PROJECT MANAGEMENT ACTIVITY TABLE

Course Title: Project Management Fundamentals


Course No: B03-001
This project management activity table is inteneded for use as a basis for the course quiz comprised of twenty questions. The user should refer to
this table when answering all twenty questions. The user should also note that each question is independent of the other.

Activity

Precedence Relation

Manpower
(per day)

Normal Cost 1
($)

Crash Cost
($)

Normal Duration
(days)

Crash Duration
(days)

Percent Complete
at Day 14 (%)

First Activity

5,000

10,000

100

First Activity

15

6,000

12,000

100

Follows A

3,000

6,000

100

Follows A

2,000

4,000

100

Follows B

4,000

8,000

60

Follows E and is the Last Activity

7,000

14,000

14

10

50

Follows C

800

1,600

50

Follows C

1,200

2,600

50

Follows G and is the Last Activity

10

7,000

14,000

Follows D,E,H and is the Last Activity

12,000

24,000

(1) The normal cost is equally distributed over the duration of each activity.