Urgent Work on Warehouse: (hand over date 10th / 6/ 2016)

Fire-Fighting Works:
1) Underground close loop connections for Fire-fighting line Priority at
Warehouse
2) Installation of Fire Hydrant Priority at Warehouse
3) Installation of Fire Hydrant Hose Cabinet Priority at Warehouse
4) Installation of Fire Department Connections Priority at Warehouse
5) Modifications on firefighting installation based on Al-Fanars instructions
Priority at Warehouse
6) Fire Pump Installations

Plumbing Works:
1)
2)
3)
4)

All Sanitary Fixture Installation Priority at Warehouse


Electrical Water Heater Priority at Warehouse
Water Hammer Arrester Priority at Warehouse
Completing site drain connections - Site

HVAC:
1) Roof Curves FOR Exhaust Fan Warehouse
2) AC split Unit at Guard house Priority at Warehouse