12TH FLOOR
1. SPRINKLER FIXING
13TH FLOOR
1. SPRINKLER FIXING
14TH FLOOR
1. FINAL PRESSURE TEST
2. SPRINKLER FIXING
15TH FLOOR
1. FINAL PRESSURE TEST
2. SPRINKLER FIXING
16TH FLOOR
1. FINAL PRESSURE TEST
2. SPRINKLER FIXING
17TH FLOOR
1. FINAL PRESSURE TEST
2. SPRINKLER FIXING
18TH FLOOR
1. FINAL PRESSURE TEST
2. SPRINKLER FIXING
19TH FLOOR
1. DROPPING IN KITCHEN & CORRIDOR
2. FINAL PRESSURE TEST
3. ZCV CONNECTION
4. SPRINKLER FIXING
20TH FLOOR
1. DROPPING IN KITCHEN & CORRIDOR
2. FINAL PRESSURE TEST
3. ZCV CONNECTION
3. SPRINKLER FIXING
21ST FLOOR
1. DROPPING IN KITCHEN & CORRIDOR
2. FINAL PRESSURE TEST
3. ZCV CONNECTION
3. SPRINKLER FIXING
22TH FLOOR
1. DROPPING IN KITCHEN & CORRIDOR
2. FINAL PRESSURE TEST
3. ZCV CONNECTION
4. SPRINKLER FIXING
23RD FLOOR
1. DROPPING
2. PRESSURE TEST
3. SPRINKLER FIXING
24TH FLOOR
1. DROPPING
2. PRESSURE TEST
3. SPRINKLER FIXING
ROOF FLOOR
1. FHCS CABINET FIXING AND CONNECTION TO RISER PIPE
SHAFT
1. FHCS CABINET CONNECTION TO RISER PIPE
2.
FLOOR
3. WATER SPRAY SYSTEM
4. PRE ACTION SYSTEM
5. FIRE HOSE REEL CABINET INSTALLATION
ALFAHAD- 1
PLUMBING REMAINING WORKS
BASEMENT 3
1.
2.
3.
4.
5.
6.
BASEMENT 2
1. CATCH BASIN COVER INSTALLATION
2. TRANSFER LINE FIXING
3. PRESSURE TEST OF TRANSFER LINE
BASEMENT -1
1. CATCH BASIN COVER INSTALLATION
2. TRANSFER LINE FIXING
3. PRESSURE TEST OF TRANSFER LINE
4. DUBAI MUNICIPALITY DRAINAGE CONNECTION
GROUND FLOOR
1. SWIMMING POOL PIPING WORK AND FIXING OF EQUIPMENTS
2. PRESSURE TEST
3. DRAINAGE SHAFT CONNECTION
4. BALCONY DRAIN PIPE CONNECTION HIGHLEVEL
5. GROUND FLOOR HIGHLEVEL DRAINAGE PIPE LEAK TESTING
6. FIXING OF MANHOLE GRATING.
7. INSTALLATION OF TRANSFER LINE
1ST FLOOR
1. SWIMMING POOL PIPING WORK
2. LEAK TEST OF HIGHLEVEL DRAINAGE LINE
3. DRAINAGE PIPE SHAFT CONNECTION
4. SANITARY FIXING IN BATHROOM(SHOWER MIXITURE AND SHOWER TRAY)
5. INSTALLATION OF TRANSFER LINE
2ND FLOOR
1. SANITARY FIXING INCLUDE SHOWER TRAY,SHOWER HEAD,WC,BIDET,KITCHEN
ZINC .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
3RD FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
4TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
5TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINCAND SHOWER MIXTURE.
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
6TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC ,SHOWER MIXTURE
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
7TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC ,SHOWER MIXTURE.
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
8TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC , SHOWER MIXTURE.
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
9TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC , SHOWER MIXTURE.
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
10TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC ,SHOWER MIXTURE
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
11TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC ,COUNTER WASHBASIN AND
SHOWER MIXTURE..
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
12TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC ,COUNTER WASHBASIN AND
SHOWER MIXTURE.
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
13TH FLOOR
WATERMIXTURE .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
14TH FLOOR
1. SANITARY FIXING INCLUDE KITCHEN ZINC ANDCOUNTER WASHBASIN .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
15TH FLOOR
1. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,WC& SHOWER HEAD .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
16TH FLOOR
1. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,WC,SHOWER HEAD
&COUNTER WASHBASIN .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
17TH FLOOR
1. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,,SHOWER MIXTURE
&COUNTER WASHBASIN .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
18TH FLOOR
1. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,WC,BIDET,SHOWER MIXTURE
.
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
19TH FLOOR
1. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,WC,SHOWER MIXTURE .
2. WATER METER CABINET
3. INSTALLATION OF TRANSFER LINE
20TH FLOOR
1. BATH TUB FIXING
2. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,,SHOWER MIXTURE
&COUNTER WASHBASIN .
3. WATER METER CABINET
4. INSTALLATION OF TRANSFER LINE
21ST FLOOR
1. BATH TUB FIXING
2. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,SHOWER MIXTURE
&COUNTER WASHBASIN .
3. WATER METER CABINET
4. INSTALLATION OF TRANSFER LINE
22TH FLOOR
1. BATH TUB FIXING
23RD FLOOR
1. BATH TUB FIXING
2. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,WC,BIDET,SHOWER HEAD
&COUNTER WASHBASIN .
3. WATER METER CABINET
4. INSTALLATION OF TRANSFER LINE
5. ACCOUSTIC LINING FOR HIGHLEVEL DRAINAGE LINE INSIDE ROOM AND
CORRIDOR
6. HIGHLEVEL DRAINAGE LEAK TEST
7. PPR PIPE INSTALLATION AND LEAK TEST
24TH FLOOR
1. BATH TUB FIXING
2. FINAL SANITARY FIXING INCLUDE KITCHEN ZINC ,WC,BIDET,SHOWER
&COUNTER WASHBASIN .
3. WATER METER CABINET
4. INSTALLATION OF TRANSFER LINE
5. ACCOUSTIC LINING FOR HIGHLEVEL DRAINAGE LINE INSIDE ROOM AND
CORRIDOR
6. HIGHLEVEL DRAINAGE PIPE INSTALLATION AND LEAK TEST
7. PPR PIPE INSTALLATION AND LEAK TES
ROOF FLOOR
1. GRP TANK INSTALLATION,CONNECTION AND TESTING
2. BOOSTER PUMP INSTALLATION AND CONNECTION
SHAFT
1. INSTALLATION AND LEAK TEST OF WATER TRANSFER LINE FROM BASEMENT
3 TO ROOF FLOOR.
2. INSTALLATION OF WATER SUPPLY LINE FROM ROOF .
1ST
7TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
8TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
9TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
10TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
11TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
12TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
13TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
14TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
15TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
16TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
17TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
18TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
19TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
5. WIRE MESH INSTALLATION
20TH FLOOR
1.
2.
3.
4.
5.
21ST FLOOR
1.
2.
3.
4.
23RD FLOOR
1.
2.
3.
4.
5.
6.
24TH FLOOR
1. FLEXIBLE DUCT GRILLS &DIFFUSER INSTALLATION.
2. THERMOSTAT WIRE CONNECTION AND FIXING
3. BTU METER INSTALLATION
4. MOTORIZED FIRE DAMPER INSTALLATION
5. AC DRAIN CONNECTION
6. SUPPLY DUCT,RETURN DUCT ,PLENUM BOX,MOUTH CONNECTION ,FRESH
AIR ,,EXHAUST ,FLEXIBLE DUCT ,MOUTH CONNECTION ACESS DOOR AND
GRILLS ,DIFFUSER INSTALLATION.
7. WIRE MESH INSTALLATION
8. PRESSURE TEST
9. VCD&FD INSTALLATION
10. CHILLED WATER PIPE& VALVE INSTALLATION AND INSULATION
11. FCU INSTALLATION
ROOF FLOOR
1. FAN FIXING IN ROOF AND TOP ROOF
2. FRESH AIR AND EXHAUST AIR DUCT ON ROOF
3. VALVE FIXING OF FAHU
4. INSTALLATION OF SOUND ATTENUATOR
SHAFT
1. PRESSURISATION RISER STAIR CASE ONE FROM 14TH FLOOR TO ROOF