Start: 29-02-16
ID: 1
Finish: 05-09-16
Comp: 0%
A
Start: Wed 02-03-16ID: 2
Finish: Tue 19-04-16Dur: 42 days
Res:
D
Start: Wed 02-03-16ID: 5
Finish: Thu 05-05-16Dur: 56 days
Res:
Page 1
E
Start: Mon 29-02-16ID: 6
Finish: Wed 23-03-16Dur: 21 days
Res:
Page 2
B
Start: Wed 20-04-16ID: 3
Finish: Mon 30-05-16Dur: 35 days
Res:
J
Start: Thu 16-06-16 ID: 11
Finish: Fri 19-08-16 Dur: 56 days
Res:
C
Start: Wed 20-04-16ID: 4
Finish: Sat 21-05-16 Dur: 28 days
Res:
F
Start: Fri 06-05-16 ID: 7
Finish: Sat 21-05-16 Dur: 14 days
Res:
G
Start: Mon 23-05-16ID: 8
Finish: Mon 18-07-16Dur: 49 days
Res:
Page 3
H
Start: Fri 06-05-16 ID: 9
Finish: Wed 15-06-16Dur: 35 days
Res:
L
Start: Thu 16-06-16 ID: 13
Finish: Tue 26-07-16Dur: 35 days
Res:
Page 4
I
Start: Tue 19-07-16 ID: 10
Finish: Sat 27-08-16 Dur: 35 days
Res:
K
Start: Tue 19-07-16 ID: 12
Finish: Mon 05-09-16Dur: 42 days
Res:
Page 5
Page 6
Project: Project1
Date: Wed 02-03-16
Critical
Summary
Critical External
Noncritical
Critical Inserted
External
Critical Milestone
Inserted
Project Summary
Milestone
Critical Marked
Highlighted Critical
Critical Summary
Marked
Highlighted Noncritical
Page 7