COMMISSIONING DOCUMENT
1. Refer Installation Guide (PDF File) for Installation. Snapshot of
Node B with Cabling shown below .
HARDWARE INSTALLATION
RF and Power Cabling
PCM and Digital Cabling
DDF INSTALLATION
Pair/
Shield Function
PCM 1 Receive 1
PCM 2 Receive 2
PCM 3 Receive 3
PCM 4 Receive 4
PCM 5 Receive 5
PCM 6 Receive 6
PCM 7 Receive 7
PCM 8 Receive 8
PCM 9 Transmit 1
PCM 10 Transmit 2
PCM 11 Transmit 3
PCM 12 Transmit 4
PCM 13 Transmit 5
PCM 14 Transmit 6
PCM 15 Transmit 7
PCM 16 Transmit 8
2. Before Power ON of Node B , Ensure the following :-
d. Java6 update5
f. IP sheet
Put your name and Default Path where you want to save all
Commissioning Reports .
Username: nodeb
Password: nodeblnx
IP Modification:
Reference:
OMC-B IP address =
10.136.130.164
OMC-B VP identifier = 1
OMC-B VC identifier = 32
Subnetwork Mask =
255.255.255.0
BTS Port = 6301
IMA Modification:
Select IMA
Success Message
Reconnect to BTS
END OF COMMISSIONING