Sie sind auf Seite 1von 1

PSC NEWS

Missouri Public Service Commission


Contact: Kevin Kelly
FY-16-121

Phone: (573) 751-9300

FOR IMMEDIATE RELEASE

Governor Office Building, Suite 600

APRIL 27, 2016

PSC ISSUES DECISION IN ATXI TRANSMISSION LINE CASE


JEFFERSON CITY---The Missouri Public Service Commission has approved an application
filed by Ameren Transmission Company of Illinois (ATXI) seeking a certificate of convenience and
necessity (CCN) to construct a 95 mile electric transmission line (known as the Mark Twain Project)
in northeast Missouri. As part of its decision, the Commission has imposed a condition whereby
ATXI would need to acquire county commission permissions (assents) before the certificate takes
effect. The Commissions vote was 5-0.
ATXI does not have assent from any of the counties through which Mark Twain would run,
said the Commission. ATXI must get assent from each county through which Mark Twain would
run before the certificate becomes effective. The Commission believes the plain language of
229.100 RSMo and its own rules require as much. If, however, a reviewing court determines that
229.100 RSMo does not require ATXI to obtain these assents, this condition will, of course, be null
and void.
The Commission, based upon the evidence in the case, determined that ATXI has shown it is
entitled to a CCN. ATXI has shown a need for Mark Twain, qualifications to own and operate it, the
financial ability to build it, the economic feasibility of building it, and the public interest that would
be served by building it. Notably, there is a benefit to Missouri ratepayers if this CCN is granted.
The Commission determined in this case that the project is in the public interest because it is
needed to: 1) Promote grid reliability; 2) Relieve congestion; 3) Promote renewable energy; 4) Meet
local load serving needs; and 5) Provide downward pressure on customer rates.
The Commission has great sympathy for the affected individual landowners, particularly
those in the Amish and Mennonite communities who have certain values and beliefs that are in
conflict with the project, said the Commission. But the Commission must balance the direct but
narrow property interests of a few against the indirect but broad economic and environmental
interests of the general public.
The ATXI 345-kV electric transmission line (the Mark Twain Project) is approximately 95
miles in length, running from the new Maywood Switching Station near Palmyra, Missouri, through
Marion, Shelby, Knox and Adair counties to the new Zachary Substation, located near Kirksville,
Missouri. The transmission line would then continue north through Adair and Schuyler counties to
the Iowa border. ATXI would also have a 2.2 mile 161-kV connector line, a substation and related
facilities.
The Mark Twain Project stems from a study conducted by Midcontinent Independent System
Operator, Inc. (MISO). In 2008, MISO began an extensive study of the regional electric transmission
grid to identify transmission needs and develop a planning process to construct transmission projects
to meet those needs.
In 2011 and updated in 2014, MISO identified a multi-value portfolio (MVP) of 17
transmission projects that would increase the overall reliability and efficiency of the regional
transmission grid, meet public policy demands for renewable energy, and provide economic benefits
in excess of the portfolio costs. ATXIs Mark Twain Project consists of the Missouri portion of two
of those MVP projects.
-30Case No. EA-2015-0146

Das könnte Ihnen auch gefallen