[éZ-\ General Manager/Project Director,
| Dasu Hydropower Project, WADA,
“y §" Floor, Al-Maalik Plaza, Davis Road, Lahore.
E-mail: dasunpp@yahoo.com
No. GM/PD/Dasu HPP/RAR-01/53/6/0 3-9 Dated: eG -.06.2016.
>. Project Manager,
Dasu Hydropower Consultants,
5 Floor, Al-Maalik Plaza, Davis Road,
Lahore
Subject: CONSTRUCTION OF RIGHT BANK ACCESS ROAD UNDER CONTRACT RAR-01.
During my visit to Dasu in February, 2016, it was decided and conveyed to all concerned that in 1*
section of RAR-01 upto K4+950, road width would be adjusted within already acquired 33 ft ROW
instead of earlier followed 20m. Now in the recent visit to Dasu during May 2016, it was shocking for
me to know that Engineer had not issued / approved the X-Sections for construction of road so far
after elapse of 3 months but arguing that it was the responsibility of contractor. Also Engineer has not
provided the schedule for issuance drawings to the contractor for construction of various parts of
works, Thereby Engineer failed to comply with the General Specifications 9.2.2 & 9.2.3 of the Contract
RAR-O1 signed with the contractor.
Irresponsible attitude of DHC staff delayed the construction works otherwise it could be started three
months earlier as the ROW was available for construction activities in entire reach of the contract.
The consultants failed to fulfill their obligation under General Condition 3.1.1 of Contract for
Consultancy Services. Therefore, WAPDA has right to lodge claim against DHC under the General
Condition 8.1 of Contract for Consultancy Services
=
e_‘
General Manager/Project Director
(Haji Muhammad Farooq Ahmad)
c.c.
Director (RAR), Dasu Hydropower Project, WAPDA, Dasu.
Additional Director (CMS), Dasu Hydropower Project, WAPDA, Dasu.
Chief Resident Engineer, Dasu Hydropower Consultants, Dasu.
Mr. Masood Ahmad, Team Leader, Dasu HPP, World Bank, Washington D.C, USA.
Ms. Uzma Sadat, Senior Procurement Specialist, World Bank, Islamabad.
‘SO to Member (Water), WAPDA, Wapda House, Lahore.
Sra
oak