Beruflich Dokumente
Kultur Dokumente
__________________
appellee.
____________________
____________________
April 22, 1993
____________________
filed
damages
for
this
a
lawsuit
defective
matter of
law that
plaintiff's claims.
court
should have
"discovery" rule
long
enough to
plaintiff
defendant
Napco
wastewater
treatment
system.
seeking
The
the statutes
of limitations
had run
on
jury decide
that material
summary judgment.
Cambridge Plating
against
Plaintiff
whether Massachusetts's
its claims.
Because we
agree
with
issues of fact
remain, we
reverse the
I.
A. Factual Background
__________________
Cambridge
Plating
is
an
electroplating
sewers.
regulations
In
business
that
an effort
to meet
strict environmental
Napco.
$400,000.
Cambridge
substantial changes
and
complex
recorders
The contract
Plating
additionally
to its facility to
array of
pipes,
tanks,
to
make
pushing the
total cost
sensors,
for the
The system began running on October 30, 1984, but it was not
then
fully operational,
and
Napco continued
installation
and
-2-
debugging for
another year.
In October
levels
in
the
wastewater
discharges
sometimes
exceeded
regulatory
limits.
Cambridge
Plating's
managers
errors in
wastewater sampling.
This
belief was
fueled by
the
Plating
took
operational or
several
sampling
it.
Plating
adopted
resolve
the
It replaced
the
asked a wastewater
to
problems.
steps
treatment expert,
his
suggestions,
but
the
company
Cambridge
continued
December
29,
1988, the
Massachusetts
Water Resources
penalty
violations during
commissioned
system.
1986-88.
another
Moleux's
of
$682,250
Cambridge
In February
expert,
lengthy
on
Peter
for
Moleux,
inspection, which
-3-
Plating
to
evaluate
included a
the
close
comparison
of Napco's
the system
as it
plans, and
Most significantly,
install
Moleux discovered
an important component,
substandard engineering
device
had
rendered the
a static
provided by Napco
been placed.
practices.
Omission
failed to
mixer, inside
a pipe
indicated erroneously
of
the static
mixer
cleaning 80 percent
of the wastewater.
After
Moleux's
evaluation, Cambridge
static
mixer
at the
point called
system
thereafter worked
for by
properly,
Plating
installed a
Napco's plans.
enabling Cambridge
The
Plating
of
negligent
unfair
action for
Plating's
limitation.
contract, negligence,
business practices
Napco moved
of
act, Mass.
of the Massachusetts
Gen. Laws
were
barred
by the
fraud,
Ann. ch.
93A.
all of Cambridge
applicable
statutes
of
was a
sale of goods,
and that
its
contract
claim thus
was governed
by the
four-year limitations
Mass. Gen. Laws
Ann.
limitations period,
ch. 260,
2.
All of
either
three-
statutes of
claims
were
or
four-year
time-barred,
with
learned that
argument that
until Moleux's
court
These
determined, because
they
discharges within
plaintiff's
the
the
limitation.1
legal
limits.
the limitations
failing to
The court
reasonable
problems.
diligence,
The
Cambridge
bring
rejected
periods were
before suit,
tolled
first learned
could
have
appeal,
Cambridge
Plating
argues
that
the
court
usurped the
not
court's grant of
summary judgment
Our review
of the district
is plenary, and
we read
the
See,
___
e.g., Pagano v.
____ ______
343, 347
(1st
Cir. 1993).
II.
____________________
ruling as a matter of law that the contract with Napco was a sale
of
goods contract
within
the
scope
of
the
UCC.
Although
function, see United States v. City of Twin Falls, 806 F.2d 862,
___ _____________
___________________
870 (9th Cir. 1986),
that the
district court
are sufficiently
was permitted
to
the
Plating
equipment it
definition of goods.
things . .
asserts
Id.
___
that the
purchased
does not
2-105.
The
wastewater
company
treatment
electroplating
facility in
inapplicable
meet
the Code's
time of identification to
emphasizes
system
is
UCC
and
the
its
an effort
immense
size
integration
to equate
of
the
into
the
this situation
132, 434
does not
is flawed.
The claims
of a completed building
sale of bricks or
131, 133.
the
window frames or
in White
_____
were
buildings" and
Id.
___
the
at
system as
the
primary subject
of
the sale
and,
-6-
indeed,
See App.
___
at
113.
provided
equipment.
Napco,
eighty-two
which
involved
pieces
of
therefore goods
system
installation
806 F.2d
are
into
of
at 871
movable
plaintiff's
facility and
of the
(components of
goods).
It
was
building that
the
hence unmovable --
UCC.
wastewater
only
after
items became
to borrow
of paint sold
the
as goods and
installation services, in
consequence.
of engineering and
addition to a sale of
In our view,
goods, is of no
factor,
are
thrust,
outside
inexorably that, if
the
In White, 386
_____
Mass. at
the "rendition
purpose is
of
the
the
UCC.
of services" is
rendition
It
of
follows
not at
the
____________________
2 Plaintiff also
Hill
position Chestnut
________
653 F. Supp. 927, 932 (D.
________________
_________________
Mass. 1987), which held that structures "attached to realty,"
such as the elevator system at issue there, are not "goods"
within the meaning of the UCC.
Under the UCC, however, the
inquiry centers on the nature of the goods "at the time of
identification to the contract," Mass. Gen. Laws Ann. ch. 106,
2-105. It is beyond debate that the contract here listed movable
items. See Burnham v. Mark IV Homes, Inc., 387 Mass. 575, 581,
___ _______
___________________
441 N.E.2d 1027 (1982) (modular homes are "goods" within coverage
of UCC).
-7-
(1989) (contract
Mass.
App. 108,
119, 546
involving both
undisputed
Cambridge
goods.
price
demonstrate
listed
facts
the purchase
items of equipment.
of
$398,200
installation
from
was
was
the deal
was for
Only $68,970 of
for
Napco
that
a sale of
the specifically
installation,3
even
between
optional.
and
See
___
purchasing
generally
_________
Chestnut Hill Dev. Corp. v. Otis Elevator Co., 653 F. Supp. 927,
_________________________
_________________
932
(D.
Mass.
components"
1987)
(a
contract
to
supply
"hundreds
of
services").
Because
We thus
move on
this and
the
Massachusetts legislature
has
set statutory
limitations periods for various causes of action, see supra at 4___ _____
5
&
n.1, determining
product
of judicial
when claims
accrue
interpretation,'"
"`has long
Hoult v.
_____
been the
Hoult, 792
_____
F.
Albert, 381
______
____________________
3
Plating
meeting
-- also
general
action
rule for
accrues at the
negligence claims
time of injury.
that the
cause of
v. Presnell, 409
________
Mass. 239,
780 (1991).
Similarly, a cause
of
& Ellis, Inc., 29 Mass. App. 215, 221, 560 N.E.2d 122 (1990), and
_____________
accrual
of
injury
a chapter
93A claim
typically
occurs at
the time
29
times
are subject
because Massachusetts
be
unfair to
before a plaintiff is
Bowen v.
_____
begin
courts
to
flexibility,
have recognized
running the
statute
some
that it
of limitations
205, 557
See
___
N.E.2d 739
Mass at 619.
ensuring fairness
is the
regardless of the
actual
time of
breach or injury,
accrue
until a
plaintiff discovers,
"a cause
of action
or reasonably
injured as
792 F. Supp.
does not
should have
a result of
at 144.
See
___
the
also
____
v. Sears,
_____
365
Mass. 83,
83-84,
310 N.E.2d
131 (1974).
The
delayed
after its
Anthony's Pier
______________
link to
not discover
until years
contractual causes
by
the
alleging breach
judicially
of action in
crafted
Massachusetts are
accrual
rules.
cause of
action
for breach
accrues
when the
breach
party's
lack
knowledge of
of
of
a sales
Under
2-275(2),
contract
generally
of the
aggrieved
occurs, "regardless
the
breach,"
and
ch. 106,
2-275(2).
When
Claims
a seller
a breach
of
gives
an explicit
____________________
4
the
cause of action
for breach of a
a sale
of goods,
and that
the UCC
therefore governs
the
contract claim.
warranted
the
of
the
wastewater treatment
Because
we
correctly ruled as a
a sale
have concluded
gave
timeliness
an
of
explicit
all
the district
court
Napco
that
of
is no challenge to
warranty of
plaintiff's
future
claims
performance,
is
linked
to
the
the
discovery rule.
IV.
Our
must
analysis of
operates.
impact in
conflicting views on
this case
"inherently unknowable"
causes of
the question
reasonably
diligent
efforts.6
If
Cambridge
Plating
____________________
6 Although the dictionary
"inherently" unknowable claim is
undiscoverable, see
___
could
_____
have
diligence,
discovered
Napco
its claims
maintains,
earlier
then
they
through
were
reasonable
not
inherently
__________
counters
that the
applicability of
the
discovery rule does not depend on whether it was possible for the
company
to
discover
Napco's
responsibility
for
the
defects
earlier
The
district
court
adopted
Napco's
view,
finding
that
company
failing to
learned
that
the water
treatment
equipment
was
The
(emphasis in original).
It
did not
reasonable
hiring the
discover
diligence in
the
unknowable turns
defects:
"[w]hether
not upon
an inquiry
first expert,
a
defect
who did
is
not
inherently
injured
____________________
Language (2d ed. 1987) at
________
describe a cause of action
982, the
phrase
has been
used
to
of detection for
discovery
led to
This implies
standard
that at least
two courses of
of reasonable diligence
-- one pursued
by the injured
Massachusetts law.
is
the
one
consistent
statement of the
with
prevailing
to protect plaintiffs,
if
plaintiff who
remained unaware
dictates
that
inapplicable simply
See
___
his claim
even after
discovery
rule
not
the
of
be
deemed
than those
it.
or cause
618 (limitations
"punish[]
negligent
delay")
(quoting
Wood
____
v.
reasonableness
Plating complains
on the
part
that nothing
the plaintiff;
Cambridge
would do.
one reasonable
of
option for
pursuing a
claim
available to
the
plaintiff would
be
penalized if
the
of equipment --
first expert
chosen
to
detect.
That the
point of
to put
them on notice
of their claims.
This, certainly,
formulation
that
we
believe
reflects
prevailing
See
___
619.
that the
decision
uncovered
whether
any
485-86).
[injury]
ha[s] to be made
therefore, "by
to apply the
should
in light of
reasonably
have
been
what a reasonable
-14-
person in
is tested,
her position
would
have known or
on inquiry
at the
various
discover the
system's
defects must
statute
of limitations.7
inquiry
the problem
This is
be sufficient
so
to toll
because, if
problem, it cannot
the
reasonable
be said that
Mass. at 206.8
We recognize that the district
literal
support
describe
in the
the discovery
unknowable"
language of
rule as
number of
applicable only
cases, which
to "inherently
402 Mass.
27, 34,
520 N.E.2d
Mass. at 825-26
v. New
___
493 (1988);
Mass. App. at
____________________
7 We presume
See infra p.17.
___ _____
here that
the expert
performed competently.
222; Melrose Hous. Auth. v. New Hampshire Ins. Co., 24 Mass. App.
___________________
______________________
207, 212,
507 N.E.2d
787 (1987).
But
on
analysis.
The two cases cited
precedent for
Hous. Auth., 24
___________
Mass. App. at
Mass. at 129
212, as do
by
Napco,
&
n.9;
International Mobiles, 29
______________________
Moreover,
position
none
of
these
cases
Mass.
App.
involved
at
218 &
plaintiff
be in here,
222.
in the
not diligent,
___
courts
and
that circumstance,
made no reasonable
efforts to
we believe,
imprecisely.
When
has led
the
a plaintiff has
or its
cause,
discovered it.
found that
a claim
diligence,
it
reasonably
should have
Mass.
at 130
would be
(in cases
could not
___
For example,
be discovered
precluding as
well
if a
court
through reasonable
a finding
discovered it.
See,
___
cited, "the
nature of
e.g.,
____
that he
White, 386
_____
the defendant's
[a later time]").
-16-
Similarly,
been
a court
conclusion, lacking
presume
Having
the
that the
if the
court's sensible
should have
______
plaintiff has no
See,
___
is logical to
actions would
v. Jablonski,
_________
253,
N.E.2d
473
700
371
212-215; Graveline
_________
254-55,
claim.
e.g., Friedman
____ ________
From this
discovered her
plaintiff had
(1985).
"Could"
Mass. App.
and "should"
comes
up empty,
disjunction between
a court
is supposed to
faced with
possible
of
do,
us present
Because none
that situation,
and because
effectively
would
cited to
should have
______
provide, we
of the
not
permit
incompetent "expert."
to
plaintiff
buy
time
Hiring an individual
by
rule
engaging
an
injury suffered by
the plaintiff is
-17-
unlikely to be deemed
the
limitations
period.
Moreover,
even
if
discover a
defect that a
the
plaintiff
competent, but
qualified expert
easily
plaintiff on notice of
(a competent lawyer
it.
See Friedman,
___ ________
371 Mass. at
search and
The
period
pending confirmation
of
stops the
events .
. .
plaintiff on notice
the plaintiff's
that someone
may have
___
injury or
its
occurrence of
"an
likely to
put the
caused her
Thus,
injury,"
a plaintiff who
in the 1970s was told that her injury may have been caused by her
the lawsuit she filed a decade later, when she felt more
these principles
case at
hand, Cambridge
discovery rule --
might be
responsible for
system's failing
performance.
In
Section
the water
V, we
treatment
discuss
our
-18-
conclusion
fact.
See
___
Mass.
at
be answered by
247-48
the trier of
(jury should
decide
V.
To survive Napco's motion for summary judgment
statute
of limitations,
Cambridge Plating
based on the
must show
a genuine
its claims
before June
22, 1987.9
See
___
Plating
problems before
in
fact
knew the
there is a factual
Eastman
_______
Fidler v.
______
792 F.
source
of
the
system's
is whether
should have
record persuades us
learned at
The
felt
that
relied heavily on
failing to
court
that such a
Cambridge
the system
was
to acceptable levels.
Plating's
knowledge
of
the
Additionally,
____________________
of the discovery rule, see Section IV supra, the court ruled that
___
_____
installed,
and throughout
Napco's debugging
process, Cambridge
static
mixer
was virtually
supposed to
diagrams
be located
indicated that
deficiencies presumably
impossible
for
Omission of
anyone but
it had been
pipe and
because Napco's
installed.
were to be resolved
Moreover, any
its finetuning.
When
the
that debugging
available.
being
problems persisted
the system
improperly.
Napco's announcement
Either
operated
despite
this point,
weighted.
however,
was
the two
system was
And
only response
Napco's
or it
required sensitive
to Cambridge
Plating's
In these circumstances, we
requires
system's defects.
of
action,
received
(quoted
in
notice of the
and thus
"notice
Plating was on
should have
of
discovered
likely cause,"
Bowen, 408
_____
Mass. at
Fidler,
______
207-08).
it, once
714
she has
F.2d at
Accordingly,
199
as we
-20-
the defendant
the
as a suspect,
We think it within
late 1985,
workmanship
solely to
See Bowen,
___ _____
to identify
that, in
reasonably
attributed
operation.
the
system's
If so, the
problems
statute of
Plating
So, in
hired new
late 1986,
operators,
the
but
the problems
company engaged
its first
expert evaluation of
the system.
operational suggestions.
defects?
resulted in
the
instructor
of fact.
first expert,
for
The record
describing
a wastewater
contains little
him only
treatment
course
as
information
an assistant
at a
community
only
by the trier
about
Should
This, too,
system?
See
___
at
____________________
10
with those in
White v. Peabody
_____
_______
where plaintiffs sought
that point?
Perhaps
the
of the earlier
the
unresolved,
factual
Plating should
possible
record
questions
have known
responsibility
expert's failure
leaves
remain as
even by
for
these
the
subsidiary
to
the end
issues
whether Cambridge
of 1986
of Napco's
system's failings.
If
the
reasonable, a jury
the rule's
on
through the
impact, assuming
time of
it reached
actual
this far,
discovery is
also a
there a point in
all of the
in the
Was
complied with
In
short,
Cambridge
many
questions
Plating "reasonably
might have
circumstances
information.
remain.
should have
requires a
To
determine
discovered" that
review of
when
it
specific
____________________