Beruflich Dokumente
Kultur Dokumente
1 Structural Design
Introduction
Structural engineering is the design of structural
elements and their connections that work together to
support loads and maintain stability within a system.
Structures vary by application and can range in
scale from complex bridge designs to massproduced cell phone enclosures. Regardless of the
structures scale or purpose, all structures are
designed to meet specific design criteria, including
operational environment, durability, aesthetics,
internal and external load handling, and cost. To
ensure that the optimal structural design is achieved
engineers with diverse backgrounds (e.g., material
science, statics, etc.) work together throughout the
design process. To aid engineers in the development
of complex structural design, computer-aided design
packages are used for design analysis and
verification.
Equipment
Engineering notebook
Research sources
Procedure
Your team will design and create a bridge utilizing West Point Bridge Designer
software. West Point Bridge Designer is a simplified and scaled down computeraided design tool developed by Colonel Stephen Ressler, Department of Civil and
Mechanical Engineering, U.S. Military Academy, West Point, New York. The software
will allow you to apply engineering design, material science, and statics to the design
of a truss bridge carrying a two-lane highway that spans a riverbed.
Design Constraints
o To provide clearance for overhead power lines, the highest point on the
bridge may not exceed an elevation 32.5 meters above the high water
level (8.5 meters above the top of the riverbanks).
o The bridge substructure may consist of either standard abutments (simple
supports) or arch abutments (arch supports). If necessary, the bridge may
also use one intermediate pier, located near the center of the valley. If
necessary, the bridge may also use cable anchorages, located 8 meters
behind one or both abutments.
o Each main truss can have no more than 50 joints and no more than 120
members.
o The bridge will have a flat, reinforced concrete deck. Two types of
concrete are available:
Medium-strength concrete requires a deck thickness of 23
centimeters (0.23 meter).
High-strength concrete requires a deck thickness of 15 centimeters
(0.15 meter).
In either case, the deck will be supported by transverse floor beams
spaced at 4-meter intervals. To accommodate these floor beams,
your structural model must have a row of joints spaced 4 meters
apart at the level of the deck. These joints are created automatically
within West Point Bridge Designer.
o The bridge deck will be 10 meters wide, such that it can accommodate two
lanes of traffic.
Member Properties
o MaterialsEach member of the truss will be made of either carbon steel;
high-strength, low-alloy steel; or quenched and tempered steel.
o Cross SectionsThe members of the truss can be either solid bars or
hollow tubes. Both types of cross sections are square.
o Member SizeBoth cross sections are available in a variety of standard
sizes.
The bridge must be capable of safely carrying the following loads:
o Weight of the reinforced concrete deck.
o Weight of a 5-cm thick asphalt wearing surface, which might be applied at
some time in the future.
o Weight of the steel floor beams and supplemental bracing members
(assumed to be 12.0 kN applied at each deck-level joint).
o Weight of the main trusses.
o Either of two possible truck loadings:
1. Weight of one standard H25 truck loading per lane, including
appropriate allowance for the dynamic effects of the moving load.
Since the bridge carries two lanes of traffic, each main truss must
safely carry one H25 vehicle, placed anywhere along the length of
the deck.
2. Weight of a single 480 kN Permit Loading, including appropriate
allowance for the dynamic effects of the moving load. Since the
Permit Loading is assumed to be centered laterally, each main
truss must safely carry one-half of the total vehicle weight, placed
anywhere along the length of the deck.
2012 Project Lead The Way, Inc.
Principles of Engineering Problem 2.4.1 Structural Design Page 2
The bridge will comply with the structural safety provisions of the 1994 LRFD
AASHTO Bridge Design Specification (Load and Resistance Factor Design), to
include:
o Material densities
o Load combinations
o Tensile strength of members
o Compressive strength of members
Cost Calculations
The cost of the design will be calculated using the following cost factors:
Material Cost:
o Carbon steel bars$3.78 per kilogram
o Carbon steel tubes$6.30 per kilogram
o High-strength steel bars$4.62 per kilogram
o High-strength steel tubes$7.03 per kilogram
o Quenched and tempered steel bars$5.70 per kilogram
o Quenched and tempered steel tubes$7.95 per kilogram
o Connection cost$300.00 per joint
o Product cost$1000.00 per product
Site Cost:
o Reinforced concrete deck (medium strength)$4,850 per 4-meter panel
o Reinforced concrete deck (high strength)$5,500 per 4-meter panel
o Excavation$1.00 per cubic meter (see the Site Design Wizard for
excavation volume)
o Supports (abutments and pier)cost varies (see the Site Design Wizard
for specific values)
o Cable Anchorages$6,000 per anchorage
Explore West Point Bridge Designer Software
1. Launch
West Point
Bridge Designer
Application.
2. Select
Create a New
Bridge Design.
Select OK.
3. Read the
design
requirements
overview.
Select Next.
4. Under local
contest code,
select No.
Select Next.
5. Explore and
investigate the
impact of deck
elevation and
support
configurations
related to the
Site Cost by
completing the
deck elevation,
arch abutment,
pier, and cable
anchorages cost
impact tables.
Deck
Elevation
24 meters
20 meters
16 meters
12 meters
8 meters
4 meters
0 meters
Deck
Elevation
24 meters
24 meters
24 meters
24 meters
24 meters
24 meters
Deck
Elevation
24 meters
24 meters
24 meters
24 meters
24 meters
20 meters
16 meters
12 meters
Cable
Anchorages
No
No
No
No
Site Cost
$62,700
$77,400
$88,400
$100,700
$110 ,400
$123,700
$134,000
Site Cost
$89,700
$83,500
$81,800
$80,800
$83,300
$80,200
Site Cost
$104,000
$101,200
$98,400
$95,600
24 meters
24 meters
24 meters
Deck
Elevation
24 meters
24 meters
24 meters
6.
Standard
Standard
Standard
8 meters
4 meters
0 meters
No
No
No
$92,800
$90,000
$87,200
Site Cost
$62,700
$65,700
$68,700
Select:
7. Explore and investigate the impact of deck material and truck loading
configurations related to the Site Cost by completing the deck material and truck
loading cost impact tables.
Site Cost
$68,700
$68,700
$73,100
$73,100
Se
ect
9.
Select Next.
10. Type your engineering team name into the Designed By field.
Type Exploring into the Project ID field.
Select Finish.
14. The Member Properties window provides you with detailed information related to
the currently selected member. Notice that the material type, cross section type, and
cross section size relate to the selected material in the toolbar. If you change the
member properties within the toolbar, the Member Properties Report will also change.
Investigate the different member properties by completing the member Material
selection comparison, member Cross Section Type comparison and member Cross
Section Size comparison.
Material
Carbon
Steel
Cross
Section
Type
Solid Bar
HighStrength
Solid Bar
Quench
ed
Solid Bar
Material
Carbon
Steel
Carbon
Steel
Material
Carbon
Steel
Cross
Section
Type
Solid
Bar
Carbon
Steel
Solid
Bar
Carbon
Steel
Solid
Bar
Carbon
Steel
Solid
Bar
Moment
of Inertia
Cost per
Meter
5.46E-5
meters^4
$864.13
5.46E-5
meters^4
$1125.38
5.46E-5
meters^4
$1205.76
Moment
of Inertia
Cost per
Meter
5.46E-5
meters^4
$864.13
1.88E-5
meters^4
$240.55
Moment
of Inertia
Cost per
Meter
6.75E-8
meters^4
$30.38
5.46E-5
meters^4
$864.13
1.40E-3
meters^4
$4374.65
5.21E-3
meters^4
$8438.75
meter
Title Page: Include the title of the project, a picture of your final bridge design
and team members, team member names, course title, name of your school, and
the date.
Design Brief: Include a description of the problem and constraints.
Research Summary: Summarize your research related to material selection and
bridge truss design. The research summary should be less than one page.
Brainstorming Sketches/CAD Designs: Include copies or originals of your
teams brainstorming sketches and CAD designs.
Modification Sketches: Include copies or originals of all major modifications.
Final Bridge Design: Include copies or originals of the final design, including the
following reports: load test results report, member property reports for all member
styles used, and cost calculations report.
Final Design Justification: Include justification for material selection and truss
configuration.
2012 Project Lead The Way, Inc.
Principles of Engineering Problem 2.4.1 Structural Design Page 13
References: Use APA format to list all sources that were used to complete this
activity.
Conclusion Questions
1 How does the type and direction of stress applied affect the selection of the
material type and the cross-sectional area?
The more beams you put into the design the cross sectional area increases and
the stress is put unto the weakest beam and so on.
21. How can the forces of compression and tension work together to make a
stronger bridge?
Compressing in areas and tension in others. An example is when a bridge that
has a beam that has too much tension and is about to break, you can put a beam
that compresses and balances out tension and compression.