Change Request Implementation Plan - Planned

Instructions:
Define Step-by-Step instructions to perform this change.
Include GO/No GO decision points throughout your process if applicable

Step-by-Step tasks to perform


1.) Notify to Service desk
2.) Restart SP1 Production Cluster
Reason: To check the package control script

3.) confirmation from the requestor


Task Owner Task Date Task Time

Himadri Bhattacharya 30-11-2008 1:00:00 AM to 02:00 AM

Himadri Bhattacharya 30-11-2008 1:00:00 AM to 02:00 AM


Changes to Implementation Plan

Instructions:
Record only changes to planned implementation here

Step-by-Step tasks to perform Task Owner Task Date


Make new changes for 4 filesystems in the package control script
1.) Log into ITDSP1 server Enterprise team 30-11-2008
2.) Halting the CI package Enterprise team 30-11-2008
3.)Halting the DB package Enterprise team 30-11-2008
4.)start the DB package on DB node Enterprise team 30-11-2008
5.)start the CI package on CI node Enterprise team 30-11-2008
6) check all the mountpoints got mounted Enterprise team 30-11-2008
7)Halting the CI package Enterprise team 30-11-2008
8)Halting the DB package Enterprise team 30-11-2008
9)start the DB package on ci node Enterprise team 30-11-2008
10)start the CI package on DB node Enterprise team 30-11-2008
11) check all the mountpoints got mounted Enterprise team 30-11-2008
12)Halting the CI package Enterprise team 30-11-2008
13)Halting the DB package Enterprise team 30-11-2008
9)start the DB package on ci node Enterprise team 30-11-2008
10)start the CI package on DB node Enterprise team 30-11-2008
7.)Get the confirmation from ECC basis Team for running of application ECC basis Team 30-11-2008
8.) Notify all clear message to Service desk Enterprise team 30-11-2008
Task Time

5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
5 Min
10 Min
5 Min