Beruflich Dokumente
Kultur Dokumente
OVERVIEW
1.1 Introduction
The economical generation of electrical energy and huge demands for power
requires creation of bigger and bigger powerhouses, may these be hydro electrical, steam
or atomic. The powerhouse may be far away from the load centers as in the case of
hydropower houses or they may be midst. Populated areas as in case to transformation
and switching stations house to be created. These are generally known as substation.
1.2 Type of Sub Station
Depending on the purpose of substation may be classified as
1. Step up sub station
2. Primary grid sub station
3. Secondary sub station
4. Distribution sub station
5. Bulk supply sub station
The step of substation is associated with the generation station. The generation
voltage is limiting to a low value and needs to step up to the primary transmission voltage
so that huge blocks of power can be carried over long distance to the centers
economically.
The primary grid sub stations are created at suitable load centers along that
primary transmission voltage is stepped down to a number of suitable secondary voltage.
From here secondary transmission lines are carried over to the load points.
Along this secondary transmission lines secondary substation are created to actual
load points where the voltage is further stepped down sub transmission and primary
distribution voltage.
The distribution substation are created where the sub transmission voltage/primary
is step down to supply voltage, these substation feed the extra consumer through a
network to distribution of and service lines.
The bulk supply and industrial sub stations are generally distributed substation
with the difference that the substation is created separately for a consumer and subsequent
distribution of the electric power or left to the particular consumer of large or medium
supply group. As may be designed by the standard laid down by the electrical supply by
undertaking.
1
A substation is immediate link between the generating stations. The generation of
electricity at low voltage link 6.6-KV or 11-KV is done although high voltage up to 33
KV is also possible but it is not expected due to economical condition. For economical
transmission of electric power, we transmit power at a very high voltage. As we know
voltage drop along the length of transmission line. We have to maintain the voltage at
such a high level that it may not be lost during transmission. Thus for the sake of efficient
transmission and considering the economical aspect all electrical authorities operating
high voltage at transmission level.
While at distribution level electrical service provides require a voltage level that
suits consumer electrical electrical equipment for this purpose we have to provide smoke
kind of stations for following reasons.
1. To maintain the voltage in original high transmission voltage.
2. To step down the voltage up to distribution load.
3. To cut the supply of desired related area, in case of any kind of damage.
All GSS are linked to each other to form network as power grid. In India, we have
two power grids; they are northern and southern power grid.
Generally we operate ring scheme of power grid.
CHAPTER- 2
2
INTRODUCTION TO 132-KV G.S.S., R.R.V.P.N.L.
MANSAROVER, JAIPUR
2.1 Introduction
R.R.V.P.N.L.. was constituted by government of Rajasthan power development
department with the general duty of promoting & coordinating development of
generation, supply & distribution of electricity within the state in the most efficient &
economic manner.
To make power system more reliable & efficient inter-state Grid system was
regional electricity Board to promote integrated operations of the constituent power
system:
1. Northern Zone
2. Western Zone
3. Eastern Zone
4. North-Eastern Zone
Regional load dispatch centers have been established to co-ordinate the activities
of state load dispatch centers so as to ensure optimum utilization of generation &
transmission facilities in the regions.
.
This is substation in Rajasthan. The various feeders are 132-KV single circuit line from
SANGANER & CHAMBEL.
4
With these basic requirements there are several bus bar arrangement are as
follows:-
1. Single bus bar arrangement.
2. Duplicate bus bar arrangement
3. Sectionalization of bus bar.
4. Ring bus.
5. One and a half breaker arrangement.
6. Mesh arrangement.
In 132-kV G.S.S. one and a half breaker arrangement scheme is adopted
between main-1 and main-2 busses.
2.5 One and A Half Breaker Scheme:
Breaker and a half scheme or one and a half breaker scheme is sometimes called the
three-switch scheme, as there are three breakers in series between the main buses. As two
circuits are connected between three breakers, hence the term breaker and the half breaker
are used for each circuit. Under normal operating conditions all breaker are closed and
both buses are energized. Opening the associated two circuit breakers trips the circuit.
This is scheme-having flexibility to attend any element in this switchyard without
losing the circuit. It occupies single bay space for two feeders oriented in diagonally
opposite directions. All the incoming feeders from generating units are in one direction
while out going feeders are oriented in opposite direction.
The breaker and half arrangement are more expensive than other scheme, however
breaker and a half scheme are superior in flexibility reliability and safety.
5
CHAPTER- 3
VARIOUS EQUIPMENT
3.1 Different Equipment of Switchyard Used In G.S.S.:
Some equipment are used in the G.S.S. for successful operation of breaker and a
half scheme between two buses, they are
1. Lightning arrester
2. Capacitor voltage transformer
3. Wave trap
4. Isolator
5. Circuit breaker
6. Current transformer
3.2 Lightning Arrester
3.2.1 Introduction:
Every instrument must be protected from the damage of lightning strokes. The three
protections in sub stations are essential:
1. Protection for transmission line from direct strokes.
2. Protection of power station or substation from direct strokes.
3. Protection of electrical apparatus against traveling waves.
Effective protection of equipment against direct strokes requires a shield to prevent
lightning from striking the electrical conductor together with adequate drainage facilities
over insulated structure.
3.2.2 Lightning Arrester:
Lightning Arrestor is a device, which protects the overhead lines & other
electrical apparatus viz., transformer from over head voltages & lighting. When the
positively charge cloud produce negative charge on the overhead line by electrostatic
induction than the negative charge is however presented just under the cloud & portion of
the line away from the cloud becomes positively charged. This charge on the line does not
flow. Figure 3.1 (below) shows the lightning arrester.
The positive charge on the far end flows to the earth through insulators, thus
leaving the negative charge on the line directly under the cloud. Now assume due to the
direct discharge occurring between this cloud & passing by negative charge on the line is
no more bound charge & is free to travel on the both direction in the form of waves.
6
Figure-3.1 Individual Lightning Arrestor
These traveling waves will be of light magnitude & have steep wave front, which
can damage the unprotected equipment connected to the line. These waves are passed to
the earth through the lighting arrestors.
In this G.S.S., the lighting arrestors used are “THYRITE ALUGARD STATION –
class lighting arrestors”, Lighting Arrestors are provided with proper Earthing. Lighting
Arrestors are installed on a concrete block which project above ground by 305 mm.
Lighting Arrestors are always with a mounting name “Discharge Counter”.
It consist of a isolator in series & connected in such a way that long isolator is in
upward & short isolator is in downward so that initially large potential up to the earth is
decreased to zero.
3.2.3 Valve Type Lighting Arrestor:
Basic Lighting Arrestor has spark gap & resistance with non-linear characteristics.
The spark gap consists of series of electrodes whose spark gap is broken. In Heerapura
G.S.S. the units consist of number of main gap, a non-linear resistor, in parallel with non-
linear resistors. A lighting surge of short duration mainly passes through parallel resistors
while a switching surge & power frequency current passes through magnetic coils.
7
All electrical equipments are protected from the severe damage of the lightning
strokes which is studied from the view of following protection:
1. Power station & sub stations from direct strokes.
2. Overhead transmission line from direct strokes.
3. Electrical apparatus from traveling waves.
3.2.5 Protection of Transmission Line From Direct Strokes:
Effective protection requires a shield to prevent lighting from striking to electrical
conductor together with adequate drainage facility over instruction so that discharge can
drain to ground.
Although ground wire runs over lines protects against lighting & reduces induced
Voltage but inadequate to protect ant traveling waves which reaches the terminal of
electrical this causes following damage:
1. High Voltage causes flash over in internal winding.
2. High Voltage causes internal flash over between the terminals of electrical equipment.
3. Step wave front of the surge may cause internal flashover between the turns of
transformer.
3.2.6 Lightning Arrestor Meter:
This meter indicates the sum of surface leakage & internal grading current of the
arrestor. It has three different indicators to indicate different conditions:
1. Green- Arrestor is healthy.
2. Red- Defective, Remove from service.
3. Counter- Maintains counts of operation undergone by the arrestor.
3.2.7 Location of Arrestors:
It is common practice to install the lightning arrestor straight on the terminals of
transformer. The lighting arrestor may be installed at a distance less than maximum
permissible from the transformer. So as to include the other substation equipment within
the protective zone in case the lighting arrestor is installed towards line side of circuit
breaker then it needs to be ensured that the lighting arrestor has adequate thermal capacity
to discharge the switching surges particularly on extra high voltage lines when circuit
breaker are not restrict free.
3.2.8 Caution:
8
Test on high voltage by common meggar do not provide correct assessment of its
health. Never leave the earth terminal if the arrestor underground by pass the monitor
with an earth shunt engaged in any work on its terminal.
9
In P.T. we use the coupling capacitor but C.V.T. it is eliminated and if we use the
PT in yard. It is very expensive due to the fact that the transformation ratio is high and the
size of the PT is high than a C.V.T. of same capacity.
So that C.V.T. are used in G.S.S. as shown below in figure- 3.2.
Figure-3.3 Isolator
One contact arm has a male contract while other has female contact. Insulation
supports contact arms. Contacts are made or broken by motor operated mechanism. When
contact is to be opened then both arms are rotated in opposite direction so that contact is
broken. Same time Earthing pole moves upwards to make contact with the female contact
situated adjoin to the terminal stud. Hence the terminal gets earthed. On this criterion
isolators can be distinguished as single earth or double earth. Through all the operation
can be carried out manually but for quick operation motor is used.
3.4.2 Rating of Air Breaker Isolator:
1. Make S&S power switchgear ltd.
2. Motor operated mechanism.
3. Rated impulse voltage :1425kV
4. Rated Amperes :2000 Amps
5. Rated mechanical term load :160 kg
6. Auxiliary voltage :220V
7.Company :ELC
11
3.4.3 Earthing Switch:
Earthing switch is connected between the line conductor and earth. Normally it is
open. When the line is disconnected, the earth switch is close so as to discharge the
voltage trap on the line. Though the line is disconnected, there is some voltage on the line
to which the capacitance between line and earth is charged. This voltage is significant in
high voltage system. Before starting the maintenance work these voltages are discharged
to earth by closing the Earthing switch.
3.5 Circuit Breaker
As in 132-kV G.S.S. a very high amount of current flows in circuits and whenever
it is necessary to open a circuit due to any reason like to work a transformer, breaker,
isolator or line circuit breaker is used.
3.5.1 Basic Concept of Using Circuit Breaker:
In any circuit carrying a large amount of current, if a contact is open then
normally a spark is produce to fact that current transverses its path through the air gap.
Arcing is harmful as it can damage precious equipments as well as it can harm any
personal nearby. So as to prevent that arcing circuit breaker are used in which different
arc quenching media are provided between contacts.
3.5.2 Different Arc Quenching Media:
1. SF6 circuit breaker
2. Oil circuit breaker
3. Air blast circuit breaker
4. Vacuum circuit breaker
In 132-kV G.S.S. only SF6 gas circuit breaker are used as for generally in G.S.S.
SF6 type breakers are very efficient.
3.5.3 SF6 Circuit Breaker:
The outstanding physical and chemical property of SF6 gas makes it an ideal
dielectric media for use in power switchgear. These properties are included: -
1. High dielectric strength
2. Unique arc quenching ability
3. Excellent thermal stability
4. Good thermal conductivity
In addition, at normal temperature SF6 is chemically inflammable, no corrosive and
non condensable at low temperature. A SF6 circuit breaker is shown below in figure- 3.4.
12
Figure-3.4 SF6 Circuit Breaker
14
3.6 Rating of Circuit Breaker:
Specification : SF6 gas
Make : BHEL, Hyderabad
Type : 3AT3
Rated Voltage : 420 kV
Rated Impulse with stand voltage Lightening/switching = 1425/1050 kV
3.6.1 Rated Power Frequency:
Voltage : 520 kV peak
Rated Frequency : 50Hz
Rated Normal current : 200 Amp
Rated short time current : 40 K Amp
Rated Short Time Duration : 1 Sec
First Pole to clear Section : 1.3
Breaking Capacity Symmetrical : 40 K Amp
Equivalent 2900 MUA
Asymmetrical 49 K Amps
Rated making Current : 100 K Amp
Rated Operation Duty : 0.3 sec to 3 min
Rated pressure of Hydraulic : Operating Mechanism (Gauge)
250-350 bar
3.6.2 Rated Pressure of SF6 Gas:
20 dg. C (gauge) : 7.5 bar
Weight of complete breaker : 11700 kg
Weight of SF6 gas : 76.5 kg
Rated trip coil voltage : 220 V dc
Rated closed coil voltage : 220 V dc
3.7 Transformer
1. Transformer is an A.C. machine that
2. Transfers electrical energy from one electrical circuit to another
3. Does isolator without a change of frequency
4. Does isolator by the principle of electromagnetic induction and
5. Has an electric circuit that is linked by a common magnetic circuit.
15
When the transformer raises the voltage i.e. when the output voltage of a
transformer is higher than its input voltage, it is called the step-up transformer and when
it lowers the voltage it is called the step down transformer.
In our G.S.S. four step down transformers are used. There are changes the voltage
from 132-kV to 33-kV (r.m.s.) and all have the power of 25 MVA. One transformer is of
50 MVA and it also step down the voltage from 132-kV to 33-kV (r.m.s.). The voltage
transformation in a 3-phase network can be had by means of either a band of three single-
phase transformers or a single 3-phase transformer. A single unit 3-phase transformer
consists essentially of 3-phase transformer with them three cores united into a single core
assembly like single-phase transformer.
The unique arrangement of the windings and the core in a 3-phase transformer
makes it possible to save a great deal of iron by inter locking the magnetic circuits
isolator that the same iron is used by the three phase simultaneously.
Since the entire three phase assembly is reduced in size and is placed in a single
tank, additional saving results because less transformer oil is used, fewer transformer
bushings are required (All polyphone connections are made inside the tank) and the
complete transformer occupation the less floor space than a bank of three single phase
transformer.
A 3-phase transformer is cheaper (about 15%) than a bank of three single-phase
transformers. It is due to saving in cost of the iron core, of the tank and oil of the bushing
and of the aux, apparatus.
A 3-phase transformer is slightly more efficient than a bank of 3 single-phase
transformers. This is due to the fact that it has shorter magnetic path and consequently the
core volume and hence the core loss is smaller. A 3-phase transformer is shown below in
figures-3.7.
16
3.7.1 Tertiary Winding:
Transformer may be built with a third winding called the tertiary, in addition to
the normal primary and secondary and such transformer are called the triple wound (3
way transformer) transformer. The tertiary winding may serve any of the following
properties or purposes.
1. To supply the sustain auxiliaries of a voltage different from that of the primary of
secondary winding.
2. To supply phase compensating device, such as condensers operated at a voltage, which
is different from both primary and secondary voltages.
3. To interconnect three supply systems operating different voltages.
4. To load large split winding generators.
5. To measure voltage of an H.V. testing transformers.
6. In star/delta-connected transformers, to allow sufficient earth fault current to flow for
operation of protective equipment, to suppress harmonic voltages, and to limit voltage,
unbalance. When the main load is unsymmetrical.
The tertiary winding is called the auxiliary winding when it is employed. For
supplying on additional small load at a different voltage On the other hand, it is called the
establishing winding when it is employed to limit the short circuit current.
Tertiary winding are normally delta-connected isolator that when faults and short
circuits occur on secondary side the considerable unbalance produced in phase voltage
may be compensated by the circulating currents flowing in a closed delta. Reactance of
the winding should be large enough to limit produced in phase voltage may be
compensated by the circulating currents flowing in a closed delta. Reactance of the
winding should be large enough to limit the circulating currents in order that there is no
overheating of the windings.
3.7.2 Auto Transformer:
In auto-transformer the primary and secondary winding are completely insulated
from each other but are magnetically linked by a common core. In the auto-transformer,
the two windings, primary and secondary are connected electrically as well as
magnetically; in fact, a part of the single continuous winding in common to primary and
secondary section of this one winding are not the same magnetic circuit.
Due to use to auto-transformer some advantage is present.
1. Only one winding is used for both winding isolator the spacing is less required.
2. Required of copper is less isolator the ohmic lass is reduced.
17
3. Less insulation is required.
4. Handling of KVA is easier than the other two winding transformer.
3.7.3 Tap Changing Transformer:
The voltage variation in power system is a normal phenomenon owing to the rapid
growth in induction and distribution network. Therefore it is very important to keep the
consumer’s terminal voltage within the limit. The transformer output voltage and isolator
the consumer’s terminal voltage may be controlled by providing tapping on the
transformer winding (either on the primary or secondary side) the principle of regulating
the secondary voltage is based on changing the number of turns on the primary or
secondary i.e. on changing the ratio of transformation. Decreases in primary turn cause
inverses in e.m.f. per turn, and in secondary output voltage secondary output voltage can
also be increased by increasing secondary turns and keeping primary turn fixed.
There is always a tapping on the H.V. side which when connected to the rated
voltage gives rated voltage on the l.v. side.
3.7.4 Specification:
25 MVA Transformer
Type : SAFLOCR< FOM-3 AMNYSCP
Making : Telk
Capacity : 25 MVA
Voltage : 400/200/33 kV
H.V. – 150/200/250
MVA I.V.–150/200/250
L.V. – 50/66.67/83.33
H.V. – 220,000
Volt on no Load I.V. – 132,000
L.V. – 33,000
H.V. – 217/289/361
Line Current I.V. – 394/525/656
(Amp) L.V. – 845/1156/1485
Phase :3
18
Frequency : 50 Hz
Diagram No. : TK204139
H.V. – I.V. 12.76%
Impedance I.V. – L.V. 38.51%
(250 MVA Base Normal Tap) I.V. – 25.76%
50 MVA Transformer
H.V. – 189/252/315
MVA I.V. – 189/252/315
L.V. – 63/84/105
H.V. – 273/364/455
Line Current I.V. – 497/62/828
19
L.V. – 1104/1741/1880
Vector Symbol : Y Na Odll
Mass of Oil : 65150 kg
Total Mass : 261200 kg
Untaking Height : 7760 mm
Impedance Voltage H.V. – I.V. HTAP 11.39%
(315 MVA Base) H.V. – I.V. RTAP 11.82%
No. of Phase 3 I.V. – I.V. LTAP 12.65%
Frequency – 50 Hz H.V – L.V. RTAP 39.16%
I.V. – L.V. RTAP 26.66%
3.7.5 Transformer Accessories:
1) Bushing: Bushing are held on the top of the part of transformer and through it he
conductor goes of outside for connection from the transformer inner part and vice-versa.
In step down transformer the conductors goes in on H.V. side through
bushing and take out the conductor on I.V. side.
20
All type of faults occurring with oil filled transformer is accompanied by
more or less violent generation of gases, which the heat liberate, from the oil. This
phenomenon has been fully utilized to provide complete internal protection of
transformation. The falling oil level, which may eventually lead to a dangerous situation,
is also detected by this relay in time.
Construction:
This is a hydraulic device, arranged in the pipe line between the mash transformer
tank and the conservator tank, it comprises, a cast iron having housing which contains
essentially two floats upper and lower. Each float carriers a switch, the leads from which
are taken to a terminal box.
The necessary pet-cucks for gas release site testing, and a drain plug on the body
of the housing are provided. Inspection windows are filled on both side of the relay
housing to see the oil level and to ascertain the volume of gas collected on a calibrated
scale ion cubic cm.
Principle of Operation:
When the transformer is healthy, the entire relay housing remains filled with oil
and the buoyancies of the respective floats flits the mercury which to the ‘open’ position.
When a slight or incipient fault occurs in the transformer, decomposition of gas
occurs & small bubbles of gas will be generated and these, attempting to pass from the
tank to the oil conservation, will be trapped in the upper portion of the relay housing. As
the gas accumulates, the oil level in the relay depresses, causing the upper float of built
thereby closing the mercury switch. The alarm circuit, which is usually connected to this
switch, gets emerged to ring an alarm bell, with a server internal fault; the gas generation
is rapid, causing the displaced oil to surge through the relay. This oil flow impinges on
the lower float. The lower float is thus deflected closing its mercury switch and
completing the trip circuit of the circuit breaker.
If the transformer suffers a loss of oil, causing the oil level to drop below the level
of relay, the buoyancy of both the floats will vanish on offer another, felting the
respective floats. First the alarm and then the surge elements will operate of close their
respective circuits.
3) Silica Gel Breather:
During the load cycle of a transformer the oil in which it is immersed expands and
contracts as its temperature rises and falls. This decreases and increases the air space
21
above the oil in the transformer and causes the transformer to breathe. During the cooling
position of the cycle air from the atmosphere is drawn into the transformer. The air may
be moist and, as the presence of moisture in transformer oil reduces the dielectric strength
of the oil and adversely affects the insulation of the transformer immersed in it, some
means of drying the incoming air is desirable.
In the dehydrating breather the air is desired by passing it through a tube
containing crystals of silica gel a substance with a great affinity for water. The crystals
are tirted blue when dry but saturated with moisture, and no longer effective then turn
pink. The gel, however, is unchanged chemically and the crystals can be restored to their
original dryness and blue color by heating in a shallow pan at a temperature of between
150o C to 200o C for two to three hours.
The breather is piped to the air space above the oil in either the transformer tank
or the conservation and forms the only entry and exit for the air this space. The crystals
are contained in a metal cartridge with a window to give a clear view of the color of the
gel the metal cartridge can be withdrawn by unscrewing the using nuts/hex nuts and then
removing the lower portion of breather.
At bottom of the breather, cup containing transformer oil is covered. This oil acts
as a seal, preventing the crystals from absorbing moisture except when breathing is taking
place. Oil level is marked on the maintained up to the level indicated before
commissioning the transformer.
If the color of the gel is pink, it is to be reactivated by heating. A silica gel
breather is shown above in figure-3.11.
22
4) Conservator: Oil is collected in the conservation. It is situated at the top of the
transformer. In this tank air is prohibited between the upper oil layer and the top inside of
conservation.
5) Pressure Relief Valve:
Pressure relief valve is designed to be used on power transform. When
pressure in the tank rises above predetermined safe limit this valve apparatus and
performs following function.
Allow the pressure to drop by instantaneously opening a part of about 150
mm diameter.
Give valve operation by raising a flag.
Operates a micro switch. This switch has four terminals hence switch can
be effectively used in conform circuit.
Construction and Working:
The Pressure relief valve has an integral flange with six holes for mounting. The
valve can be mounted vertically or horizontally on the tank. The Pressure relief valve has
got a part of about 150 mm diameter. A stain seals this part less steel. The diaphragm
rests on and ‘O’ ring and is kept pressed by two heavy-duty springs, thereby keeping the
port closed. The other side of diaphragm is exposed to tank. Pressure rises due to any
reason, the same pressures acts on diaphragm from inside. When pressure rises above
predetermined safe limit the diaphragm gets lifted from it seat. This lifting is
instantaneous and allows vapors, gases or liquid to come out of the tank depending upon
the position of valve on tank. The diaphragm restores its position as soon as pressure in
the tank below set limit. The lit of the diaphragm is utilized to operate flag and micro
switch with the help of red. The flag and switch remain operated until they are reset
manually.
6) Oil Level Indicator:
It is manufactures considering transformer application. It can also be used as
content gauge on other tanks where level of liquid inside the tank is required to be
indicated continuously on a dial.
Construction Working:
A float is used as sensor of liquid level inside the conservator. Swing of hinged
float due to the change in liquid level is utilized to indicate level on a calibrated dial and
to operated at which for external alarm unit.
23
User of magnetic coupling in the indicator achieves completes sealing of liquid
inside the conservation from surrounding atmosphere.
The result in avoiding any leakage of costly oil and avoiding contamination of
insulating oil due to leakage of surrounding air in the conservator.
The glass mercury switch is nylon encapsulated to avoid breakage and spilling of
mercury.
Switch is accessible for servicing while indicator is mounted on the conservator
without any necessity of draining the oil.
One mercury switch is provided for low oil level alarm. The normally open switch
close when oil drops to 10 mm above empty levels i.e. 75 mm room bottom of
conservator heads from mercury switch are brought into a terminal box positioned at the
bottom of indicator.
7) Winding temperature indicator:
As the thermometer pocket houses the temperature-sending device of the winding
temperature indicator. The WTI records the winding hot spot temperature. The working
and construction of the thermometer are described in the attached leaflet. Three sets of
adjustable mercury contacts are provided, one to actuate the fans when the load exceeds
the ‘ON’ rating of the transformer, and the other two contacts for actuating the alarm and
trip contacts on the main control panel. The instrument is housed in the box.
8) Marshalling Box:
The marshalling box is of sheet steel weather proof construction mounted on the
side of the transformer. It is provided with hinged door and pad lock, and houses the
following instruments and terminal blocks.
1. Winding Temperature indicator
2. Oil temperature indicator
3. Terminal block for alarm and tripping contacts of Buchloz Relay
4. Terminal blocks for oil level alarm contacts of magnetic oil level gauge.
5. Cooler supply switch
6. Heater supply switch
7. Fuses links and terminal block etc.
A heater in the marshalling box to avoid condensation of moisture inside the box.
9) Cooling equipment:
24
Transformer having mixed cooling ONAF and ANOF is provided with through
values.
3.8 Current Transformer
Instruction transformers used in conjunction with ammeter, overcorrect relays, etc.
current ratio is transformer step-down current from high value to a low value. Their
current ratio is substantially constant of given range of primary current tend phase angle
error is within specified limits. The VA rating of current transformer is small as compare
with that of a power transformer.
A current transformer is provided for the winding temperature indicating
equipment. The current transformer has a rectangular core, and the primary is formed by
phase ‘V’ of the transformer LV located inside the tank. The secondary of the C.T. is
connected to heater element located in the thermometer itself. A pocket on the tank cover
houses the temperature sensing device of the temperature recorded two terminals and
brought out from the current transformer secondary circuit to the tank cover.
An instruction plate giving the diameter of connection for testing the C.T. and for
connection to the heater oil has been provide inside the terminal box.
3.8.1 Rating of Current Transformer
Make : W.S. insulation of India Limited
Rated Frequency : 50 Hz
Hide Side Volt : 420 kV
Weight of Oil : 750 kg
BIL : 630/1425 kV
Current Ratio : 2000-1000/12000-1000-500
Turn Ratio : 2000-1000/2000-1000-500
Core No. : 1 and 2, 3, 4 and 5
Output (VA) : 40 Accuracy Class P.S.O.
CHAPTER- 4
PROTECTION AND CONTROL
4.1 Protection and Control:
25
Protective will are used for protection. Protective relay are connected in the
secondary circuit of current transformer or potential transformer. The relay senses the
abnormal condition & closed the trip circuit of associated circuit breaker. The circuit
breaker open it’s contents one are between the contacts. As they separate the arc is
extinguished by suitable medium technique.
The relay distinguish between normal & abnormal condition whenever an
abnormal condition develops, the relay closed it’s contacts there by the trip circuit
breakers & circuit breakers opens & faulty point is disconnected flow the supply, various
types of relays used for power system.
4.2 The Various Type of Relay Installed at 400 KV G.S.S. are:
1. Buchloz Relay
2. Over Current Relay
3. Earth Fault Relay
4. Over Voltage Relay
5. Differential Relay
6. Bus Bar Relay
1) Buchloz Relay: Gas operated relay, commonly known as Buchloz relay is used
for protection of oil immersed transformers, reactors etc. It is as shown below in
figure-4.1.
All type of faults occurring with oil filled transformer are accompanied by
more or less violent generation of gases, which the heat liberate, from the oil. This
phenomenon has been fully utilized to provide complete internal protection of
transformation. The falling oil level, which may eventually lead to a dangerous situation,
is also detected by this relay in time.
26
Construction:
This is a hydraulic device, arranged in the pipe line between the mash transformer
tank and the conservator tank, it comprises, a cast iron having housing which contains
essentially two floats upper and lower. Each float carriers a switch, the leads from which
are taken to a terminal box.
The necessary pet-cucks for gas release site testing, and a drain plug on the body
of the housing are provided. Inspection windows are filled on both side of the relay
housing to see the oil level and to ascertain the volume of gas collected on a calibrated
scale ion cubic cm.
Principle of Operation:
When the transformer is healthy, the entire relay housing remains filled with oil
and the buoyancies of the respective floats flits the mercury which to the ‘open’ position.
When a slight or incipient fault occurs in the transformer, decomposition of gas
occurs & small bubbles of gas will be generated and these, attempting to pass from the
tank to the oil conservation, will be trapped in the upper portion of the relay housing. As
the gas accumulates, the oil level in the relay depresses, causing the upper float of built
thereby closing the mercury switch. The alarm circuit, which is usually connected to this
switch, gets emerged to ring an alarm bell, with a server internal fault; the gas generation
is rapid, causing the displaced oil to surge through the relay. This oil flow impinges on
the lower float. The lower float is thus deflected closing its mercury switch and
completing the trip circuit of the circuit breaker.
If the transformer suffers a loss of oil, causing the oil level to drop below the level
of relay, the buoyancy of both the floats will vanish on offer another, felting the
respective floats. First the alarm and then the surge elements will operate of close their
respective circuits.
27
Several protection devices are used for over current protection, which ultimately
isolate the circuit. These include (1) Fuses (2) circuit breaker fitted with overload coils (3)
series connected trip coils (4) over current relays in conjunction with current transformer.
3) Earth Fault Projection:
When the fault current flows through earth return path the fault is called Earth
faults, which don’t involve earth, are called phase fault. Since earth faults are relatively
frequency, therefore relays are necessary in protective systems. It is noted that phase
relays also sense the earth fault current. Following are the method of earth fault
protection.
Residually Connected Earth Fault Relay:
In absence of earth fault
Irresidual = Ias + Ibs +Ics = 0
when earth fault occur and if residual current is above the pickup value of earth fault relay
then earth fault relay will be operated.
Combined Earth Fault & Phase Fault Protection:
The increase in current of phase cause corresponding increase in respective
secondary currents. The secondary flows through respective relay unit. Very often only-
phase relays are provided instead of three because in case of phase fault currents in any
two phases must increase. Hence two relays are enough. The earth fault relay is residually
connected.
For various fault the relay will also operated as follows:
1. Between R & Y phases R phases o/c relay will operate.
2. Between Y & B phases B phases o/c relay will operate.
3. Between R & B phases R & B phase o/c relay will operate.
4. Between R phase & earth o/c R & e/f relay will operate.
5. Between B phase & Earth o/c B & e/f will operate.
6. Between Y phase & Earth e/f relay will operate.
4) Over Voltage Protection:
There are many reasons for the Voltage in the power system mainly classified as
external & internal source. The most once are:
1. Lightning
2. Neutral displacement during line to ground fault.
3. Operating of switching and over current protective equipment.
4. Resource effects associated with inductance and capacitance in series.
28
The system can be protected against external over voltage by using a shielding method
which does not allow an arc path to form between the line conductor and ground, there by
inherent protection in the line designs. For protection against internal voltage normally
non-shielding methods are used which allow an arc path between the ground structure and
the line conductor but means are provided to quench the arc. The use of ground wire is a
shielding method where the use of spark gap and lighting arrestors are non-shielding
methods.
5) Differential Protection:
In this protection a different relay operates when the vector difference of two or
more similar electrical quantities exceeds a predetermined value. Most of the different
relays are current differential relays are current differential relay in which vector
difference between current entering the protected element and current leaving the
protected element is used for relay operation. For this purpose two current transformers
have the same ratio of transformation & their secondary are interconnected. Differential
protection is unit type protection.
6) Bus Bar Protection:
To protect bus bar of important G.S.S. and to clear Bus faults, bus bar protection
is used. This is based on the differential basis. All the secondary of current transformer on
the same bus are connected in such a manner that during normal condition the sum of
CT’s secondary current is zero. During the fault condition the current reaching to the bus
is more than the leaving the bus as some current is fed to this fault and the excess current
is fed to a relay which operates and tripping signal is given to all the breakers connected
to the bus thus isolated the faulty bus.
Synchronizing
Before coupling any incoming feeder to bus base it must be synchronized with bus
bar voltage.
The voltage can be checked by voltmeters. The function of synchornoscope is to
indicate the difference in phase and frequency and voltage of bus bar and incoming
feeder.
Energy meters are fitted on different panels to record import and export of power.
Frequency meters are fitted on different or each feeder of measure frequency.
There are analog of digital.
Voltmeter, ammeter and MUAR meter are provided on each panel for the
indication of voltage, line current and reactive power being supplied.
29
Power factor meters indication of p.f. of power max. demand indicator record the
max., this records the average power of over successive predetermined period.
4.3 Power Line Carrier Communication
This type of protection for transmission lines carrier current of frequency range
30-200 KHz in USA and 80-500 KHz in determined and transmitted and received through
the transmission lines provided with identical equipment consisting of transistor, receiver,
line tuning unit, master oscillator power amplifier etc.
Coupling Capacitor:
The carrier equipment is connected to the transmission lines through the
coupling capacitor, which is such value that it offers a low reactance to the carrier
frequency but high reactance to the power frequency. For example 2000 p.f. capacitor
offers 1.5 Mega ohms to 50 Hz and 150 ohm to 500 KHz. Thus coupling capacitor allows
equipment but doesn’t allow 50 Hz power frequency currents to enter the equipments. To
reduce the impedance further a low inductance is connected in series with the coupling
capacitor to form a resonance at carrier frequency.
CHAPTER- 5
OTHER PLANTS
5.1 Other Plants:
30
In 132-kV G.S.S. there is number of department. We will discuss them one
by one. The departments are:
1. Control Room
2. Power Line Carrier Communication Room
3. Fire Fighting Plant
4. Oil Testing Lab
5. Battery Room
6. Air Conditioning Plant
5.1.1 Control Room
The remote control of power switchgear requires the provision of suitable control
panels located at a suitable point remote from the immediate vicinity of CBS and other
equipment.
On each panel a control switch is provided for remote control operation of CBS
control switch for each isolator is provided. Indicator lamps are also provided to show
whether the isolator or CB is open or closed.
The color or signal lamps are as
Red: circuit breaker of isolator is closed position.
Green: Circuit breaker or isolator is open position.
In addition to visual indication an alarm is also providing for indication
abnormal conditions. When any tripping relay operates, its contents emerges an auxiliary
alarm relay, which on operation completes the alarm bell circuit.
Synchronizing:
Before coupling any incoming feeder to bus base it must be synchronized with bus
bar voltage.
31
The voltage can be checked by voltmeters. The function of synchornoscope is to
indicate the difference in phase and frequency and voltage of bus bar and incoming
feeder.
Energy meters are fitted on different panels to record import and export of power.
Frequency meter are fitted on different or each feeder of measure frequency. There
are analog of digital.
Voltmeter, ammeter and MUAR meter are provided on each panel for the indication
of voltage, line current and reactive power being supplied.
Power factor meters indication of p.f. of power max. demand indicator record the
max., this records the average power of over successive predetermined period. A control
room is shown above in figure-5.1.
5.1.2 Power Line Carrier Communication
This type of protection for transmission lines carrier current of frequency range 30-
200 KHz in USA and 80-500 KHz is determined and transmitted and received through the
transmission lines provided with identical equipment consisting of transistor, receiver,
line tuning unit, master oscillator power amplifier etc.
1. Coupling Capacitor:
The carrier equipment is connected to the transmission lines through the coupling
capacitor, which is such value that it offers a low reactance to the carrier frequency but
high reactance to the power frequency. For example 2000 p.f. capacitor offers 1.5 Mega
ohms to 50 Hz and 150 ohm to 500 KHz. Thus coupling capacitor allows equipment but
doesn’t allow 50 Hz power frequency currents to enter the equipments. To reduce the
impedance further a low inductance is connected in series with the coupling capacitor to
form a resonance at carrier frequency.
2. Line Trap Unit:
The line trap unit is inserted between bus bars and connection of coupling
capacitor of the line. It is parallel tuned circuit comprising L & C. it has a low impedance
approximately 1 ohm to 50 Hz and high impedance to the frequency signals from entering
the neighboring line and the carrier currents flows only in the protected lines.
33
Other Uses:
1. Station to station communication: In power line stations, substation and receiving,
telephones are provided. These are connected to the carrier current equipment &
conversation can be carried out by means of carrier current communications.
2. Remote control of power stations equipment by carrier signals.
3. Telemetering.
5.1.3 Fire Fighting System
For only transformer: In G.S.S. costlier and heavier equipment is the transformer.
So first need is the fire fighting system for protection in transformer.
For transformer “mulsifire system” is used. Basic principle of this system is that
its block’s the incoming oxygen by cover or enclosed the entire transformer by the use of
water with pressure.
Red pips are covered the concerns of the transformer as a cube. And yellow pipes
are also in the form of cube. In water lines the nozzles are kept one entire pipe around the
pipe transformer.
On the air pipe line quarter values are present. In these values has a glass tube,
which is broken, when the temperature of surrounding are increased beyond the
predetermined limit.
“Dilues Value” is present on water pipelines. It is controlled by pneumatic values.
When the fire s present at transformer due to increase in temperature the glass tube
of quarter values is broken so the pressure is reduced due to decrease of pressure the
dilutes value also opened and water came out from pipe through the fountain and make a
water net around the transformer. Thus the fire is quenched.
If the pressure is decreased from a certain level of pressure due to a failure
of electrical supply it is stated automatically.
Appearance:
At first the insulating oil is seeing by the engineers. Some judgment is taken, such
as which test is done at first etc. by appearance far good condition of insulating oil the
color may be lemon yellow type.
Break down voltage test:
Break down is the voltage at which the oil breaks down when subjected to an AC
electric field with a continuously increasing voltage contained in a specified apparatus.
The voltage is expressed in kV. It depends upon the degree of determine of liquid by
solid, especially hydroscope particles such fiber water contents of oil. Pressure of oil,
temperature of oil and dielectric strength are as follows-
36
In the gas chromate graph, after same time later automatic a graph is drawn which
shows the quantity of different gas in sample. For good oil Acetylene should be
negligible. Standard results of various gas content in the oil are as shown in table 5.1
below.
Table 5.1- Standard Results of Various Gas Content In The Oil
Gas Contents Standard Result for Oil
1 Hydrogen 100-150
2 Methane 50-70
3 Ethane 30-50
4 Ethylene 100-150
5 Acetylene 20-30
6 Carbon dioxide 3000-3500
7 Carbon mono oxide 200-300
37
Water electrolyte. In charged state, it has a specific gravity of 1.2 at temperature
of 30. In the battery room, batteries are mounted on wooden stand. The cells are installed
from stand by porcelain.
The conductor connecting the cells are greased and coated with electrolyte
resisting varnish. The room is kept continuously maintainable so that room is not
accumulated with acid vapors to avoid risk of explosion, smoking, winding etc. any arc is
prohibited in this room.
Operation:
The station batteries are normally kept floating across the float rectifier which also
supply the current and boost charge is off. The controller maintains the DC voltage, with
allowable limit i.e. 2%. The batteries are kept in healthy state at 2.1 to 2.2 Volt/Cell.
In case of emergency due to main failure station batteries supply the load when
the supply is restarted the batteries held to be recharged to achieve this. Boost charger is
switch ‘On’ by closing switch open thereby demurring the coil of contractor and batteries
are boost charge and the constant load is provided by connecting the load to coil for
continuity of supply between battery and load.
Specification:
Ampere-hour capacity is that quantity of electricity at fully discharged battery- 1.1
at temperature 20.
1. Fixed charge current – 24 A
2. First charge ampere-hour input – 2300 A
3. Normal recharge current – 45 A
4. Finishing charge current – 2 A
5. Recommended heating voltage of batteries – 2.16 to 2.18
Charging:
The input of charging source should have a voltage equal to the number of cells in
the batteries multiplied by 2.7 and should be capable of delivering continuously a current
in amperes equal to the normal charging rate of the battery.
Specification:
1. No. of cells – 110
2. Manufacture’s cell design – 10 SRG
3. Capacity at 10-hour rate discharge – 450 Amp/hour
4. Quantity of acid required per cell for the first cell filling – 1.18 at temperature of 20
38
5. Recommended specific gravity of electrolyte in fully charged condition – 1.210 +/- .
005 at 25 temperatures.
6. Charging equipment is required for
a) Initial charging
b) For quick charging after batteries discharge
5.1.7 Air Conditioning Plant
This plant is held for air conditioning the control room, class rooms, etc. an ideal
air conditioning system should maintain correct temperature, humidity, air party, air
movement and noise level.
In the 132-kV G.S.S. the load is about 40 tones. So that central station air
condition system is used. The area where all times there are no requirements of the
system FCU is used. When the switch is on the system is on for that place and vice-versa.
5.2 Annunciator
In a control room, the Annunciator is must. It consists of a sounding alarm and an
indicator, which indicates the nature of fault and the zone in which the fault occurs. The
alarm keeps ringing until the Annunciator is not accepted. The Annunciator is of two
sections. The first one is minor fault in which there is a buzzer sounding and indicates
come on the panel for the nature of fault. Fault such as the batteries charger is out of
order, low oil lines in transformer cooling system of transformer is out of order etc. are
the minor faults & are just warned the Annunciator to the authority concerned.
39
40