Sie sind auf Seite 1von 9

BRIGHT ELECTRICAL WORKS LLC

72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY


METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

S.
No.

Date

Description

12-03-2014 Method Statement for


Electrical
Conduiting
concealed in wall.

8/8

Prepared by

Checked by

Mr. Naufal
Nazim

Mr. Sharkawy

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

CONTENTS

1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. SAFETY
6. RESPONSIBILITIES
7. PROCEDURE
8. QA/QC PROCEDURE
9. ATTACHMENTS

8/8

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

1.PURPOSE

To ensure that installation of Electrical Conduiting Concealed within the wall are
executed safely and in accordance with the contract requirements and that all
quality assurance / control activities required for the same are conducted in a
systematic manner, works are inspected and conformance is verified and
documented.

2.SCOPE OF WORKS/METHOD
2.1 This procedure is applicable to the following works associated with the project
titled 72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY

Electrical Conduiting Concealed within the wall

3. REFERENCES
3.1 Approved material submittals:

PVC Conduits & Accessories

3.2Latest Approved Shop Drawings


3.3Inspection and Test plan.

8/8

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

DEFINITIONS
4.1 EMPLOYER:

JARVIS CORPORATION

4.2 ENGINEER:

DIAR CONSULTANT

4.3 CONTRACTOR:

BHATIA GENERAL CONTRACTING CO. L.L.C.

4.4 MEPCONTRACTOR:
4.5 PROJECT:

HEALTH, SAFETY AND ENVIRONMENT

4.7 ITR:

INSPECTION TEST REQUEST

4.8 ITP:

INSPECTION AND TEST PLAN


QUALITY ASSURANCE / QUALITY CONTROL

SAFETY

72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY

4.6 HSE:

4.9 QA/QC:

BRIGHT ELECTRICAL WORKS EST LLC

Tool box talk has to be conducted all the hazards have to be identified before
starting the work.
Personnel Protective Equipments (PPE) to be worn by the Task force during
execution at site.
Clear the obstructions from the surrounding area to avoid Near misses and
accidents.
Manufacturers recommendation has to be followed on health and safety if
applicable.
Any Process adopted and may have a particular safety risk will be assessed
and addressed as required.

RESPONSIBILITIES
6.1

Project Engineer
To be the focal point for interfaces and other communications with the
ENGINEER and Contractors as required during execution of work.
He shall ensure that adequate quality measures are being undertaken.
He shall ensure that the proper tools and tackles are available for the timely
completion of the job in a quality manner.
8/8

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

He shall ensure all inspection are conducted as per the contract specifications

and ITPs. To ensure all inspections, proper tools & tackles and manpower are
used at all stages of work. To ensure all current issues of procedures,
Approved Material and shop drawings and standards are available at the
point of use. He should also ensure the works complies with the contract
requirements / approved shop drawings. He shall be responsible for the total
quality control for installation work. He shall liaise with ENGINEER for
inspection of installations works.

Inspect for any damage during, handling and storage.


Monitor the quality of work & ensure that fulfillment of specified requirement

and that all quality records related to work are completed.

Ensure the work is completed as per quality requirements. Contractor shall

inspect the same work prior to initiate ITR for ENGINEER approval.
Maintain

Comprehensive inspection and test records for any further


documentation.

Reviews the Method Statement before starting the work, explains the same
to the subordinates and prepares program for the daily job. Aware of all code
of practices, Standards & Specifications and HSE plan and to appreciate the
workforce to perform a time bound and quality job.
He shall originate ITR for completed installation works and companies.
6.3

Site Foreman (Electrical)


Checks the locations and the dimensions of the pipes.
Checks the sizes and the slope of the pipes.
Checks with the approved shop drawings.

PROCEDURE
7.1

Equipments:
Standard Tools - Grinding machine, Chisel, Hammer, Hack saw, File, etc.

7.2

Handling
During transportation pipes must not be handled roughly. This is particularly
so when they are in contact with hard surfaces. Dropping from a height or
8/8

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

dragging them from one place to another may damage the pipes and make
them unsuitable for use, particularly when the pipe ends have already been
prepared for installation.
Use improper machinery / handing equipment for lifting or moving pipes must
be avoided at all times.
Where mechanical handling equipment is used, it should be insured that any
metallic implements do not come in direct contact with the pipes. Fibrous
material like ropes and web slings are ideal for such purposes, as they will
not damage the pipe walls. Before installations, pipes and fittings should be
minutely examined for any structural damage.
7.3

Transportation:
The transporting vehicle must ideally have a flat bed, free for any rough
surfaces or corrugation.
Overhanging of pipes from bed of the transporting vehicle must not exceed 1
meter, must be evenly supported and should be loaded with sockets aligned
at alternate ends. Heavier and large pipes must always be loaded first, with
proper side supports.

7.4

Storage
Pipe should be stacked on a flat base or level ground. Pipe stack should

contain one size diameter only. If this is not possible the largest diameter
should be sheeted with an opaque material.

The pipes should not be in direct expose of the sunlight to avoid ultraviolet

degradation. Even if the pipes where covered the stack should be in


minimum height under high ambient temperature.
7.5

Site Work:

7.5.1

Electrical Conduiting Concealed within the wall

Check that the Shop Drawings are approved and available at site.
Check the materials and confirm all items with the Material Approval.
Mark on the wall at proper location to place the conduit.
Cut and chase the wall. Cutting to be done with the grinder.
Place the conduits as per the requirement.
Tight the conduit to avoid any damage.

8/8

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

Ensure the following:


Conduiting is done as per approved shop drawing and approved
materials.
Sharp bends are not done on conduiting.
There are no any damage on the conduits after laying.
Pull wires are used inside the conduiting.
Protect the conduit ends to prevent the entry of any foreign materials
Arrange for inspection of the installation.
Co-ordinate with the Main Contractor to cover the conduits.
8

QA/QC PROCEDURE
All inspection / Testing as defined in related Inspection and Test Plan (ITP) shall
be conducted. Related check sheets shall be completed.

8/8

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL

ATTACHMENTS

9.1

CHECK LIST FOR INSTALLATION OF ELECTRICAL CONDUITING CONCEALED WITHIN


THE WALL

Electrical Conduiting Concealed within the Wall


Drawing No:

Report No:

Location:

Date:

SL.
NO

CHECK LIST FOR INSTALLATION


OF ELECTRICAL CONDUITING
CONCEALED WITHIN THE WALL

STATUS

Accepte
d

1.

Check that the material is as


per approved submittal.

2.

Marking the location of points.

3.

Wall cutting.

4.

Check the location of points.

5.

Installation of conduit.

6.

Check the pipe work against


any damages.

Date

SubContract
or

Rejecte
d

Contract
or

Consulta
nt

BHATIA

DIAR

Remark
s

REMARKS:

APPROVALS

For SUB- CONTRACTOR

For CONTRACTOR

8/8

For CONSULTANT

BRIGHT ELECTRICAL WORKS LLC


72 GALLERY TOWNHOUSES PHASE 2 IN DUBAI SPORTS CITY
METHOD STATEMENT FOR ELECTRICAL CONDUITING CONCEALED IN WALL
SITE ENGINEER
(ELECTRICAL)

QA/QC

SIGNATURE
NAME
DATE

8/8

DIAR

Das könnte Ihnen auch gefallen