MANAGEMENT OF CHANGE CHECKLIST


Checklist Manajemen Perubahan
Initiator
Pencetus

Date

: Proteam D

: 25-03-2015

Tanggal

Reason and or description of change


Alasan dan atau deskripsi perubahan

As required by Contract (detail clause for installation of charterer office)

Task

Person in charge

Completion Target

Done

Tugas

Penanggungjawab

Target Penyelesaian

Selesai

Carry out HIRADC for installation work

QHSE and Crew


onboard

30-03-2014

06-042014

Prepare container as per spec required

Team and Logistic

Prepare chiller as per spec required

Team and Logistic

Carry Out test and Examination for


Rigging gears and equipments

Team

30-05-14

05-06-14

Installement of container and chiller

Team

No
1
2

Close Out Date


Ditutup Tanggal

Update on
Diupdate tanggal

Approved by Managing Director


Disetujui oleh Managing Director