Beruflich Dokumente
Kultur Dokumente
400/220 kV TRANSMISSION
SUBSTATION
OPERATED BY:
MADE BY:ADITYA BALUNI
120070105132
B.TECH ELECTRICAL ENGINEERING
DEHRADUN INSTITUTE OF TECHNOLOGY DEHRADUN
SUBMITTED TO:
Mr. DIGAMBAR
Assistant Professor
1
ACKNOWLEDGEMENTS
"Gratitude is not a thing of expression; it is more a matter of feeling."
TABLE OF CONTENTS
S.NO.
1.
2.
2.a)
2.b)
2.c)
2.d)
2.e)
2.f)
2.g)
2.h)
3.
3.a)
3.b)
3.c)
3.d)
3.d.1)
3.d.2)
3.d.3)
3.d.4)
3.d.5)
3.d.6)
3.d.7)
3.d8)
3.d.9)
CONTENTS
INTRODUCTION
ABOUT CORPORATION
OBJECTIVES
VISION
MISSION
Electrical Substation
Introduction
Functions of a Substation
Classifications of Substations
Substation Site Selection
Substation Parts and Equipment
Substation Protection
Formation of Substation Earthing
Lightning Protection
Overview of 400/200kv Substation Dehradun
Brief about Project
Scope of Project
AIS
Component at Site
Lightning Arrester
Capacitive Voltage transformer
Wave Trap
Gantry
Current Transformer
Disconnector
Circuit Breaker
Bus Reactor
Auto Transformer
3
PAGENO.
5
5
6-7
8
8
9-25
9
10-11
11-15
15
15-17
17-20
20-22
22-25
26-64
26
26-28
28-29
29
29-32
32-35
35-36
36
36-40
40-43
44-53
53-55
56-64
4.
4.1)
4.2)
4.3)
4.4)
4.5)
4.6)
4.7)
4.8)
4.9)
5.
Miscellaneous
Insulator
Conductor
Corona Ring
65-77
65
65-69
69-70
70-71
71
71-73
74
74-75
75-77
78
OLTC in Transformer
Marshaling Box
Switching Scheme
Bus Coupler
PLCC
SCADA
Conclusion
1. INTRODUCTION
ABOUT CORPORATION:
The Power Grid Corporation of India Limited a Navaratna Central Public
Sector Enterprise (POWERGRID), is an Indian state-owned electric utilities
company headquartered in Gurgaon, India. POWERGRID transmits about 50%
of the total power generated in India on its transmission network. Power
Grid Corporation of India Limited (POWERGRID) was
incorporated on October 23, 1989 under the Companies Act,
1956 with an authorized share capital of Rs. 5,000 Crore
(subsequently enhanced to Rs. 10,000 Crore in Financial Year
(FY) 2007-08) as a public limited company, wholly owned by
the Government of India.Its original name was the 'National Power
Transmission Corporation Limited', and it was charged with planning,
executing, owning, operating and maintaining high-voltage transmission
systems in the country. On 8 November 1990, the National Power Transmission
Corporation received its Certificate for Commencement of Business. Their
name was subsequently changed to Power Grid Corporation of India Limited,
which took effect on October 23, 1992.POWERGRID started functioning on
management basis with effect from August, 1991 and subsequently it took over
transmission assets from NTPC, NHPC, NEEPCO, NLC, NPC, THDC, SJVNL
etc. in a phased manner and it commenced commercial operation in 1992-93. In
addition to this, it also took over the operation of existing Regional Load
Dispatch Centers (RLDCs) from Central Electricity Authority (CEA), in a
phased manner from 1994 to 1996, which have been upgraded and modernized
with State of-the-art Unified Load Dispatch and Communication (ULDC)
schemes. Consequently, National Load Dispatch Centre (NLDC) was
established in 2009 for overall coordination at National level. According to its
mandate, the Corporation, apart from providing transmission system for
evacuation of central sector power, is also responsible for Establishment and
Operation of Regional and National Power Grids to facilitate transfer of power
within and across the Regions with Reliability, Security and Economy on sound
commercial principles. Based on its performance POWERGRID was
5
OBJECTIVES :The Corporation has set following objectives in line with its
mission and its status as Central Transmission Utility to:
Undertake transmission of electric power through Inter-State
Transmission System.
Discharge all functions of planning and coordination relating
to Inter-State Transmission System with State Transmission Utilities
Central Government
State Government
Generating Companies
6
and
Maintenance
of
Transmission
distance
Trunk
Telecommunication
VISION : Keeping pace with changing business environment, POWERGRID had set
its Vision and aligned its mission and objectives as a vanguard of foresight.
7
MISSION :We will become a Global Transmission Company with Dominant Leadership in
Emerging Power Markets with World Class Capabilities by:
World Class: Setting superior standards in capital project management and
operations for the industry and ourselves
Global: Leveraging capabilities to consistently generate maximum value for all
stakeholders in India and in emerging and growing economies.
Inspiring, nurturing and empowering the next generation of professionals.
Achieving continuous improvements through innovation and state of the art
technology.
Committing to highest standards in health, safety, security and environment
2. ELECTRICAL SUBSTATION
a. INTRODUCTION:An electrical Network comprises of the following systems:
Generating Stations
Transmission Systems
Receiving Stations
Distribution Systems
Load Points
flow
by
10
c. CLASSIFICATIONS OF SUB STATIONS:Based ON Nature Of Duties: Step up or primary Electrical Power substation:
Primary substations are associated with the power generating
plants where the voltage is stepped up from low voltage (3.3,
6.6, 11, 33kV) to 220kV or 400kV for transmitting the power
so that huge amount of power can be transmitted over a large
distance to load centers.
Primary Grid Electrical Power Substation:
Such substations are located at suitable load centers along
with the primary transmission lines. At primary Grid Power
Substations the primary transmission voltage (220kV or
400kV) is stepped down to secondary transmission voltages
(110kV or 220KV). This Secondary transmission lines are
carried over to Secondary Power Substations situated at the
load centers where the voltage is further stepped down to Sub
11
12
d. SUB-STATION SITE SELECTION:The aspects necessary to be considered for site selection are:
Fairly level ground
Right of way around the substation yard for incoming &
outgoing transmission & distribution lines.
Preferably of soil strata having low earth resistance values
Easy approach & accessibility from main roads for Heavy
equipment transportation and routine O & M of substation.
Economy / Cost
-Busbars
-Transformers
15
-Insulators
-Substation Equipment such as Circuit
breakers, Isolators, Earthing, Switches,
Surge Arresters, CTs, VTs/CVTs
-Neutral Grounding Equipment
-Station Earthing system comprising ground
mat, risers, earthing strips, earthing spikes.
-Overhead earthwire shielding against
lightning strokes, or, lightning masts.
-Galvanised steel structures for towers,
gantries, equipment supports
-PLCC Equipment including line trap, tuning
unit, coupling capacitor, etc.
-Power cables
-Control cables for protection and control
-Roads, Railway track, cable trenches
-Station lighting system
11/ 33 kV Switchgear:-
- 33 kV Outdoor Switchgear
-11 kV Indoor Switchgear
LT Panels: -
Protection system: -
- CTs, CVTs
- Protective Relays
- Circuit breakers
-Computer/Microprocessors, Data
Data processing
- Man-machine interface
- Expert system etc.
19
g. FORMATION OF SUBSTATION EARTHING: The main earth mat shall be laid horizontally at a regular
spacing in both X & Y direction(9m) based upon soil resistivity
value and substation layout arrangement .The main earth mat
shall be laid at a depth of 600 mm from ground. The earth mat
shall be connected to the following in substation
i.
ii.
iii.
iv.
v.
vi.
Equipment and Structure Earthing in Substation: i) Earthing pads are provided for the apparatus/equipments at
accessible position. The connection between earthing pads and
the earthing grid is made by two short earthing leads (one direct
and another through the support structure) free from kinks and
splices by 75 mm x 12 mm GS earth flat. The GS earth flat is
welded to a MS Rod riser which is connected to the earth mat in
ground.
ii) All steel/RCC columns, metallic stairs etc. are connected to the
nearby earthing grid conductor by two earthing leads. Electrical
continuity is ensured by bonding different sections of rails and
metallic stairs.
iii) Metallic pipes, conduits and cable tray sections for cable
installation are bonded to ensure electrical continuity and
connected to earthing conductors at regular interval. Apart from
intermediate connections, beginning points are also connected to
earthing system.
iv) A separate earthing conductor should be provided for earthing
the lighting fixtures, receptacles, switches, junction boxes,
lighting conduits etc.
v)
A continuous ground conductor of 16 SWG GI wire is run all
along each conduit run and bonded at every 600 mm by not less
than two turns of the same size of wires. The Conductor is
connected to each panel ground bus, all junction boxes,
receptacles, lighting fixtures etc.
21
h. LIGHTNING PROTECTION: The protection from the lightning is done with the help of shield
wire and lightning mast (high lattice structure with a spike on
top).
Shield wire
Shield wire lightning protection system will be generally used in
smaller sub stations of:
Lower voltage class, where number of bays is less, area of the
substation is small, & height of the main structures is of normal
height. The major disadvantage of shield wire type lightning
protection is, that it causes short circuit in the substation or may
even damage the costly equipments in case of its failure
(snapping ).
22
Earth wire
Overhead power lines are often equipped with a ground conductor
(shield wire or overhead earth wire). A ground conductor is a
conductor that is usually grounded (earthed) at the top of the
supporting structure to minimize the likelihood of direct lightning
strikes to the phase conductors. The ground wire is also a parallel
path with the earth for fault currents in earthed neutral circuits.
Very high-voltage transmission lines may have two ground
conductors. These are either at the outermost ends of the highest
cross beam, at two V-shaped mast points, or at a separate cross
arm. By protecting the line from lightning, the design of apparatus
in substations is simplified due to lower stress on insulation.
Shield wires on transmission lines may include optical fibers
(OPGW), used for communication and control of the power
system.
7/3.66 mm wire is used for providing earthing in lightning mast
and towers.
The main function of Earth wire/ Ground wire is to provide
protection against direct lightening strokes to the line conductors
or towers. In addition Ground wire reduces the induced voltage on
parallel telecom lines under fault condition
DEHRADUN
25
type layout arrangement for 400KV voltage level and Double Main
and Transfer Bus (DMT) scheme for 220KV voltage level.
b. SCOPE OF PROJECT:
The scope of this specification covers the following:
Construction of 400/220 KV Dehradun substation with the
provisions of following bays as per SLD
a. 400 KV bays for two (2) nos.400/220/33 KV, 315 MVA Auto
transformers.
b. 400 KV bays for termination of 400 KV Bagpat D/C line.
c. 400 KV bay for 1 no. 420 KV 80 MVAR Bus reactor.
d. 220 KV bays for termination of six (6) nos. 220 KV lines.
e. 220 KV Transfer Bus Coupler Bay and 220 KV bus coupler bay 1
no. each.
Requirement of the Dehradun substation:
a. 400 KV and 220 KV circuit breakers, isolators, current
transformer, CVT, surge arrester.
b. 630 KVA 33/0.433 KV Auxiliary Transformer along with 33KV
isolator, 30KV surge arrester & 33KV horn gap fuse to be
connected on SEB supply.
c. 3 nos. kiosk for 400 KV and 5 nos. for 220 KV,BCU for
controlling and monitoring of auxiliary system 1 no.
d. Relay and protection system.
e. PLCC system
f. Wave Traps
27
28
Advantages:
1. The primary choice for areas with extensive space
2. With quality design, the system is viable due to the low construction costs and
cost of switchgear
3. Less construction time, thereby more suited for expedited installations
4. Easy maintenance as all the equipment is within view. It is easy to notice and
attend to faults.
5. Scope of future expansion.
d. COMPONENTS AT SITE:
1. LIGTHNING ARRESTOR
29
It is the first equipment in a substation. Substation design involves more than one
installing apparatus, protective devices and equipment. The significant momentary
investment and required reliable continuous operation of the facility requires
detailed attention to preventing surges from entering the substation facility. The
effects of disturbances with limiting in a power system, which if allowed to persist,
may damage plant and interrupt the supply of electrical energy. Lightning is one of
the most serious causes of over voltage. If the power equipment especially at
outdoor substation is not protected, the over-voltage will cause burning of
insulation. Thus it results into complete shutdown of the power and the loss may
run into cores of kyat. Electrical equipment can be damaged due to over-voltage
such as switching surge over-voltage, Lightning surge over-voltage, transient
recovery voltage and power frequency temporary over-voltage in transmission line
and receiving end of substation. It is important to protect power equipment against
30
them wherever possible. Lightning Arrester can protect the damages of electrical
equipments.
i.
Rating:
S.
Description
Rating
No.
KV(rms)
400
220
420
220
1.
2.
Rated frequency
50
50
3.
No. of poles
4.
50
50
5.
10500
6125
6.
1425
1050
7.
1050
630
460
31
9.
500
500
Effectively Effectiv
ely
earthed
earthed
32
33
one
Rating:
S.
Description
Rating
No.
KV(rms)
400
220
420
220
1.
2.
Rated frequency
50
50
3.
No. of poles
4.
50
50
5.
10500
6125
6.
1425
1050
34
for
CVT , kV(peak)
7.
1050
630
460
9.
10.
320min
1000
_
1000
Effectively Effectiv
earthed
ely
earthed
CVT are used to step down EHV by using capacitors to provide low voltage signal
either for measurement or to operate a protective relay. Capacitance split the EHV
and maximum voltage appears across it. L tunes the device to line frequency.
In practice, C1 is a series of various small capacitors.
iii. Where Found:
CVT are found in each phase of Feeder circuit.
iv. Remarks:
CVT are also used in PLCC. Combination of CVT and WT are used for filtering
HF communication signal.
35
3. WAVE TRAP
It is also called "LINE trap". It is connected in series with the power line. It blocks
the high frequency carrier waves (24 kHz to 500 kHz) and let power waves (50 Hz
- 60 Hz) to pass through. It is basically an inductor of rating in milli henry. .
i. Where Found:
At the end of each feeder there are two WT are installed (Connecting phase will be
same for all feeders).
36
4. GANTRY
The incoming or outgoing electrical circuit terminates on gantry.
5. CURRENT TRANSFORMERS
The current transformers incorporated into the AIS are used for
protective relaying and metering and are of metal-enclosed type.
The secondary windings are air insulated and mounted inside
metal enclosure. The Current transformers are provided with the
transformation ratio of: 500/1 A to 3000/1 A for 400 KV and 800/1
to 1600/1for220KV.
electromagnetic
All
shields
current
to
transformers
protect
against
have
high
effective
frequency
37
38
1. Protective cap
2. Below
3. Primary terminals
4. Active part
5. Insulator
i. Rating:
39
S.
Description
Rating
No.
KV(rms)
400
220
420
220
1.
Rated voltage of CT
2.
Type
3.
Insulation level
4.
3600A
5.
6.
7.
Rated frequency
50
50
8.
No. of poles
9.
50
50
SAS 420
630/1425KV
48 kg
OSKF-245
460/1050KV
_
40KA/1 sec
160Kg
10500
6125
1425
1050
1050
630
460
ground of CT , kV(peak)
12. Switching impulse withstand voltage
(250/2500micro second) dry and wet
between lines and ground of CVT KV
(peak)
13. 1
minute
power
frequency
(dry)
40
14.
15.
320min
1000
1000
Effectively
Effectively
earthed
Earthed
Core no.
Ratio
Primary
Terminal
Secondary
Terminal
II
III
IV
P1- P2
P1- P2
1S11S2:500/1
2S11S2:500/1
3S11S2:500/1
1S11S3:2000/1
2S11S3:2000/1
3S11S3:2000/1
1S11S4:3000/1
2S11S4:3000/1
3S11S4:3000/1
Burden
(VA)
Class
PS
ISF/ALF
P1- P2
P1- P2
4S15S1-1S2:500/1
1S2:500/1
5S14S11S3:2000/1
1S3:2000/1
5S14S11S4:3000/1
1S4:3000/1
20
PS
0.2S
PS
PS
<5
ii. Operation:
41
Description
Rating
No.
420
220
1.
Rated voltage
420
245
2.
Type
DBR
HDB
43
3.
Current:
2000/3150
1600
4.
STC (kA-sec-kAp):
50-1-125
40-1-125
5.
Impulse
1425KV
1050
6.
P.F voltage
610KV
460
7.
Frequency
50Hz
50Hz
8.
Operating device
Motor
Motor
9.
DC Voltage
220
220
10. AC Voltage
415
220
50
50
10500
6125
1425
1050
1425
1200
wave
impulse
withstand
1050
44
16. 1
minute
power
frequency
(dry)
460
520
18.
320min
1000
460
_
1000
Effectively
Earthed
Effectively
earthed
ii. Operation:
This disconnecting device can be operated manually or
automatically via motors. When abnormal current appears in
circuit it isolates CB from circuit.
iii. Where Found:
It is connected across each CB in switchyard and before and after
ICT
7. Circuit breaker:
45
47
Bulk oil
Minimum oil
Air blast
Vacuum
SF6
Oil Circuit Breaker
A high-voltage circuit breaker in which the arc is drawn in oil to
dissipate the heat and extinguish the arc; the intense heat of the
arc decomposes the oil, generating a gas whose high pressure
produces a flow of fresh fluid through the arc that furnishes the
necessary insulation to prevent a restrike of the arc.
The arc is then extinguished, both because of its elongation upon
parting of contacts and because of intensive cooling by the gases
and oil vapor.
48
51
During the arcing period SF6 gas is blown axially along the arc.
The gas removes the heat from the arc by axial convection and
radial dissipation. As a result, the arc diameter reduces during the
decreasing mode of the current wave. The diameter becomes
small during the current zero and the arc is extinguished. Due to
its electro negativity, and low arc time constant, the SF6 gas
regains its dielectric strength rapidly after the current zero, the
rate of rise of dielectric strength is very high and the time
constant is very small.
52
53
i.
Rating:
S.No. Description
Rating
400
220
1.
Rated voltage KV
420
245
2.
1425
1050
3.
Rated
610
460
4.
KV(rms)
Rated Frequency Hz
50
50
5.
4000
3150
6.
125
125
power
frequency
withstand
54
voltage
7.
8.
9.
10.
11.
12.
13.
14.
50
3s
12.5KA
1.3
50
3s
12.5
1.3
600
50
125
50
DC 220 V
DC 220 V
AC 240 V
AC 240 V
AC 240 V
AC 240 V
7 bar at
6.5 bar at
20C
20C
51 kg
16.5 kg
ii. Operation:
CB is basically a switch which can interrupt circuit when fault
current flows or when power flows in reverse direction. A
circuit breaker essentially consists of fixed and moving
contacts. These contacts can be opened manually or by
remote control whenever desired. When a fault occurs on
any part of the system, the trip coils of breaker get
energized and the moving contacts are pulled apart by some
mechanism, thus opening the circuit. As the switching is
done under SF6 gas environment, the arcing is limited and
does not damage equipment. It protects the transformer
from fault current.
iii. Where Found:
55
Rating
o
1.
2.
3.
4.
5.
ONAN
420
80
109.97
45
Types of cooling
Rated Voltage KV
Rated Power MVAR
Rated Current Amp
Temp. Rise winding C
57
6.
7.
8.
9.
10.
11.
12.
13.
14.
40
3
50
YN
SI 1050 LI 1300-LI 550 AC 230
63360 Kg
63360 Kg
36720 Kg
133710 Kg
9. AUTO TRANSFORMER:
Auto transformer is kind of electrical transformer where primary
and secondary shares same common single winding.
58
Hence, the voltage across the portion BC of the winding, will be,
60
I1.
Copper Savings in Auto Transformer
Now we will discuss the savings of copper in auto transformer
compared to conventional two winding transformer.
We know that weight of copper of any winding depends upon its
length and cross - sectional area. Again length of conductor in
winding is proportional to its number of turns and cross - sectional
area varies with rated current. So weight of copper in winding is
directly proportional to product of number of turns and rated
current of the winding. Therefore, weight of copper in the section
AC proportional to,
61
N1I1 + N2I2
2N1I1
62
Advantages
of
using
auto
transformer.
For
63
primary
and secondary
sides have
i. Rating:
Specification
of
315
MVA
400/220
KV
3-
auto
transformer :
S.N Description:
Rating
o
1.
2.
Types of cooling
Rating of H.V. & I.V.
ONAN
189
ONAF
252
OFAF
315
3.
4.
5.
6.
(MVA)
Rating of L.V. (MVA)
Line current H.V.(Amps)
Line current I.V. (Amps)
Line
current
L.V.
63
273.12
496.58
1103.52
84
364.16
662.11
1471.36
105
455.20
827.64
1639.20
7.
8.
9.
10.
11.
12.
13.
14.
15.
(Amps)
No load voltage H.V
No load voltage I.V
No load voltage L.V
Temp. Rise winding C
Temp. rise oil C
Phase
Frequency
Connection symbol
Insulation level:
55
400
220
33
55
50
3
50
YNa0d11
HV
SI 1050 LI 1300 AC 38
IV
LI 950 AC 38
LV
16. Core and Coil mass
17. Tank and Fitting Mass
LI 250 AC 95
1,34,000 Kg
71,000 Kg
65
55
7,2900 Kg
2,77900Kg
Vector group:
1U
2U
3U
3V
2W
1W
2V
1V
3W
66
67
4. Miscellaneous:
1. INSULATORS:
Conductor
Bundled
Conductor
Insulated
Conductor
a. Rating:
69
70
71
Size
C Core
Control
2c x 2.5
3c x 2.5
4c x 2.5
cable
mm2
mm2
mm2
Power Cable
2c x 6 mm2
4c x 6 mm2
4c x 16 mm2
7c x 2.5 mm2
10c x 2.5 mm2
3.5c x 35 mm2
3.5c x 70 mm2
1c x 250 mm2
5c x 2.5 mm2
2c x 10 mm2
1c x 630 mm2
72
73
It has two meter which indicate the temperature of the oil and
winding of main tank. If temperature of oil or winding exceeds
than specified value, relay operates to sound an alarm. If there is
further increase in temperature then relay completes the trip
circuit to open the circuit breaker controlling the transformer.
6. Switching schemes:
The factors considered for selection of switching schemes
Reliability factor
Availability of the space
Economics (project cost)
There can be several combinations in which the equipments,
busbars, structures
75
76
77
7. BUS COUPLER:
The bus coupler consists of circuit breaker and isolator. Each generator and feeder
may be connected to either main bus bar or spar bus bar with the help of bus
coupler. Repairing, maintenance and testing of feeder circuit or other section can
be done by putting them on spar bus bar, thus keeping the main bus bar
undisturbed. Bus coupler is a device which is used switch from one bus to the other
without any interruption in power supply and without creating hazardous arcs. It is
achieved with the help of circuit breaker and isolators
8. POWER LINE CARRIER COMMUNICATION:
Introduction:
Reliable & fast communication is necessary for safe efficient & economic power
supply. To reduce the power failure in extent & time, to maintain the
interconnected grid system in optimum working condition; to coordinate the
78
9. SCADA:
79
Fig: Scada
The task of supervision of machinery and industrial processes on
a routine basis can be an excruciatingly tiresome job. Always
being by the side a machine or being on a 24x7 patrol duty
around the assembly line equipment checking the temperature
levels, water levels, oil level and performing other checks would
be considered a wastage of the expertise of the technician on
trivial tasks. But, to get rid of this burdensome task, the engineers
devised equipments and sensors that would prevent or at least
reduce the frequency of these routine checks. As a result of that,
control systems and its various off springs like SCADA systems
were formed. Supervisory Control and Data Acquisition
(SCADA) offers the ease of monitoring of sensors placed at
distances, from one central location.
SCADA systems are used to monitor and control a plant or
equipment in industries such as telecommunications, water and
waste control, energy, oil and gas refining and transportation. A
SCADA system gathers information, such as where a leak on a
pipeline has occurred, transfers the information back to a central
site, alerting the home station that the leak has occurred, carrying
80
5. CONCLUSION:I got acquainted with the Electrical department engaged here in the Commissioning
of such a massive project and came to know about their working. These people
work day and night to lighten the world and in particular us so that we have all the
means to do our work with utmost ease. By virtue of this training program I came
to know about various technical aspects and implications of such Substation
project starting from ground zero to the level it is now, the technical equipments
required for the same the implications arising with the utilization of those with the
idea in the mind to utilize each and every bit used to it full potential with longest
possible life from along with the hard work and expertise of the officials and
workers which they put in to make this massive project sustained, running and
maintaining the reputation of its existence.
83
84