Sugarlandia
juwi Confidential
TABLE of CONTENT
1. Project Snapshot
Introduction
Site Locations
2. Project Development
Project Development
Site Pictures
3. Technical Package
Soil & Flood Studies
Layout and Topo studies
Energy Yield Analysis
4. Commercial Package
Development Fee Proposal
Project Snapshot
Introduction 1/2
One site with 3 adjacent land owners up to 154 hectares that have been secured in Negros Occidental
Service Contract received Blocked ~800ha; ECC permit obtained
Preliminary Facility Study Grid received
Grid Impact Study / System Impact Study conducted and preliminary results received 50 MWp
PV Power plant to be connected to the NGCP 69 kV or 138 kV for capacity above ~ 60 MWp
No right of way needed. Direct access to 69 kV transmission line on site (north east plots)
All sites have DAR Certificate of Exemption and/or Notice of Non-Coverage
Non irrigated land, to date used for sugar cane plantation
All sites have proper land titles
Topography, Flood and Soil studies have been conducted and all sites are solar ready
Landlords and local LGUs are very supportive of the project
Project Snapshot
Introduction 2/2
Land lease option terms have been agreed 25yr lease ; Lease contract renewable
Average PHP 75k per hectare per annum excluding taxes
10% escalation every 5 years
Landlords are prominent local businessmen/politician with
good standing in society
Substation and Transmission lines have adequate capacity
for all solar plants (site approx. 1.5km direct line from the
NGCP substation or by road 4.5km)
Clean SPV set up for the project
No coconut trees
Sites locations
Project Development
Site Pictures
Technical Package
Site layout & Topographical studies
Currently planned with 50 MWp, design on left shows up to 61MWp
69kV transmission line shown in red on east corner of upper plot
juwi conducted extensive site selection and engineering and project is
construction ready from engineering perspective
Topographical & hydrological studies for all sites conducive
Availability of local labor and construction assets
Technical Package
Soil & Flood Studies
Flood and Soil studies for all sites have been
conducted
There is no flood risk on any site
Soil conditions are good
Initial screw pile solution has been identified
Technical Package
Energy Yield Analysis
The
yield
carried
out
analysis
was
with
the
by SolarGIS.
A degeneration of 0.7% per
year of the initial first year
simulated
calculated.
output
can be
Ms Maricel Monfort
Founded in 1996
Proposal
Expansion - Exclusivity
Total MWp
50 MWp
Scenarios
BASE CASE
UPSIDE CASE
~US$ 1MM
Issuance of NTP
Commercial Operation
Milestones