0 Bewertungen0% fanden dieses Dokument nützlich (0 Abstimmungen)
19 Ansichten1 Seite
The document provides cost estimates for infrastructure work for a development project in Santa Rosa, CA. It includes estimated linear feet, quantities, unit costs, and total amounts for roads, sidewalks, water systems, sewer systems, drainage, utilities, and landscaping. The total estimated costs are $203,800 for roads, $176,000 for water, $156,000 for sewer, $180,000 for drainage, $120,000 for utilities, and $804,000 for landscaping.
The document provides cost estimates for infrastructure work for a development project in Santa Rosa, CA. It includes estimated linear feet, quantities, unit costs, and total amounts for roads, sidewalks, water systems, sewer systems, drainage, utilities, and landscaping. The total estimated costs are $203,800 for roads, $176,000 for water, $156,000 for sewer, $180,000 for drainage, $120,000 for utilities, and $804,000 for landscaping.
Copyright:
Attribution Non-Commercial (BY-NC)
Verfügbare Formate
Als PDF, TXT herunterladen oder online auf Scribd lesen
The document provides cost estimates for infrastructure work for a development project in Santa Rosa, CA. It includes estimated linear feet, quantities, unit costs, and total amounts for roads, sidewalks, water systems, sewer systems, drainage, utilities, and landscaping. The total estimated costs are $203,800 for roads, $176,000 for water, $156,000 for sewer, $180,000 for drainage, $120,000 for utilities, and $804,000 for landscaping.
Copyright:
Attribution Non-Commercial (BY-NC)
Verfügbare Formate
Als PDF, TXT herunterladen oder online auf Scribd lesen
Service 20.00 8.00 100.00 16,000.00 Mains 1,000.00 1.00 100.00 100,000.00 Hydrants 1.00 4.00 5,000.00 20,000.00 Other water work 1.00 8.00 5,000.00 40,000.00 Total 176,000.00
SEWER Lin. Ft. Quan. $/Ln. Ft. Amount
Laterals 20.00 8.00 100.00 16,000.00 Main 1,000.00 1.00 100.00 100,000.00 Pump station - 1.00 50,000.00 - Other sewer work 1.00 8.00 5,000.00 40,000.00 Total 156,000.00
DRAINAGE Lin. Ft. Quan. $/Ln. Ft. Amount
Units 100.00 8.00 100.00 80,000.00 Site 1,000.00 1.00 100.00 100,000.00 Other drainage work 1.00 - 5,000.00 - Total 180,000.00
UTILITIES Lin. Ft. Quan. $/Ln. Ft. Amount
Combined utilities 1,000.00 1.00 100.00 100,000.00 PG&E Engineering - 1.00 50,000 - Other utility work 1.00 8.00 2,500.00 20,000.00 Total 120,000.00
LANDSCAPE Units $/Unit Amount
Front & rear yards 1.00 7.00 25,000.00 175,000.00 Common landscape 1.00 1.00 50,000.00 50,000.00 Terraces 2.00 13,800.00 15.00 414,000.00 Specialty trees 10.00 1.00 1,000.00 10,000.00 Retaining Walls 150.00 5.00 100.00 75,000.00 Fencing 1,000.00 1.00 35.00 35,000.00 Other landscaping work 1.00 9.00 5,000.00 45,000.00 Total 804,000.00