Wipro Project (PH-VI ) Hinjawadi, Pune

Daily Progress Report


Date: 2-Jul-08

SDB-IV 1-Jul-08
S Up to
Cleared by
r.N Items Unit Total Qty
TCE Prog Achmt
o.
1 Excavation Nos 95 95 95 95 ###
2 PCC Nos 95 95 95 95
3 Footing /Pedestal Nos 95 95 95 95
4 L.G.F.Stem Columns Nos 87 87 87
5 LGF Stem Column (Grid 1 To 5) Nos 32 32 32
6 L G.F.Superstructure Column Nos 91 91 91
7 Ground Floor Column Nos 122 122 87
8 1st Floor Column Nos 122 122 77
9 Plinth Beam ( L G F) Rmt 1050 1050 1050
10 Plinth Beam ( G F1 To 6 ) Rmt 320 320 45
11 R. Wall Rmt 65 65 65
12 L.G.F.Grade Slab Sqm2 3400 3400 2500
13 Lift Wall / Shear Wall Rmt 209 209 209
SDB-V
S Up to 1-Jul-08
Cleared by
r.N Items Unit Total Qty Remark
TCE Prog Achmt
o.
1 Excavation Nos 97 97 50+12 IP
2 PCC Nos 97 57 50
3 Footing /Pedestal Nos 97 52 47
4 Stem Columns Nos 126 45 14
5 Plinth Beam Rmt 1130
6 G.F.Stem Column Nos
7 L.G.F.Stem Column Nos

MUB
S Up to 1-Jul-08
Cleared by
r.N Items Unit Total Qty Remark
TCE Prog Achmt
o.
1 Excavation Nos 47 47 12
2 PCC Nos 47 47 12
3 Footing /Pedestal Nos 47 47 5
4 Stem Columns Nos 77 77 8

Concrete (M3) Prog for May -08 3410 ###


Achived up to 1-Jul-08 25.0
Balance days 28
Target / day (M3) 121

41.07

D/PH-V/ASJ/3804317.xls DPR
32 Column Grid 1 To 5 SDB - 4

D/PH-V/ASJ/3804317.xls DPR
7/30/2008

D/PH-V/ASJ/3804317.xls DPR
D/PH-V/ASJ/3804317.xls DPR
Wipro Project (PH-V) Hinjawadi, Pune
Daily Progress Report

SDB-IV (July)
S 01.07.08 02.07.08 03.07.08 04.07.08 05.07.08 06.07.08 07.07.08 08.07.08 09.07.08
Total Target
r.N Items Unit Total
Days /Day
o. P A P A P A P A P A P A P A P A P A

1 Excavation Nos 95

2 PCC Nos 95 `

3 Footing /Pedestal Nos 95

4 LGFStem Columns Nos 87

5 G.F.Stem-Column(Grid1 to5) Nos 32

6 L.G.F. Superstructure Column Nos 91

7 Ground Floor Column Nos 87

8 1 st Floor Column Nos 87

9 Plinth Beams( LGF ) Rmt 1050

10 Plinth Beams( G F ) Rmt 164

11 R. Wall Rmt 65

12 LG F - Gread Slab Sqm2 3400

13 Lift Wall / Shear wall Rmt 209

SDB-V
S 01.07.08 02.07.08 03.07.08 04.07.08 05.07.08 06.07.08 07.07.08 08.07.08 09.07.08
Total Target
r.N Items Unit Total
Days /Day
o.
P A P A P A P A P A P A P A P A P A

1 Excavation Nos 98

2 PCC Nos 98 `

3 Footing /Pedestal Nos 98

4 Stem Columns Nos 126

5 Plinth Beams Rmt

mub
S 01.07.08 02.07.08 03.07.08 04.07.08 05.07.08 06.07.08 07.07.08 08.07.08 09.07.08
Total Target
r.N Items Unit Total
Days /Day
o.
P A P A P A P A P A P A P A P A P A

1 Excavation Nos 47

2 PCC Nos 47 `

3 Footing /Pedestal Nos 47

4 Stem Column Nos 69

D/PH-V/ASJ/3804317.xls 123
……………………………
Target/da
Concrete (M3) Prog for Aug -07 3000 Achvd up to 1486 y (M3)

D/PH-V/ASJ/3804317.xls 123