FPSO Offshore Execution

Week Ending 31 Mar-06

Nigeria OPL 209


PROPRIETARY

First Oil 27 March-2006


Drill Center East
Well Startup Sequence
Opened PE15 Well: 8:15 am
Opened PE 18 Well: 9:15 am
Flowing through 6 in. Test Riser
First Oil Received onboard the
FPSO at 10:40 am March 27, 2006

6 in. Test Riser

Drill Center East - Risers

FPSO Offshore Execution


Week Ending 31 Mar-06

Nigeria OPL 209


PROPRIETARY

Valve Lineup to Test Separator

Verifying Separator Levels

FPSO First Oil 27 March 2006

Nigeria OPL 209


PROPRIETARY

First Oil in Separator 10:40 am

Crude to Cargo Oil Tank 4


Center

FPSO Offshore Execution


Drill Center West SCR Completion
Approaching
FPSO SIMOPS
Zone (500 Meter)

Nigeria OPL 209


PROPRIETARY

DLB Seaway Polaris Laying


DCW 10 In. Production SCR
towards FPSO

Riser Pull in
system ready
M/V Milton McCall
for Handoff to
FPSO

FPSO Offshore Execution


Week Ending 31-Mar-06

Nigeria OPL 209


PROPRIETARY

Multi-Purpose Pump Opened for Plunger


inspection after riser pigging

Preparing HP Gas
Compressor No. 2 for
Commissioning

FPSO Offshore Execution


Week Ending 31-Mar-06

FPSO Flare Ignition 31 March 2006

Nigeria OPL 209


PROPRIETARY

FPSO Offshore Execution


Week Ending 31-Mar-06

Nigeria OPL 209


PROPRIETARY

Arrival of the PO1B Replacement


Jumper to Onne Quay via Panelpina
Trailers

Load out of the PO1B Replacement


Jumper onto the CB19 in Onne