ID WBS Task Name Duration Mar '11 Apr '11 May '11 Jun '11 Jul '11

12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9
1 ASFHos.1 Asfour Hospital Project 318 days
2 ASFHos.1.1 Contractual 318 days
3 ASFHos.1.1.01 Key Dates & Milestones 318 days
4 ASFHos.1.1.01.04 Contract Signature 0 days 3/1
5 ASFHos.1.1.01.05 Receiving Downpayment 0 days 3/17
6 ASFHos.1.1.01.06 End of Project 0 days
7 ASFHos.1.1.02 Mobilization 318 days
8 ASFHos.1.1.02.04 Site Handover 0 days 3/1
9 ASFHos.1.1.02.05 Mobilization 30 days
10 ASFHos.1.1.02.06 Demobilization 30 days
11 ASFHos.1.2 Procurement 188 days
12 ASFHos.1.2.01 Materials Submittal 34 days
13 ASFHos.1.2.01.1 Submital of RACEWAY AND BOXES 14 days
14 ASFHos.1.2.01.2 Submital of LV & MV Cables 14 days
15 ASFHos.1.2.01.3 Submital of CABLE TRAYS 14 days
16 ASFHos.1.2.01.4 Submital of WIRING DEVICES 14 days
17 ASFHos.1.2.01.5 Submital of EARTHING & LIGHTNING SYSTEM14 days
18 ASFHos.1.2.01.6 Submital of PANEL BOARDS 14 days
19 ASFHos.1.2.01.7 Submital of MCC 14 days
20 ASFHos.1.2.01.8 Submital of INTERIOR LIGHTING FIXTURES 14 days
21 ASFHos.1.2.01.9 Submital of UPS 14 days
22 ASFHos.1.2.01.10 Submital of CBS 14 days
23 ASFHos.1.2.01.11 Submital of FIRE ALARM SYSTEM 14 days
24 ASFHos.1.2.01.12 Submital of Voice / Data System 14 days
25 ASFHos.1.2.01.13 Submital of CCTV 14 days
26 ASFHos.1.2.01.14 Submital of DIESEL-GENERATOR SETS 14 days
27 ASFHos.1.2.01.15 Submital of TELEPHONE EXCHANGE 14 days
28 ASFHos.1.2.01.16 Submital of MASTER CLOCK SYSTEM 14 days
29 ASFHos.1.2.01.17 Submital of PUBLIC ADDRESS 14 days
30 ASFHos.1.2.01.18 Submital of Power Transformers 14 days
31
32
33 ASFHos.1.2.02 Materials Approval 34 days
34 ASFHos.1.2.02.05 Approval of RACEWAY AND BOXES 14 days
35 ASFHos.1.2.02.06 Approval of LV & MV Cables 14 days
36 ASFHos.1.2.02.07 Approval of CABLE TRAYS 14 days
37 ASFHos.1.2.02.08 Approval of WIRING DEVICES 14 days
38 ASFHos.1.2.02.09 Approval of EARTHING & LIGHTNING SYSTEM14 days
39 ASFHos.1.2.02.10 Approval of PANEL BOARDS 14 days
40 ASFHos.1.2.02.11 Approval of MCC 14 days
41 ASFHos.1.2.02.12 Approval of INTERIOR LIGHTING FIXTURES 14 days
42 ASFHos.1.2.02.13 Approval of UPS 14 days
43 ASFHos.1.2.02.14 Approval of CBS 14 days
44 ASFHos.1.2.02.15 Approval of FIRE ALARM SYSTEM 14 days
45 ASFHos.1.2.02.16 Approval of Voice / Data System 14 days
46 ASFHos.1.2.02.17 Approval of CCTV 14 days
47 ASFHos.1.2.02.18 Approval of DIESEL-GENERATOR SETS 14 days
48 ASFHos.1.2.02.19 Approval of TELEPHONE EXCHANGE 14 days

Task Summary Rolled Up Progress Project Summary


Project: AsforVer2
Progress Rolled Up Task Split Group By Summary
Date: Tue 2/22/11
Milestone Rolled Up Milestone External Tasks Deadline

Page 1
ID WBS Task Name Duration Mar '11 Apr '11 May '11 Jun '11 Jul '11
12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9
49 ASFHos.1.2.02.20 Approval of MASTER CLOCK SYSTEM 14 days
50 ASFHos.1.2.02.21 Approval of PUBLIC ADDRESS 14 days
51 ASFHos.1.2.02.22 Approval of Power Transformers 14 days
52
53
54
55 ASFHos.1.2.03 Delivery on site 160 days
56 ASFHos.1.2.03.1 Delivery of RACEWAY AND BOXES 8 wks
57 ASFHos.1.2.03.2 Delivery of LV & MV Cables 10 wks
58 ASFHos.1.2.03.3 Delivery of CABLE TRAYS 3 mons
59 ASFHos.1.2.03.4 Delivery of WIRING DEVICES 7 wks
60 ASFHos.1.2.03.5 Delivery of EARTHING & LIGHTNING SYSTEM 10 wks
61 ASFHos.1.2.03.6 Delivery of PANEL BOARDS 4 mons
62 ASFHos.1.2.03.7 Delivery of MCC 4 mons
63 ASFHos.1.2.03.8 Delivery of INTERIOR LIGHTING FIXTURES 30 days
64 ASFHos.1.2.03.9 Delivery of UPS 12 wks
65 ASFHos.1.2.03.10 Delivery of CBS 10 wks
66 ASFHos.1.2.03.11 Delivery of FIRE ALARM SYSTEM 10 wks
67 ASFHos.1.2.03.12 Delivery of Voice / Data System 10 wks
68 ASFHos.1.2.03.13 Delivery of CCTV 8 wks
69 ASFHos.1.2.03.14 Delivery of DIESEL-GENERATOR SETS 6 mons
70 ASFHos.1.2.03.15 Delivery of TELEPHONE EXCHANGE 90 days
71 ASFHos.1.2.03.16 Delivery of MASTER CLOCK SYSTEM 3 mons
72 ASFHos.1.2.03.17 Delivery of PUBLIC ADDRESS 10 wks
73 ASFHos.1.2.03.18 Delivery of Power Transformers 7 mons
74
75
76 ASFHos.1.3 Construction 243 days
77 ASFHos.1.3.01 Milestones 15 days
78 ASFHos.1.3.01.04 Receiving Work Insruction from Main Contractor 0 days 3/1
79 ASFHos.1.3.01.05 Receiving Approved Shop DWGs 0 days 3/17
80 ASFHos.1.3.02 Main Building 163 days
81 ASFHos.1.3.02.1 RACEWAY AND BOXES FOR ELECTRICAL 30 days
82 ASFHos.1.3.02.2 EARTHING SYSTEM 20 days
83 ASFHos.1.3.02.3 PANEL BOARDS 35 days
84 ASFHos.1.3.02.4 MCC 30 days
85 ASFHos.1.3.02.5 LIGHTING FIXTURES 30 days
86 ASFHos.1.3.02.6 UPS 30 days
87 ASFHos.1.3.02.7 CENTRAL BATTERY SYSTEM 30 days
88 ASFHos.1.3.02.8 Lightning Protection System 30 days
89 ASFHos.1.3.02.9 FIRE ALARM SYSTEM 30 days
90 ASFHos.1.3.02.10 NURSE CALL SYSTEM 30 days
91 ASFHos.1.3.02.11 MASTER CLOCK SYSTEM 30 days
92 ASFHos.1.3.02.12 Voice and Data System 30 days
93 ASFHos.1.3.02.13 TELEPHONE EXCHANGE 30 days
94 ASFHos.1.3.02.14 INTERCOM SYSTEM 30 days
95 ASFHos.1.3.02.15 PUBLIC ADDRESS 30 days
96 ASFHos.1.3.02.16 MASTER ANTENNA TV SYSTEM 30 days

Task Summary Rolled Up Progress Project Summary


Project: AsforVer2
Progress Rolled Up Task Split Group By Summary
Date: Tue 2/22/11
Milestone Rolled Up Milestone External Tasks Deadline

Page 2
ID WBS Task Name Duration Mar '11 Apr '11 May '11 Jun '11 Jul '11
12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9
97 ASFHos.1.3.02.17 CCTV 30 days
98 ASFHos.1.3.02.21 MATV 30 days
99 ASFHos.1.3.02.22 ACCESS CONTROL SYSTEM 15 days
100 ASFHos.1.3.10 Service Building 213 days
101 ASFHos.1.3.10.135 RACEWAY AND BOXES FOR ELECTRICAL 30 days
102 ASFHos.1.3.10.136 EARTHING SYSTEM 30 days
103 ASFHos.1.3.10.137 PANEL BOARDS 30 days
104 ASFHos.1.3.10.138 MCC 30 days
105 ASFHos.1.3.10.139 LIGHTING FIXTURES 30 days
106 ASFHos.1.3.10.140 UPS 30 days
107 ASFHos.1.3.10.141 CENTRAL BATTERY SYSTEM 30 days
108 ASFHos.1.3.10.142 Lightning Protection System 30 days
109 ASFHos.1.3.10.143 FIRE ALARM SYSTEM 30 days
110 ASFHos.1.3.10.144 Voice and Data System 30 days
111 ASFHos.1.3.10.145 PUBLIC ADDRESS: 30 days
112 ASFHos.1.3.10.146 CCTV 30 days
113 ASFHos.1.3.10.147 Power Transformers 30 days
114 ASFHos.1.3.10.148 MV SWITCHGEAR 30 days
115 ASFHos.1.3.10.149 DIESEL-GENERATOR SETS 30 days
116 ASFHos.1.3.10.150 Final Touchup 15 days
117 ASFHos.1.4 Closing 95 days
118 ASFHos.1.4.01 Testing and Comissioning 80 days
119 ASFHos.1.4.01.03 Tesing for Main Building 30 days
120 ASFHos.1.4.01.04 Tesing for Service Building 30 days
121 ASFHos.1.4.02 Handing Over 65 days
122 ASFHos.1.4.02.1 Handover or Main Building 15 days
123 ASFHos.1.4.02.2 Handover for Service Building 15 days

Task Summary Rolled Up Progress Project Summary


Project: AsforVer2
Progress Rolled Up Task Split Group By Summary
Date: Tue 2/22/11
Milestone Rolled Up Milestone External Tasks Deadline