ID Task Name September October November December January February March April May June

Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10Week 11Week 12Week 13Week 14Week 15Week 16Week 17Week 18Week 19Week 20Week 21Week 22Week 23Week 24Week 25Week 26Week 27Week 28Week 29Week 30Week 31Week 32Week 33Week 34Week 35Week 36Week 37Week 38Week 39Week 40
1 Foundations Foundations

2 Site Strip Foundation Exc + Concrete Site Strip Foundation Exc + Concrete

3 Substructures Substructures

4 GF: Subase & Slab GF: Subase & Slab

5 Timber Frame Timber Frame

6 GF: Timber Panelling GF: Timber Panelling

7 FF: Joists FF: Joists

8 FF: Timber Panelling FF: Timber Panelling

9 Roofing Roofing

10 Joiner Joiner

11 Plumber & Slater Plumber & Slater

12 Superstucture Superstucture

13 Superstructure Superstructure

14 First Fix First Fix

15 Electrical Electrical

16 Plumber Plumber

17 Joiner Joiner

18 Walls Walls

19 Internal Internal

20 External External

21 Second Fix Second Fix

22 Electrical Electrical

23 Pumber Pumber

24 Joiner Joiner

25 Decoration Decoration

26 Decoration Decoration

27 Drainage and External Works Drainage and External Works

28 Drainage and External Works Drainage and External Works

29 Drainage and External Works Drainage and External Works

30 Sevices Sevices

31 Site Tidy & Handover Site Tidy & Handover

32 Christmas Break Christmas Break

Task Progress Summary External Tasks Deadline


Project: Programme of Works
Date: Mon 16/08/10 Split Milestone Project Summary External Milestone