Doc. No.
Section/Location
Catofin Reactor/Nozzle
Job Title
Job Duration
Start date
Sl. No.
1
2
End date
Hazards
Activities(Sequence of work)
Staff Training, and PPE
Permits to work
All mechanical activities are over and ready for CFB lining work
Material Handling
Persons responsible
Safety Supervisor
Safety Supervisor
Site in Charge
Client
1) Fall of materials
2) Injury during loading /unloading in the material cage.
3)Mannual handling
1) Fall of materials
2) Injury during loading /unloading in the material cage.
3) Mannual handling
1. Fall of persons
2. Heat
Fall of materials
10
Completion of job.
House Keeping
Departmental representative
Safety Precautions
1) Fall of workmen
2) Injury during movement through metal parts in the platform/access door etc.
Site in Charge
Site in Charge/Supervisor
Ensure the proper use of PPE with all the workmen.
1. Proper unloading of materials in working zone.
2. Working platforms are in position.
3. All required machines are in position with proper arrangements.
1. Start work carefully with proper safety equipment.
2. Ensure Working platforms is balanced properly with man and materials.
3. Ensure materials do not fall from platform.
1. Switch off the power connections.
2. Clean the area properly.
3. Shift the debris to proper place.
4. Inform concern officer for completion of work.
Site in Charge
Site in Charge
Site in Charge
Site in Charge
Contractors representative