STRUCTURAL DESIGN 366

ORAL PRESENTATION
GROUP 4
WONG WEE TIAN
LOK YONG QUAN
NG WEI HONG
SADIA TASNIM
HWONG CHOON CHIAT

INTRODUCTION
Background
Project: Pump shed design ( portal frame)
Location: Newman Australia (modern mining town,
with suburban-style homes )
Climate: has an arid climate, with very hot
summers and mild winters.

Material used: Steel (timber is not strong and


no resources for concrete near
by)
Lifespan: 30 years
Specification: Clearance width of 5.7m, overall
length of 16.5m and height to
the underside of the monorail
beam of 4.0m

Design Process
Finding load cases
Analysis using software to get BMD diagrams.
Preliminary calculation to get member sizes
Connection and foundation design
Construction, installation and transportation
methods
Constraints

Design Options

Flat Roof

Pitched Roof

Load Combination
1) 1.2G+ 1.5Q+1.5C

2) 1.2G+1.5C+Wu

Member selection
Z10015
200UB22.3
50*50*6E
A

Construction Method
Foundation -in
situ concrete,
concrete slab

Column installation
-Column: 200UB22.3

-Pinned base
-From Left to Right.

Rafter installation
-Rigid connection
-Haunches and stiffener installed

Purlin and Girt Installation


-Purlins Z10015 with 0.9m spacing.
-Girt Z10015 at 2.5m from Ground

Bracing installation
-50*50*6 EA section

Sheeting installation
-Custom ORB 0.42BMT

Final Design
-Crane installation

Connection!

Bolted

Semi-

skilled
installation
Easy to punch hole
Can be removed
Field installation
Minimize
construction error

Welded
High skilled
installation, high
experience
Good quality
Not suit to field
application

Apex connection

Final decision

Thickness of
the plate=25mm

M20

Apex
haunches

Connectio
n details

Column and rafter

Final Decision

Size of bolt:
M20

Eaves
haunch

Rafter and purlin

VS

Pinned Connection
27mm
134mm

27mm

150mm
4 M16 Bolts

210mm

Thickness of base
plate = 20mm

Transportation
panel

assemblies

Need to apply permits


Length > 3.5m and < 5.5m
Connections needed to do on sites

Safety

Common Hazards

Falling from a height while rigging.


Collapse of the structure.
Falling Objects.

We need a Erector supervisor to supervise


on site.

Quality Control
Coating

Corrosion and fire protections

Inspection

Separation

and packing
During Installation of portal frame structures
Shop drawings
Checking procedures

conclusion
Advantages
Cost effectiveness.
Save time.
Sustainability.
Capable taking loads immediately.