Task ID
Mode
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
1
2
Task Name
Duration
Start
Finish
CONSTRUCCIN DE CASA
20 days
Mon 11/01/16
Fri 05/02/16
4 days
Mon 11/01/16
Thu 14/01/16
MOVILIZACIN
2 days
Mon 11/01/16
Tue 12/01/16
EXCAVACIN
2 days
Wed 13/01/16
Thu 14/01/16
13 days
Wed 13/01/16
Fri 29/01/16
10 days
Wed 13/01/16
Tue 26/01/16
PRELIMINARES
FUNDACIONES
Thu 14/01/16
Tue 19/01/16
VACIADO DE ZAPATAS
2 days
Tue 19/01/16
Wed 20/01/16
3 days
Tue 19/01/16
Thu 21/01/16
10
REFUERZO DE PEDESTALES
2 days
Thu 21/01/16
Fri 22/01/16
11
ENCOFRADO DE PEDESTALES
1 day
Mon 25/01/16
Mon 25/01/16
12
VACIADO DE PEDESTALES
1 day
Tue 26/01/16
Tue 26/01/16
13
BLOQUE RELLENO
4 days
Fri 22/01/16
Wed 27/01/16
RELLENO
14
2 days
Thu 28/01/16
Fri 29/01/16
15
CONSTRUCCIN DE LOSA
5 days
Mon 01/02/16
Fri 05/02/16
16
REFUERZO DE LOSA
4 days
Mon 01/02/16
Thu 04/02/16
17
VACIADO DE LOSA
1 day
Fri 05/02/16
Fri 05/02/16
11 Jan '16
18 Jan '16
25 Jan '16
01 Feb '16
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Critical
Project Summary
Duration-only
Critical Split
External Tasks
Progress
External Milestone
Manual Summary
Page 1