Prepared For
Dr. Nikhil R. Dhar, Ph.D
Professor
IPE department
BUET
Prepared By
Sourav Paul
Batch: 52D ID:37
1 | Page
Report
on
SCM
in
UTAH
garments
|2
1. Executive Summary:
Todays apparel industry is more demand centric. Foreign buyers place orders according to the need of
them. Bangladeshi garments normally play a role of tailoring shop of fulfilling the role of manufacturing.
Many factories are concerning about the compliance issues now days to attain better position in ethical
issue. Supply chain helps to demonstrate the application of proper management of all the possible layouts
to have a better understanding of the process.
Here I conducted research on UTAH garments to find out their prevailing supply chain management system
and any possible gap to find a better way of implementing Supply Chain Management. I used both primary
and secondary data to reach specific findings.
UTAH is a new generation garments originated from Pakistan and started its operation in Bangladesh from
2002. They managed most of their production and warehouse facility through an integrated computer
system which is an older version of present ERP.
They have many opportunities in implementing better management systems through ERP and more
penetration of standard Supply Chain management.
Report
on
SCM
in
UTAH
garments
|3
2. Acknowledgement:
The report is submitted as an effort of being in supply chain course in 4 th semester of Institute of Business
Administration, University of Dhaka.
There were numerous helping hands in conducting the total research. It added a lot to my practical
exposure and knowledge.
I would like to express my gratitude to my course instructor Nikhil R. Dhar, Ph.D. whose generous guidance,
attention, and particularly unwavering encouragement always kept my focus on the desired work to be done
to conduct the research. The paper he provided devising exact key points how to write the findings helped
to shape this report.Nevertheless Md. Raisul Islam , Production executive of UTAh Garments helped with
his time and insights to get exact findings.
Finally I thank the almighty God for keeping me on track during the full process of the report.
Report
on
SCM
in
UTAH
garments
|4
3.Contents:
Table of Contents
1. Executive Summary:......................................................................2
2. Acknowledgement:........................................................................3
3.Contents:........................................................................................4
4. Company Information:...................................................................5
5. Analysis of Supply Chain Delivery Performance.............................5
UTAH Garments business structure:...............................................5
Manufacturer Lead time:................................................................7
Types of Inventory:..........................................................................8
6. SCM implementation Methodology Challenges:...........................10
Ticketing System:.........................................................................10
Log book:......................................................................................11
Employee attendance...................................................................11
Truck number entry......................................................................12
Forecasting:..................................................................................12
JIT layout:......................................................................................12
Particular challenges in implementation:......................................15
7. Business benefits of SCM implementation:..................................16
8.Summay:.......................................................................................17
9.References:...................................................................................18
Report
on
SCM
in
UTAH
garments
|5
4. Company Information:
Utah is one of the composite factories in Bangladesh. Its a Pakistani
multinational company. It has been operating since 2002 in Bangladesh and
its a 100% export oriented composite factory. Here dyeing, knitting, washing,
printing, embroidery are done full proficiently.
In the two garments, there are 76 lines. They have many departments for
maintaining the sector like production, quality, cutting, merchandising,
planning, industrial engineering etc. Most of their buyers are from European
Union who are working with them cooperatively. H&M, addidas, next, jordous,
jecipeny, carters, puma, s- oliver, American eagle etc are their main branded
customers. They have around 10000 employees and per day approximate
100000 pieces of garments are produced from this garments.
Report
on
SCM
in
UTAH
garments
|6
Foreignbuyers
Garments Company
Manufacturer
Information flow
Report
on
SCM
in
UTAH
garments
|7
From the above equation, we can say that through the first four stages a
manufacturer received fabrics fromthe suppliers after 60 days on average.
Report
on
SCM
in
UTAH
garments
|8
Out of this the shipping time of 25 days is constant. There was no chance to
reduce this shipping time but they could successfully reduce the rest 35 days.
There are two parties and various activities involved between suppliers and
manufacturers in the supply chain. It can be seen in the fig.-4 broadly. The
activities and time consumption area have been illustrated here through four
boxes (A-D) or stages.
Normal scenario was the following flowchart:
(A) Supplier
received order
from fabric
(B) Manufacturing
Fabrics &
shipments
(C) Unloading
fabrics at sea
Port
Manufactu
rers Plant/
Warehous
e
After final contract with the buyers, manufacturers first place order to the
foreign fabrics supplier (A). Then the supplier manufactures fabrics (B) and
sends fabrics by shipment. After a certain time the ship reaches at the port
(C). Here after unloading and completing some custom formalities fabrics are
sent through train or road transport to the manufacturers productionplant/warehouse (D). For this total process from A-D manufacturers need 5575 days.
They thought that at the time of import a proper management in the supply
chain could reduce 30-35 days. The rest of the time of 25-35 days is needed
only for shipment. Management in the supply chain could reduce 30-35 days.
The rest of the time of 25-30 days was needed only for shipment. Most of the
buyers of UTAH group have their regional office in Bangkok or Singapore.
One of the largest European garment sub-contractors based in Dhaka is
Hennes & Mauritaz (H&M) from Sweden (Asia invest, p-11, Sector 4.). The
regional offices and the buyers resident in Dhaka can build a stock of the
required quality of fabrics in advance before making final contract with the
manufacturers. It contributed definitely to reduce the manufacturing time.
Again the proper and efficient management at port and good transportation
Report
on
SCM
in
UTAH
garments
|9
Types of Inventory:
There are mainly four types of regular inventory in UTAH group.
Report
on
SCM
in
UTAH
garments
| 10
Scope of improvement:
Ticketing System:
This system allows to add tickets and number mark on each garments
stock carrier. They can identify which products container is for which
particular production and place those is respective area of raw
material. This can be improved by implementing KANBAN system.
KANBAN will allow the ware house materials to tag particular colored
tag with each box or cartoon according to their designated use and so
these will be easier to monitor the exact condition of them. If any
product is out of order or need to be changed that can be easily
identified by looking at the attached KANBAN.
Report
on
SCM
in
UTAH
garments
| 11
Log book:
When a particular sack or container is taken from ware house that is
noted manually in log-book and that is maintained over a period of time
and rechecked to make sure whether those are aligned to the total use
in production floor. Since all the data keeping are manual that
sometimes make is tough to find exact track of any products
movement.
KANBAN will be very helpful in maintaining exact flow of material and it
will be possible to keep track of the materials taken away from the ware
-house.
Employee attendance
There are many numbers of employee who are not that educated to
write their name by themselves. As they arrive at entry point their name
in entered in the attendance book by the helping hand of floor in
charge. These sometimes keep a secret gateway of false statement in
the attendance book.
An integrated ID verification system is must for this garments to exactly
identify everyones attendance.This may sound a very expensive and
time consuming work now but this will have a better impact in coming
future.
Less gap in working process and more authorized supervision will
increase productivity of the employee. Nevertheless many Bangladeshi
organizations are already implementing this system.
Report
on
SCM
in
UTAH
garments
| 12
Forecasting:
Techniques of forecasting must be revised and maintained in a more
handy way to reduce expenses of excess inventory. UTAH garments
presently follow and order the products when necessary and mainly the
button, Zipper these are ordered according to assumptions and spare
ones are not taken into considerations when a single order is
completed.
These techniques are age old and proper management in ordering
should be maintained to ensure best use of previously unused
resources. A computer generated number of the spare ones to all
departments will be able to provide the exact number of necessary
products when a single batch is under operation.
JIT layout:
According to regular operation in UTAH garments they are following
two types of arrangements in their production floor. One is in ZIGZAG
pattern and other is Y pattern.
They normally have 40-43 machines in a single line. For any knit wear
production they use this regular lines in ZIGZAG pattern. In time of
jeans production they use line consisting of 60-70 machines and use U
shaped pattern. Very minimal number of products of special attention
are prepared by Y shaped production line.
Warehouse is in a separate floor. But in condition of JIT layout excess
space in single unit could be used for regular inventory and time
management would be more efficient.
In JIT techniques similar functionalities are managed in single room
comprising of similar functionality technicians. These cross functionality
Report
on
SCM
in
UTAH
garments
| 13
Report
on
SCM
in
UTAH
garments
| 14
Problem I identified with this layout is these machines are fixed and very
heavy to move. So ultimate utilization of floor space is not possible yet. It
would be a better idea if these machines were made moveable to redesign
the overall area in term of utilization of JIT layout.
Report
on
SCM
in
UTAH
garments
| 15
Report
on
SCM
in
UTAH
garments
| 16
Generate sourcing plans that keep inventories in sync with everchanging forecasts and static capacity constraints
Report
on
SCM
in
UTAH
garments
| 17
It is observed that company first identify and work on reducing and eliminating
non-valued added activities, processes and components in the business. It is
only when they start to adopt a holistic view to efficiently address enterprise
needs that they will be able to deliver their products and services with speed,
ease and quality.
8.Summay:
Based on the above discussion the following decisions can be made:
All the business channels should work better to implement the
wide spread opportunity of supply chain management.
ERP system will reduce substantial amount of work load and
help to monitor work process.
Implementation of KANBAN will help to keep good track of
material flow through the inventory and warehouse and
transparency will be more prevalent.
Relationship with supplier will lead to reduced lead time and
more accurate measure of cost in production process.
Better flow of information through the channel will make sure
that the value chain partners are provided with enough
emphasis.
Variable task performed by workers will increase flexibility in
the working environment.
Report
on
SCM
in
UTAH
garments
9.References:
1. http://www.ajbms.org/articlepdf/7ajbms2012282716.pdf
2. Interview with Mr. Raisul Islam. Industrial engineer(executive)
3. Official website of UTAH group.
4.
https://globaljournals.org/GJMBR_Volume14/4-Supply-ChainManagement-in-Garments.pdf
5. Slides of honorable Nikhil R. Dhar, Ph. D, Professor, IPE
Department, BUET
| 18
Report
on
SCM
in
UTAH
garments
| 19