Construction

Arbitration
Dr. Crengua Leaua
Course no. 6

Alternative dispute resolution


methods in construction disputes
Pre-arbitration procedures
General
Negotiation
Mediation
Early neutral evaluation

Specific to FIDIC contracts


Engineer determination
Dispute adjudecation board decision
Dispute resolution board decisions
Combined board decisions

Alternative dispute resolution


methods in construction disputes
Pre-arbitration procedures:
Non-mandatory ( possible, but not required before the initiation of
the arbitration )
Negotiation
Mediation
Early neutral evaluation
Dispute adjudecation board decision DAB
Dispute resolution board decisions DRB
Combined board decisions CB

Mandatory under the FIDIC General Conditions


Engineer determination
Dispute resolution board decision

Alternative dispute resolution


methods in construction disputes
Pre-arbitration procedures:
Without the participation of a neutral
Negotiation

With the participation of a neutral


Mediation
Early neutral evaluation
Dispute adjudecation board decision
Dispute resolution board decisions
Combined board decisions

Alternative dispute resolution


methods in construction disputes
Pre-arbitration procedures:
If successful, finalised with a settlement of the parties
Negotiation
Mediation

Finalised with a decision of the neutral


Early neutral evaluation
Dispute adjudecation board decision
Dispute resolution board decisions
Combined board decisions
Such decisions are not replacing an arbitral award or court decision. They may
be complied voluntarily by the parties, but in case of dissatisfaction properly
notified, parties may proceed with the arbitration.