I.
Site Inspection
1. Sump Pumps for Genset room, as of December 22, 2015, is in normal
operating condition.
2. Genset Room floor drain still has small pool of water due to clogged floor
drain and leaks on wall.
3. Site tube for Cistern Tank already fix.
4. Transfer Pump Pump A for cluster C still on manual operation. Pump
B not yet operational.
II.
BTO Status
1. Sump Pumps for Genset Room already turned over last November 5,
2015 and accepted last December 3, 2015.
Persons Involve in BTO:
Kenneth Raymundo
TOE PIM
Kevin Cadsawan
TOD TEM
Czariel Lee
PE PTV2
2. Genset Room already turned over last November 5, 2015 but not yet
accepted because flooring not yet epoxy painted. CMT advised FOPM,
flooring not yet epoxy painted because room is still under observation for
leaks.
Persons Involve in BTO:
Kenneth Raymundo
TOE PIM
Czariel Lee
PE PTV2
3. Transfer Pump and Cistern tank already turned over last August 27,
2015 and accepted last September 14, 2015.
Persons Involve in BTO:
Francis Aviso
TOE PIM
Kevin Cadsawan
TOD TEM
III.
IV.
Action Taken
1. Sump pump is subjected to retesting. Sump Pump operates accordingly.
2. Property Engineer submitted Incident report to CMT about the leaks and
clog on Genset room. CMT to remove clog on floor drain and to add
plugging on wall to remove leaks.
3. Property Engineer submitted Incident Report to CMT about the
disconnected Site Tube for Cistern Tank. Site Tube for Cistern tank was fix
by Contractor the same day it was reported. CMT instructed Contractor to
put additional clamp on Site Tube.
4. Transfer Pump Pump B for Cluster C is subjected for replacement of
suction valve by AMICI Supplier.
Photos
Leaks on wall
Annex
a. Annex A Site Observation Report, Reference no.: TEM/Dec.21/Ref.
015
Prepared by:
Noted by: