Drill Center East Well Startup Sequence Opened PE15 Well: 8:15 am Opened PE 18 Well: 9:15 am Flowing through 6 in. Test Riser First Oil Received onboard the FPSO at 10:40 am March 27, 2006
6 in. Test Riser
Drill Center East - Risers
FPSO Offshore Execution
Week Ending 31 Mar-06
Nigeria OPL 209
PROPRIETARY
Valve Lineup to Test Separator
Verifying Separator Levels
FPSO First Oil 27 March 2006
Nigeria OPL 209
PROPRIETARY
First Oil in Separator 10:40 am
Crude to Cargo Oil Tank 4
Center
FPSO Offshore Execution
Drill Center West SCR Completion Approaching FPSO SIMOPS Zone (500 Meter)
Nigeria OPL 209
PROPRIETARY
DLB Seaway Polaris Laying
DCW 10 In. Production SCR towards FPSO
Riser Pull in system ready M/V Milton McCall for Handoff to FPSO
FPSO Offshore Execution
Week Ending 31-Mar-06
Nigeria OPL 209
PROPRIETARY
Multi-Purpose Pump Opened for Plunger
inspection after riser pigging
Preparing HP Gas Compressor No. 2 for Commissioning