Case Studies
Sl.
No
Span
Project
Arrangement (m)
Client
Contractor Status
34 + 60 + 34
CC28
Delhi Metro
Phase III, Line 7
Delhi
Metro
L&T
Completed
60 + 60
CC28
Delhi Metro
Phase III, Line 7
L&T
Superstructure
partly
completed
37 + 69 + 67 + 55
+ 34
CC26R
Delhi Metro
Phase III, Line 7
ITD
Foundation
and Substructure
completed
i) 34 + 60 + 34 m
ii) 60 + 60 m
II. 60 + 60 m
34 + 60 + 34
Cross Sections
Area (m2)
8.890
Iyy (m4)
28.79
Area (m2)
4.980
Iyy (m4)
2.63
34 + 60 + 34
34 + 60 + 34
Construction Sequence
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
- Midas Civil has been used for numerical modelling and Structural Analysis
- Super Structure (Box Girder) Piers and Piles have been modelled as Line Element
- Pile Cap has been modelled as plate element.
- Point Spring Supports to take the effect of soil.
34 + 60 + 34
- Concrete
- Creep and Shrinkage and compressive strength gain behaviour has been defined as
per CEB-FIP
34 + 60 + 34
- Internal Prestressing
- 19T15 and 12T15 anchorages
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
34 + 60 + 34
- Precision: Only 6mm of difference between the theoretical value and the
observed value of deflection at the cantilever tips, just before stitching.
34 + 60 + 34
Cross Sections
Area (m2)
8.890
Iyy (m4)
28.79
Area (m2)
5.71
Iyy (m4)
5.86
- Midas Civil has been used for numerical modelling and Structural Analysis
- Super Structure (Box Girder) Piers and Piles have been modelled as Line Element
- Pile Cap has been modelled as plate element.
- Point Spring Supports to take the effect of soil.
37 + 69.9 + 67 + 55 + 34m
Cross Sections
Area (m2)
10.01
Iyy (m4)
28.73
Area (m2)
5.90
Iyy (m4)
6.13
37 + 69.9 + 67 + 55 + 34m
Construction Sequence
Intermediate Piers
P235:
Free Pier
P236:
Integral Pier
P237:
Integral Pier
P238:
Free Pier
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
37 + 69.9 + 67 + 55 + 34m
- Internal Prestressing
- 19T15 and 12T15 anchorages
37 + 69.9 + 67 + 55 + 34m