Beruflich Dokumente
Kultur Dokumente
2.4
=2.58 m
2.Stability on sliding basis
H
B
*G
W
1
P1
W2
S.n
Item
1.
2.
W1
W2
3.
P1
Description and
Force KN
Dimension
Fig: concrete gravity dam
(a) weight of the
Vertical Horizantal
dam
4.2*0.6*24
60.48
0.5*2*3.08*24
73.92
(b) uplift pressure
(c) Water pressure
0.5*3.012*9.81
44.44
Total
134.4
44.44
Lever
arm
2.3
1.33
1.96
237.414
x=
M 150.312
=
=1.12m
V
134.4
e = B/2- x
=0.18<B/6 (Hence safe in Tension)
MR
Overturning factor Ff = MO
Safety against sliding (SFF) =
237.414
=2.73
> 1.5 (Hence stable)
87.102
V 0.75134.4
=
H
44.44
= 1.83
= 30 mm
= 70 mm (Recommended 50-200mm)
= 2m
Now,
Total thickness
N0 of bars required =
Spacing
2000
70
= 29 nos
Now
Tracing angle of inclination from horizontal () = 60 0
Flow deviation in the river ()
= 550
Flow discharge (Q)
= 4800 lps
Ht of trash rack bottom from river bed
=2m
= 4.04m
Adopt length of trash rack = 4 m
Now,
Diameter of settling particles = 11 * RS
= (11 * 0.6*1)/ 300
= 0.022 m
= 22 mm bar diameter of Trash Rack, OK.
Designed Parameters
Diameter of Bar
=30 mm
Spacing of Bar
=70 mm
2 g(hrh h)
= 0.6 *
29.81(1.801.55)
= 1.328 m/s
Q =A* V
= 4.8 * 1.328
= 6.37 m3/s
= 6.77m3/sec > 4.8m3/sec , hence OK..
(The excess flood flow has to be discharged via spillway at the gravel trap.)
Design Parameters:
0.667
Q flood
C w *Wriver
hovertop=
Where Wriver = Lweir + Width of bitch
= 22 + 30 = 52m
3590
1.5 * 52
0.667
hovertop=
= 12.86m
Hence provide 12.86 m flood barrier wall.
( BH )5 / 3 * s1/ 2
n( B 2 H ) 2 / 3
(2 H 2 )5 / 3 * (1 / 300)1/ 2
0.02( 4 H ) 2 / 3
Or , 4.8 =
By hit and trial method,
H = 1.11m
B = 2H = 2 * 1.11 = 2.2 m.
Adopt,
H = 1.2m and B = 2.4 m
As we know, Velocity in canal 0.8 * Critical Velocity
Now,
Q
A
Velocity in canal (V) =
4 .8
1.2 * 2.4
=
V = 1.67 m/s
2 Hg
Critical Velocity =
2 *1.2 * 9.81
=
= 3.43 m/s
Now,
1.67m/s 0.8 * 3.43 m/s = 2.745 m/s
Hence OK.
Now,
Wetted perimeter (P) = 2H + B
= 2 * 1.2 + 2.4
= 4.8 m
A
P
Hydraulic radius (R) =
1.2 * 2.4
4 .8
=
= 0.6 m
Again,
1 2 / 3 1/ 2
R s
n
V=
1
( 0 .6 ) 2 / 3 s 1 / 2
0.02
Or, 1.67 =
1
1
454 300
S = 0.0022
Hence OK.
Provide a free board of 0.5 m.
Designed Parameters:
B = 2.4 m
H = 1.2 + 0.5 = 1.7 m
1: s = 1: 300
b Headrace Canal from Silting basin to Forebay:
Same except the bed slope be 1: 500
Now,
( 2 H 2 ) 5 / 3 * s1 / 2
n( 4 H ) 2 / 3
Q=
(2 H 2 )5 / 3 * (1 / 500)1/ 2
0.02( 4 H ) 2 / 3
Or, 4.8 =
By Hit and trial;
H = 1.22 m
B = 2 * 1.22 = 2.44 m
Adopt;
H = 1.3 m
Free board = 0.4 m
Total height = 1.3 + 0.4 = 1.7 m
B = 1.3 * 2 = 2.6 m
Check for Velocity:
Q
4.8
A 1.3 * 2.6
V=
= 1.42 m/s
V=
1 2 / 3 1/ 2
R *s
n
Or, 1.42=
1 1.3 * 2.6
0.02 1.3 * 2 2.6
s = 0.00143
1
1
698 500
2/3
* s1/ 2
, Hence OK.
Design Parameters:
1 : S = 1 : 500
H = 1.3 m
B = 2.6m
Total Height = 1.3 + 0.4= 1.7 m
Hence OK.
A 0.8
Area (A) =
= 6 m2
Depth of water in the canal (H) = 1.2 m
6
1.2
Width of Gravel Trap (B) =
=5m
Now,
Length of Trap (L) = 3 * Canal width
= 3 * 2.4
= 7.2 m
(Note: For provision of flushing system and accumulation of gravel load, bed of gravel trap
is provided 0.5 m below the bed of the Headrace Canal)
Transition Design:
a For Inlet:
Floor slope () = 11
BTrap BCanal
L inlet =
2Tan
5 2.4
2 * Tan 11
=
= 6.6 m
Again,
b For Exit:
Floor Slope () = 27
BTrap BCanal
2Tan
L Exit =
1.6 1
2Tan 27
=
Designed parameters
= 2.55 2.5 m
Cw * H 1.5
Length of Spillway (L) =
= 4.207 m 4.2 m
Free board = 0.2 m
Size of Spillway:
2Tan
2Tan 13
L Inlet =
L Inlet = 10.17 10 m
b. Outlet:
2Tan
2Tan 25
L Outlet =
= 4.82 m.
Let us adopt 5 m
Depth of settling zone:
D1 / 2
BV 7.1* 0.241
Depth (y) =
= 3.36 m
Let us adopt depth as 3.5 m.
Compute the sediment depth in the basin
Let us adopt the sediment concentration of the 1kg/m3
Detention for the sediment 6 hrs
T = 6* 60 * 60 = 21600 sec
Now,
Theoretical value of the sediment load (in kg )= Q*T*C
S Load
S Density* PFactor
Volume of Sediment =
Volume of Sediment =
= 60 m3
D 3 / 2V
W D 0.132V
4.5 3 / 2 * 0.241
0.02831 4.5 0.132 * 0.241
Basin Dimensions:
L = 40 m
B = 7.1 m
D = 4.5 m
L Inlet = 10 m
L Outlet = 5 m
40.12 40m
1.5v 2
2g
Submergence head (h)s
Now,
hs =
1.5 * 32
2 * 9.81
hs = 0.69 m
Now,
According to Water Conveyance System Design Guidelines DoED
Height of Forebay = hdownsurge + hsub + h dia of penstock + free board
= 1.5 m + 0.69 m + 1.45 m + 0.5 m
= 4.14m
Thus,
Adopt height of Forebay = 4.2 m
Now,
Detention period = 50 sec
Capacity of forebay,
V = Q*t
= 2*4.8*15 (forebay discharge is taken as twice the design discharge)
= 144 m3
Now,
Area of forebay (A) = B*H
= 4*4.2
= 16.8m2
Now,
V
A
Length of Forebay basin =
144
16.8
= 8.57m
Adopt length of Forebay basin = 9 m
Designed parameters
Length of Basin (L) = 9.00 m
Width of Basin (B) = 4.00 m
Height of Basin (H) = 4.20 m
10. DESIGN OF SPILLWAY FOR FOREBAY:
Since free board in Forebay basin is 0.5 m so that
Adopt Head over the spillway crest (H) = 0.7m
For sharp crested weir, weir coefficient (Cw) = 1.7
Now,
We have
Q = Cw*Lspillway*H1.5
or, 2*4.8 = 1.7*Lspillway*(0.7)1.5
Lspillway = 7.5 m
Designed parameters
Length of spillway = 7.5 m
Design of Trash Rack for Forebay
Provide 25 mm circular bars @ 80 mm C/C inclined at an angle of 60 with horizontal
Now,
Width of trash rack (W) = width of Forebay + 40 mm (for groove at side)
= 4.0+0.04
= 4.04m
Now,
Totalwidth
Spacing diameter
Total no of bars =
4040
25 80
=
= 38.48
Now,
Providing the trash rack 10 cm above the bed of the Forebay to allow for deposition
of sediments (if any) and maintaining the top of Forebay
4.2 0.5 0.1
0.02
sin 60
Length of trash rack =
{since 20 mm is provided for slot}
= 4.18 m
Gross Head
= 105 m
4Qd
V
1/ 2
4 * 0.45174
* 3
1/ 2
d=
d = 1.427m 1430 mm
So, Adopt Internal diameter of Penstock Pipe (d) = 1450mm
Now, Calculation for wall loss:
for cast iron, Roughness Value (K) =0.06mm
Now,
K 0.06
d 1450
=
=0.0000413)
VD
Reynolds number = = 4.8*106
Friction factor (f) =0.004
(L =965)
Now,
flv 2
2 gd
Head loss in penstock wall (hwall) =
=
hwall= 1.22m
0.004 * 965 * 32
2 * 9.81*1.45
Now,
Head loss coefficient for intake (Kent) =0.5
Now,
V2
2g
Inlet loss (hinlet) =Kentry*
0.5 * 32
2 * 9.81
hinlet=0.23m
Now,
For bent loss
Bent angle ( )
= 40
Diameter of penstock (d) = 1450mm
Radius of bent (r)
=5m
Now,
r 5000
d 1450
=
=3.45
Now,
K 45 K 20 45 20
K 20 K 40 20 40
0 .2 0 .1
1.25
0.1 K 40
K 40
So,
hBent
= 0.18
32
K Bent *
2 * 9.81
= 0.083 m
Take length of single pipe as 6 m. So total no of joint = 160
K Jo int
= 0.05
n = 160
V2
2g
3.00 2
2 * 9.81
= 3.67 m
1440
1.45 * 9.81 * 2.15 * 10 8
(1
)
0.03 * 78.5 * 10 3
1228.83m / sec
Surge Head
(hSurge )
av 1
*
g n
Where,
n: Total no of nozzles in turbine.
We have, two Francis Turbines with single nozzle each turbine (n = 2*1= 2)
( hSurge )
1228.83 * 3 1
*
9.81
2
= 187.89 m
=
Tc=1.57 sec < 2 sec,so adopt Tc greater than 2 sec
Penstock joints
Thickness of joint = 2*t = 2*30 = 60 mm
At site
Maximum temperature = 30C
Minimum temperature = 1C
Thus,
Temperature Variation (Dt) = 29C
Coefficient of expansion () = 10*10-6/m/C (i.e. for cast iron)
DL = 24 mm
Now,
At installation period
Maximum temperature = 38C
Minimum temperature = 20C
Thus,
Temperature Variation (Dt) = 18C
Now,
Max. Pipe expansion or contraction,
DL = *Dt*L
= 10*10-6*29*6
=0.0017 m
DL = 1.7 mm
Thus,
Adopt joint length = 2*1.7= 3.4 mm
Designed parameters
Diameter of penstock (dp) = 1450 mm
Thickness of pipe material (t) = 30 mm
Time to close valve (Tc) = 5 sec
Length of joint = 3.4 mm
12. DESIGN OF AIR VENT AT THE ENTRANCE OF PENSTOCK:
Design Discharge (Qd) = 4.8 m3/s
Young's modulus of elasticity (E) = 78.5*109 N/m2
Internal diameter of penstock (dp) = 1.45 m
Thickness of penstock pipe (t) = 30 mm
Now,
t
2.0
1.1*1.2
Effective thickness (teff) =
30
2.0
1.1*1.2
=
=20.73 mm
d2 = Q
10
1450 3
*(
)
3
20.73
78.5 *10
= 4800*
= 31692.72 mm2
d = 178.02 mm
Adopt Size of air vent (d) = 180 mm
Designed Parameter
Diameter of air vent (d) = 180 mm
Diameter of turbine = D
We have,
Specific speed (Ns ) =2400/H
= 2400/10
240 rpm
Rotational speed (N) =(Ns*H5/4)/P
= (240*1005/4)/
2459.79
= 1530.25 rpm
Number of pole (P) =120f/N
= 120*50/1530.25
= 3.92
Let us adopt P = 8 (divisible by 4 for head upto 200 m)
Corrected Synchronous speed N = 120f/P
= 120*50/8
=750 rpm
Corrected(Ns) =(NP)/H5/4
=(750
2459.79 )/1005/4
=117.63 rpm
84.6 H
N
Diameter of turbine =
=0.0127Ns2/3+0.0275
= 0.0127*117.632/3+0.0275
= 0.332
Therefore,
D=
84.60.332 100
750
=0.37 0.5 m
Setting of the turbine Hs
c = 0.625
=0.625
Ns
)
380.78
101.67
)
380.78
=0.13
Again,
c = (Ha-Hv-Hs)/H
Hs = Ha-Hv-cH
=10-0-0.13*100
= 3 m ( So turbine axis should set 3 m above the tail water label )
s1/2 = 0.038
s = 0.00143
s 1 in 700
Design summary of tail race