SEQUENCE OF WORK

1. Piling work
2. Instal Bracket & H-Beam
3. Instal Base form (Staging work)
4. Instal Beams Reinforcement bar & Embedded anchor
5 S
5.
Setting
tti Side
Sid fform B
Beam
6. Concreting work of Beam
7. Removal of Side form (Inside)
8 Instal Precast Slab
8.
9. Instal Reinforcement bar of Slab
10. Concreting of Slab (insitu)
g g
11. Removal of Side form and Staging

Crawler
Crane 50
t
ton

12. Compeled concrete deck

Concre
Bucke

Reinforcement
bar
Reinforcement
of slab Pre-cast slab
Concrete Bucket
Concrete Slab
Side form
Side form

SECTION OF LOADING JETTY


By Lambutan Sinaga
www.berthing.wordpress.com