Important Key dates, liase Ahead

Date

Platform 4
LV power turn on to SWC isolators at New LRT Platform 4
Handover of High Covered Linkway to Lot 1 (A&A)
Completion of Covered Linkway between New Side LRT Platform 4 & Commercial Bldg
Completion of New LRT Platform 4 (Incl. TOP)

30-Dec-15*
30-Mar-16*
30-Mar-16*
30-Mar-16*

Platform 3
Basic Structure Completion - New LRT Platform 3
LV power turn on to SWC isolators at New LRT Platform 3
Completion of New LRT Platform 3 (Incl. TOP)

30-May-16*
30-Jul-16*
31-Oct-16*

Completion of the Whole of the Works

31-Oct-16*