FORMULAS RELATED TO POWER PLANT PERFORMANCE INDICES:

(Actual operating hours + Restricted S/D hours)*100


AVAILABILITY FACTOR (%) = 24

(Actual generation in a day in MU )X 100


LOADING FACTOR (%) = (Actual operating hours X 0.125)

( Actual generation in a day in MU) X 100


PLANT LOAD FACTOR (%) = (24 X 0.125)

( Actual operating hours) *100


GENERATOR ON LINE (%) = 24

(Availability factor - PLF) * 100


PARTIAL LOADING (%) = Availability factor

Actual power consumption in MWh* 100


AUXILIARY POWER CONSUMPTION (%) = Actual generation in MWh

( Actual oil consumption in KL)*100


SPECIFIC OIL CONSUMPTION (ml/kWh) = Actual generation in MU

Actual lignite consumption in MT x 100


SPECIFIC LIGNITE CONSUMPTION (kg/kWh) = Actual generation in MWh

(Actual SG makeup consumption in MT X act Running hours)


SG MAKEUP CONSUMPTION (MT) = 24

SG makeup consumption in MT x 100


SG MAKEUP CONSUMPTION (%MCR) = (Actual running hours X 390)

Net export inc. colony & mines in MU


COMMERCIAL AVAILABILITY IN MU = .9

Dump power in MWh - Deemed non generation in MWh + Deemed generation in MU


9000 90

(Commercial availability in MU) * 100


COMMERCIAL AVAILABILITY (%) = 6.000 X No. Of days

Deemed generation in MWh


GENERATION LOSS GRID/LIGNITE (MU) = 900

(Generation loss grid/lignite in MU) * 100


PLF LOSS GRID/LIGNITE (%) = (24 X 0.125)

DEEMED GENERATION IN MU = Generation loss grid/lignite in MU + Actual generation in MU