-Oct-15
0%
0%
11-Oct-15
07-Oct-15
14-Oct-15
0%
0%
11-Oct-15
13-Oct-15
14-Oct-15
0%
0%
11-Oct-15
12-Oct-15
14-Oct-15
15-Oct-15
0%
0%
03-Oct-15
13-Oct-15
06-Oct-15
17-Oct-15
0%
0%
03-Oct-15
10-Oct-15
06-Oct-15
13-Oct-15
0%
0%
05-Oct-15
11-Oct-15
08-Oct-15
14-Oct-15
0%
0%
06-Oct-15
12-Oct-15
10-Oct-15
15-Oct-15
0%
0%
12-Oct-15
14-Oct-15
15-Oct-15
0%
0%
12-Oct-15
13-Oct-15
15-Oct-15
17-Oct-15
0%
0%
13-Oct-15
25-Oct-15
17-Oct-15
28-Oct-15
0%
0%
13-Oct-15
22-Oct-15
17-Oct-15
26-Oct-15
0%
0%
14-Oct-15
24-Oct-15
18-Oct-15
27-Oct-15
0%
0%
20-Oct-15
25-Oct-15
24-Oct-15
28-Oct-15
0%
0%
COLUMNS
Start
Finish
08-Oct-15
30-Sep-15
03-Oct-15
10-Oct-15
04-Oct-15
Critical Activity
Baseline Bar
Actual Work
Early Bar
Early Bar
2015
S O N
2016
F M A M J Jul A S O N
F M A M J Jul A S O N D
Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil