Networking Diagram

and Resource Allocation

Project Management

Presented by
Sai Suprith ME1428
Mani Shankar ME1418
Srikanth Chittam ME1438
Yashas ME1446
Arunima Joshi ME1406
Rekha MET1454

E ID
E
S
F
S
S
L
L
L DU L
Project Management
S R
F
Networking Diagram with Resource Allocation
Problem 1 Pg No- 451
1. Given the network plan that follows, compute the early, late, and slack times.
What is the project duration? Using any approach you wish (e.g., trial and
error), develop a loading chart for resources, Electrical Engineers (EE), and
resource, Mechanical Engineers (ME). Assume only one of each resource
exists. Given you schedule, compute the early, late, and slack times for your
project. Which activities are now critical? What is the project duration now?
Could something like this happen in real projects?
Networking diagram for completion of project.
0 3
3
2 M 2
2 4 3
3 5 9
E 2
0 1
0 E 0
0 M 0
2 E
3 05
0
E
E
E
2
1 3
3 6 9
0 2 2
4 6 6
0 2 4
3 M 3
Start
3 E 3
E
Critical
E
7 2 9
Path
3 4 7
3
2
5

7
E
E
4

Stop

7
2
9

Calculation of critical path for the work flow:


1 EE + 4 EE + 5 ME = 2+1+6 = 9 weeks
2 EE + 6 ME
= 4+2
= 6 weeks
3 ME + 7 EE
= 3+4
= 7 weeks

Legend

Resource

For the completion of the project the maximum number of


weeks is 9 weeks, this path is considered to be critical path
for the completion of the project.
Critical path is 1 EE + 4 EE + 5 ME = 2+1+6 = 9 weeks

ID/RE
S
1-EE
2-EE

E
S
0
0

L
S
0
3

E
F
2
4

L
F
2
7

S
L
0
3

Resource
activity
schedule

3-ME
4-EE
5-ME
6-ME
7-EE

0
2
3
4
3

2
2
3
7
5

3
3
9
6
7

5
3
9
9
9

2
0
0
3
2

Loading schedule for each resource


EE
ME

1
3

1
3
0

2
3

2
5
1

2
5
2

2
5
3

4
5

7
5
4

7
5
5

7
6
6

7
6
7

10

11

12

13
Conclusion
For the normal completion duration for the project is 9 weeks but in the practical
implementation scenario of project with only one Electrical Engineer and Mechanical
Engineer it delayed by 2 weeks (i.e., total duration is 11 weeks).