Fast TOC
How to Implement CCPM & DBR
In One-Third of the Time
With Team Buy-In
The Premise
Assumption: We have enough application knowledge to last
the next 20 years.
The constraint of any TOC implementation is the speed:
To fully implement
To get top management and implementation team buyin
For the organization to absorb knowledge
All of the above impacts the time needed to get bottom line
results
www.tocpractice.com
CCPM Pre-work
1. Data Gathering: Prove the benefits, get ammunition for
top management.
2. Top Management Buy-In: 4 hours, I use a combination of
Vision (based on past results), Statistics (Exepron
Simulators) and Multitasking Exercise.
3. CCPM Training: Maximum 1 Day. Dont kill them with
everything you know, just enough to get started.
4. Homework for top executive:
www.tocpractice.com
Synchronization
Resource Pools
Software
What if Analysis
Buffering
Software updates
Software reporting
Organization Team
Fast Track Issue Resolution
Daily Updating
Full Kit
Project Recovery
Freeze
Synchronization control
Task assignment
Resourcing of projects
CCPM Day 1
1. 4-8 Hours Network Building First Project: They are
already implementing their first project on Day 1!
2. Activate the project in Exepron.
3. If the Project Manager is not on the implementation team,
train them to do the daily updates and provide feedback
(30 minutes).
4. Both the Technical and Organization Teams participate,
since the first step of Network Building requires Full Kit,
stakeholder goals, scope and tangible success criteria,
impact on T, I, OE.
See Advanced Multi-Project Management Kendall & Austin
www.tocpractice.com
CCPM Results
1. 1998 My First CCPM Implementation 8 months, half
the time struggling with software.
2. 2009 - Many implementations later 4 months, painful
S&T, still struggling with software, batch updates, all
technical work done by consultants for first 3 months.
3. 2016 Live on Day 2 with one project, big learning curve
starts on Day 2 and builds, Client does all the software
work from Day 1 with no formal software training, Full
Live within 2 months.
www.tocpractice.com
CCPM Results
Thanks for the great recap and what I believe has been a great
growth and learning experience for the Project Team at Helion.
Your commitment to our successful implementation is inspiring.
Knowing the team, I am sure that they have all thanked you for
bringing this new way of operating to us. However, let me thank
you as well on behalf of all of us you have most certainly
exceeded our expectations.
Erik Nachbar, President, Helion Technologies
February 2016
www.tocpractice.com
Whole
Pain/Purpose $/
Base / Plan /
Buy-In
www.tocpractice.com
Parts
Plan Plan/
Process/Metrics/
R&Rs
Whole
Approval/ Scary
Date/ Audit/
Improve
Whole
Pain/Purpose $ Base - Go/ Team
Buy-In / Plan
Understand the
Pain
HELP !!
Whole
Parts
Plan Plan/ Process/
Metrics/ R&Rs
Purpose $Base- Go
Approval/ Scary
Date/
Audit/Improve
Team Buy-In training/ Implementation Plan- review
Phone calls
with ops
leader; day
visit (maybe)
www.tocpractice.com
Purpose/ go
1 Day
with Staff
3 Days
Whole
Pain/Purpose $/
Plan/ Buy-In
Current
State/As-IS
Current System
Future/To-Be
Metrics/R&Rs
/ IT
Parts
Plan Plan/Process /
Metrics/R&R
Design Approval
Whole
Approval/ Scary
Date/ Audit /
Improve
Sustain Audits/
Improve
1 Week
www.tocpractice.com
1 Week
1 Week
1 Week
2 days
Whole
Pain/Purpose $/
Plan/ Buy-In
Base Training
Current
State/As-IS
Current System
Whole
Parts
Plan Plan/Process /
Metrics/R&R
Future/To-Be
Metrics/R&Rs
/ IT
Design Approval
Approval/ Scary
Date/ Audit /
Improve
Sustain Audits/
Improve
FAST alignment:
DBR Process Swim Lane
Whole
Pain/Purpose $ Base - Go/ Team
Buy-In / Plan
Base
Training
Current
State/As-IS
Current
System
Future/To-Be
Metrics/R&Rs
/ IT
Whole
Parts
Approval/ Scary
Date/
Audit/Improve
Design
Approval
Design
"Turn on"
Sustain Audits/
Improve
Step 1;2;3.
T + 30%; I- (25%); OE- (0)
Go LIVE 4/26
Design approved
Additional training
Metrics changed
Policies; R&Rs updated
IT / support working
Valium script filled
FocusedSustainable
Bottom Line impact
Audit--Improve
Approval/ Date
3-4 Days
www.tocpractice.com
3-6 weeks
2 days
www.tocpractice.com
We all know,
Question is why more
companies arent taking
this path to great results
After a successful implementation, what next ?
www.tocpractice.com
www.tocpractice.com
Questions
www.tocpractice.com