FORM IPI 17
CONTRACTOR COMPLETION CHECKLIST
Project
Contract No

Date

Contractor
UNOPS Representative

Item Description

Whom to
Action

Target
Date done
by

Sign Off
Complete and
Dated

Contractor submitted request for Taking Over Certificate?


Taking Over Inspections (Forms IPI 14/15) undertaken
(consider in conjunction with end users)
Local authority/government testing and inspections carried out
UNOPS issue of Take Over certificate (see standard Contract
templates)
Guarantees/Warrantees submitted by Contractor (Form IPI 16)
All required producer statements/ independent certifications
and sign offs submitted
All As-Builts submitted (Form IPI 16)
All final commissioning results received
All spares submitted (Form IPI 16)
Organise and undertake demonstrations and training for plant,
facilities and equipment for the end users
All operational manuals submitted (Form IPI 16)
All temporary services disconnected accounts settled,
permanent services providers to be established by end users
All services metering reading at time of Taking Over recorded
Temporary accommodation, plant and equipment removed and
any commercial arrangements concluded
Handover of all keying, access and building/site security
measures to end users from contractor
Post contract defects procedure and communication process
with contractor and end users established?
Plan/organise and communicate approach to undertake any
deferred or post contract works with end users and contractor
Confirm bond, retention and insurance part/full release, and
restructuring for defects liability are in place
Any contractor review, debriefing, lessons learnt, request for
references etc are organised and auctioned
Other