Sie sind auf Seite 1von 1

Logo, format space

Customer : P.O.No :
Project : Ref :
Equipment : Tag No :

INSPECTION AND TEST PLAN


Requirement
ID ACTIVITY MFR TPI Client
1 Review the records for materials H R R
2 Review stage inspection records H R R
3 Hydrotest Evaparator & condenser H W R
4 Dimensional Check H R R
5 Witness the Functional test of the unit H W W
6 Review all the records before shipment H R R
7 Review the shipping crate H R R
8
9
10
11
12
H - HOLD POINT Activity will not pass until waived by inspector
W - Witness Point, Inspector will be notified,but will not be held.
R - Review Inspector will be notified of the activity,to review documentation.work to
Proceed. TPI : Third Party Inspection
Applicable Specifications
Spec.No.
ASME B&PV code sections I &VIII and ISO 9001