Project

Employer
Consultant
Contractor
Contract Title
Period Cover

: Administration Building
: Mohamad Al Twaiergi
: Fast Consultancy
: West Gate Contracting
: Finishing Works
: November 07,2015 to November 12,2015

CDRL #: CDRW028

Construction Daily Report Log


Working
Day no.

Date

Total
Manpower at
Site

Activity
01 - Plastering Works - Plastering of Exterior Sides

114

Saturday, November 07, 2015

12

02 - Masonry - Chipping of Concrete wall

Location
Typical Floor
Elevator pit

03 - HVAC - Fabrication of A/C Ducts

115

Sunday, November 08, 2015

13

01 - Structural - Installation of Cladding Structural support

Left Elevation

02 - Cladding works - Installation of Stone Cladding

Back Elevation

03 - Plastering Works - Plastering of Exterior Sides

Typical Floor

04 - Masonry - Chipping of Concrete wall

Elevator pit

01 - Plastering Works - Plastering of Exterior Sides

Typical floor

02 - Structural - Installation of Cladding Structural support


116

Monday, November 09, 2015

28

03 - Cladding works - Installation of Stone Cladding


04 - Fire Fighting - Fire Fighting Modification

Back Elevation
Front Door frame
Basement

05 - Electrical - Fixing of Cable Ladder


06 - Aluminum - Fixing Bottom Edge
01 - HVAC - Check and Inspection for Ducts
117

Tuesday, November 10, 2015

20

02 - Cladding works - Installation of Stone Cladding

Wednesday, November 11, 2015

20

Thursday, November 12, 2015

24

Front Door frame


Typical Floor

04 - Aluminum - Fixing Bottom Edge

Exterior Side

02 - Cladding works - Installation of Stone Cladding

Front Door frame

03 - Plastering Works - Plastering (Interior)

Typical Floor

04 - Aluminum - Fixing Bottom Edge

Exterior Side

01 - Cladding works - Installation of Stone Cladding

119

03 - Plastering Works - Plastering (Interior)

01 - HVAC - Check and Inspection for Ducts


118

Exterior Front Side

Front Door frame

02 - HVAC - Fix Ducts

Typical floor

03 - Plastering Works - Plastering (Interior)

Typical floor

04 - Aluminum - Make silicon for edge

Typical floor

05 - Electrical - Fixing of Cable Ladder

Roof Floor

06 - Fire Fighting - Modification

Basement

Remarks