Beruflich Dokumente
Kultur Dokumente
Kolhapur
AN
Inplant Training
AT
Kolhapur Zilla Sahakari Dudh Utpadak
Sangh L.T.D. Kolhapur.
Submitted By
ACKNOWLEDGEMENT
Kolhapur Zilla Sahakari Dudh Utpadak
Sangh Ltd.,
Kolhapur is the best dairy industry . It provides greate
opportunity to learn more about Milk processing and their
products.
We were very fortunate to get support from number
of people to whom we are very thankful .
We are very thankful to Mr. Mahadik (Chairman)
for giving us great opportunity. We are also very thankful to
Mr. R. C. Shah (Dy General Manager) , Mr. Chaudhari , Mr.
Tathe for their valuable support.
We express our sincere thanks to Mr. Shahaji
Magdum, Mr.Bharat Lad , Mr. Khatavkar , Mr. A. A. Amte , Mr.
A . Magdum,
Mr. Suraj Ingavale , Mr. Shankar Patil, Mr. Uday Patil, Mr. A. P.
Patil, Mr. J. D. Patil, Mr. Narinkar for their helpful guidance in
training period.
I am grateful to our Principal Mr. P.T. Patil and
Prof. A.S. Dhane for his able guidance in systematic and
successful completion of training.
Finaly we are thankful to all dairy workers for
giving their moral support during our inplant training.
Content
1) Introduction
2) Product line
5) Prepack Section
6) Butter Section
7) Ghee Section
8) Lassi Section
9) Dahi Section
INTRODUCTION
Shri arjun narake; shri anandrao patil & shri sarnaik established GOKUL
DIARY in 1963.the current turnover of this company is approximately_________, the
plant of Gokul Dairy is at GOKUL SHIRGAON ,MIDC.
The dairy was commissioned towads the ends of 1985. MCANWHILC; with
the efforts of the NDDB , the Govt. milk scheme in kolhapur was handed over to the
Kolhapur Zilla Dudh Sangh in mid 1985. with commissioning of a new dairy at Gokul
Shirgaon . the Avg milk procrument was 114836 PD with 676.villages level Societes
affiliated to the Dudh sangh.
2) Fulfill the growing needs for milk & milk products of the consumers in the
maharashtra & else where.
5) inparting training for developing human resourses at rural level for effective
leadership , management skills & improvement of services to rural milk producers.
AREAS OF OPERATION:-
However 41 villages from Hatkanagle & panhakla talukas are affiliated to Gokul milk
producers union.
PRODUCT LINE:-
1.MILK::-
Standardized Milk
Cow Milk
Toned milk
Double tonned milk.
2. Cooking Butter
3. Table Butter
4. Paneer
5. Dahi.
6. Lassi
7. Ghee
8. Milk Powder
9. Shrikhand
10 Amrkhand
ADDRESS OF DAIRY:- “Gokul plant” , Plot no. B-1, M.I.D.C , BT No.2, Gokul
Shrigaon ,Tal:- Karvier, Dist:- Kolhapur Pin:- 416234
YEAR OF ESTABLISHMENT:-1963
DISTANCE FROM CITY:- Gokul dairy is 13 Km. Away from Kolhapur city.
Introduction :
RMRD at Gokul dairy is well equipped with the advanced equipment like
computers and pneumatic sampler, milk testing machinates, electronic weighing system.
There is spacious area in front of the dock to park the vehicles. The dock having two ran
reception lines, so has two units of each equipment like can opener, weighing tank Dump
Tank, can washer, and crate washer.
The process on RMRD starts from unloading the tempos. The cans are conveyed
on Hook chain conveyer. On the way to tilting point auto lid opener opens can lids and
organoleptic tests are conducted. If anything wrong with can then it is detected and such
can is taken out from conveyor. Then these cans are unloaded / emptied in dump tank
manually at tilting point. The cow milk and buffalo milk is collected separately on
RMRD. The suspected / sour milk is not allowed to mix with good / fresh milk. It is
diverted from that line and conveyed to sour milk dump tank. A lab person or chemist
analyses the sample for platform tests such as Fat,SNF,CLR, Acidity, EKOMILK,
(machine) , etc. machine tests are carried out in separate laboratory chamber. Here are
two computer chambers to record the quantitative and qualitative parameters of incoming
milk from the societies. These parameters are fat, CLR and quantity of milk. These
parameters are used to calculate the price of milk per liter.
Sampling is done automatically by pneumatic sampler. Sample from each lot
( Tilting tank) is taken in bottles and carried to the milk testing chamber on a sample
bottle conveyor.
The cans, which are not properly cleaned, are taken to can scrubber and again
loaded to can washer for recleaning.
Tanker Reception :
The milk from the chilling centers located at Boravade (Bidri), Lingnur
(Gadhinglaj), Tavarewadi (Chandgad), Gogave ( Shahuwadi) etc. is transported by road
tankers. These tankers are on hire basis as and when required subjected to procurement of
milk.
As soon as the tanker arrives at the dock containing processed or chilled milk it is
being tested for organoleptic tests and lab tests. After analyzing its quality, it is accepted
for further processing and production.
The reception starts from 8.00 a.m. during morning and 7.00 p.m. at evening and
continues till all the expected milk is received. The milk handling capacity of Gokul is
around 6 lakh lit / day
Can conveyor
Oraganoleptic Testing
(if doubt then COB testing)
Tilting of Cans
Sour milk
Weighing
Sampling
(Testing CLR and Fat)
Processing Dump tank Reception of milk
from tankers
Empty can
Milk Draining
Dispatch
2. Can Conveyor :
Type = 1. Chain conveyor ( In can washer)
3.Can Opener :
Working = Power driven
1. Principle of operation = Vibration
4.Organoleptic Testing :
At first, milk is well mixed with the help of plunger and following tests are
carried out by experienced persons.
a) Color b) Smell
c) Taste d) Appearance e) Temperature by touch to cans.
5.Tilting of cans :
Mode of operation = Manual
CLEANING OF CANS:-
The empty cans are washed in a straight through can washer daily. Once
in a week the cans should be washed manually with schedule programme.
Can Washer Operating Parameters:-
1. Steam pressure 3Kg/.cm2
2. Pre-rinse temp min. 450C
3. Detergent temp min 700C
4. Final rinse temp 80-850C
5. Hot air temp 90-1000C
6. Washing speed 600 can/hr
TANKER CLEANING:-
After every Emptying & before every filling.
-Pre-rinse with water.
-Manul cleaning with hot water, detergent & pads.
-Final rinse with hot water.
-Sterilisation with chlorine150-220 ppm i.e. 150 ml in 40 lits of water
Solution.
- Man hole cover, gaskets, air vents : Brushing with liquid detergent,
flushing
- with hot water, & sterilization with chlorine.
-Valve box steam union : Open valve body, union & clean them with
detergent & hot water.
PROCESSING SECTION
Introduction :
Processing section is the heart of Dairy industry. The milk received from the
RMRD cannot be instantly processed. So it is first chilled and stored in silo tanks.
Consequently processing is carried out in this section are chilling, storage, pasteurization,
cream separation, filtration, clarification , homogenization, standardization,
reconstitution .
Milk Process:
The eqipments in this section are Chillers, Silos, Tanks, HTST, Pasteurizers,
Duplex filters, Clarifier cum Separators.
Chilling :
All the milk received through RMRD is chilled to 5 – 70 C through the plate heat
exchanger type chillers. Chilled water at 1-1.50C is used as cooling agent. Chilled water
pipes are insulated by thermocol. Total 3 chillers of PHE type are in working in the
process section.
Sr Parameter Specification
No
1. Flow rate chiller no 1 18,000 litres /hr.min
2. Flow rate chiller no 2 18,000 litres/ hr. min
3. Flow rate chiller no 3 27,000 litres/hr min
Storage :
The chilled milk is stored in silos at 50 C and then supplied for further processing
steps.
Pasteurization :
In this section, HTST Pasteurizers ( 3 for milk and 2 for cream ) are
working here. Out of 3 milk Pasteurizers , 2 have the holding tubes . Milk is pasteurized
at a temperature of 78+/-20 C for 15 Sec. The cream pasteurization is carried out at 90 –
980 C for 15 – 16 seconds. Pasteurizers are composed or four regeneration sections in
which the temperature of milk is increased in steps as 350C, 470C , 650C & 80 hence milk
can be sent to separation, homogenization between the regeneration sections. Pasteurizers
are connected to Duplex filter, Westfalia separator and Homogenizer. Flow Diversion
Valve is attached after the holding section. After pasteurization product (Milk or cream)
is instantly cooled to 50 C or below and stored in storage tanks.
Duplex Filters :
The milk from regeneration 4 section of pasteurizer is taken to duplex
filters, which is a closed cylindrical body. The milk enters from top and passes out from
bottom, which is connected, to Westfalia separator. This body consists of two layers of
metallic filters.
Westfalia Separator :
In this type of separator milk is clarified as well separated into cream
and skim milk. The slime is removed manually during cleaning operation. The cream is
pumped to cream pasteurizer while and skim milk returns to pasteurizer .
Homogenizer :
A two stage homogenizer is installed in processing section, which is used for
homogenizing whole milk and it is connected in between regeneration 1 and heating
section .
Milk Pasteurizer:-
Sr Parameter Specification
No.
1. Pasteurizer Temperature 78 ± 2ºc
2. Chilled Milk Temperature ≤04 ºc
≤06ºc (For recombined
milk)
3. Chilled water inlet temperature 02ºc Max.
4. Hot water inlet Temperature 88ºc Max.
5. Flow rate
For past. no 1&2 >8500 LPH
For past. no 3 >14,000 LPH
For past. no 4&5 >18,000 LPH
Cream Pasteurizer:-
Sr Parameter Specification
no.
1. Pasteurizer temperature 92 ± 2ºc
2. Chilled Cream temperature 07 ± 2ºc
3. Flow rate
For CP 01 3,500 LPH
For CP 02 5,500 LPH
Seperators (Westfalia):-
Sr Parameter Specification
No.
1. Air Pressure Min 6 kg/cm2
2. Soft water pressure Min 3 bar
Homoginizer:-
Sr Parameters Specification
no.
1. Pressure 2nd stage Min 500 psi+ 100 psi
2. Pressure 1st Stage
For cow milk Min 1,500 psi + 100 psi
For Recombined milk Min 2,500 psi + 100 psi
Deep Chiller:-
Parameters specifications
Temperature of chilled milk ≤4ºC
Flow Rate 20,000 litres/hrs.max
Glycol Inlet Temperature -5ºC to 0ºC max
Or
Chilled water temperature ≤1.5ºC
Store in silos
Processing
Cream Seperator
Storage tank
Flow Chart for Cream Pasteurization :
Cream from cream separator
Cream pasteurizer.
Balance tank
Feed pump.
MILK STANDARDIZATION
Standardization is an important procedure for the adjustment of fat and SNF as per the
specified standard. The standardization is done by Skim milk or Reconstituted milk for
buffalo milk while buffalo milk for cow milk. The tanks are provided agitators inside for
through mixing continuously. There are different ratios for standardized milk and whole
milk.
Hopper
Addition of water
Mixing tank
Reconstituted Milk
BULK MILK DISPATCH THROUGH TANKER :
Daily near about 1,25,000 lit. processed milk is sent to Washi for packaging.
Before the milk is dispatched through tankers, the tankers, the tankers are cleaned
properly as per schedule given previously in the RMRD section. The Pasteurized Whole
milk and Standardized milk is chilled at 1.5 – 2 0 C and filled in tankers and after filling ,
the sample is given for analysis. After satisfactory analysis report, the tanker are
permitted for transportation to Washi for packaging. This is carried out with Glycol
chiller. The cooling medium used in this chilling is Glycol.
PRE-PACK SECTION
Introduction :
This section is very important as it gives the protection to the product and
improve its attractiveness i.e. contributing for enhancing the acceptance.
This section is located just behind the RMRD. It is in between RMRD & process
section. The washed creates are received in prepack, section for placing the pouch of
milk and then shifted to cold storage. In this section, there are five fillpack machines.
This section is laterally connected with cold storage.
The milk is pouched in various capacities with different types of milk. The milk
pouched are Buffalo whole milk, Cow whole milk, Tonned milk. Lassi is also packed in
this section at 40 C. the pouches are filled in crates and stored in cold storage at 10 C in
stacks. Stacks means keeping the crates one over other. 10 crates form a stack. Pouches
are checked for leakage while stacking in cold storage. There are two cold storage for
storing market / pouch milk.
Filling cylinder.
Milk pouch.
Filling in crates.
Crate coyer.
Dispatch.
Details of Packing Machine :
In this section, five packaging machines are working. Packaging material is
polythene film. Roll is fixed on the backside of the machine and it is carried out to the
top of front side mechanically by the nib rollers. It is sterilized by UV light. Vertical
edges of material are sealed to each other by vertical Teflon coated electrode rod at a
temperature of 600 C. then the material comes down and sealed by horizontal electrode
rod at 900 C. The horizontal rod seals first lower end of pouch horizontally and after
filling adjusted amount of milk with the help of pneumatically operated pistons having
adjustable stroke volume, the pouch slips down a specified distance and then its upper
edge is sealed. Horizontal sealing of upper side of one pouch and lower side of next
pouch & horizontally cutting of filled pouch is carried out in single stroke of horizontal
sealer. Packaging machine and quantity of milk to be packed without leakage
.
Parameters of Packaging Machines :
No. of Units - 05
01 - Power saver (Nichrome )
02 - Nichrome
The milk, which is collected from leaked pouches is sent for reprocessing. Average milk
loss during adjustment & due to leakage is around 6 liters per hour. Air is used as
lubricant in pulling cylinder.
On line 8 kg/cm2
Machine 6 kg/cm2
4. Cooling Water Running
5. Weight & Length Checking From each working head.random checking of
Frequency 20 pouches at every hrAvg. Wt shall confirm
to the specification
6. Weigh Balance To be checked with dead wt. at the start of
each shift
7. Film loss norm 1.5% max. During packing
8. Drop Test 16 samples of filled pouches shall be taken
random from filling line.the sample bags
drawn from machine shall be dropped from
the height of 1.2 meter on a flat, smooth ,
hard surface in 4 ways i.e 1)at vertical seam.
2)at opposite to vertical seam. 3) & 4) at
vertical edges.The samples have deamed to
have the test of 75% of the sample with
stood all the above 4 drops .
Storage of film:-
1) At dry cool & dust free area
2) Keep wrapped until taken for use.
3) Stacking on wooden pallets/ racks
BUTTER SECTION
Introduction-
In Gokul dairy White Butter as well as Table Butter are manufactured in the
Butter –Section by using cream (40-45% fat) of Buffalo milk or Cow milk or
combination their of. Daily near about Cream is converted into Butter.
White butter :
White butter is produced for the conversion of surplus fat, it is not sold in the
market and used in the production of Ghee. Generally the white butter is prepared by
using continuous butter making machine. But sometimes when bulk of the cream is less,
it may be prepared in tabletop churn.
Cold storage
(-10 to -150 C.)
CBMM Operation:-
3.Working cylinder :
It consist of two working blades with chilled water jacket cylinder. In this part of
CBMM, continuous mass of butter is formed due to action of working blades.
Operating parameters:-
Parametrs Specification
Temperature 9 to 13 ºC
Ageing Time 4 hrs. min
Agitators In working hrs , no oil leakage under blades ,
Sufficient agitation to break froth
System Followed FIFO
Cleaning of CBMM :
The cleaning of CBMM is done manually by dismantling. All parts are scrubbed
with brush using detergent and caustic, then are washed with water and reassembled.
Table Butter :
The table butter is sold under brand name GOKUL BUTTER. The
production is done as per demand.
Loading of churn
Testing sample
Packaging
Addition of color –
The annatto color is used to add into the cream,. The quality of
annatto to be added depends upon the fat % of cream and bulk of cream taken in the
churn. As annatto is a fat soluble pigment which does not lost into buttermilk hence
almost all the added annatto comes into butter. Only prerequisite is that the butter should
contain 0.1 % annatto. Therefore annatto to be added can be determined easily as follows
:
Addition of Salt:-
Addition of salt should be up to 2.5% which is added on the total kg fat in cream
and the %fat in butter. Salt is added is of the High grade TATA SALT. Quantity should
be calculated as follows,
Quantity of salt added = (Total kg fat) × (% salt added )
% fat in butter
Packaging of butter –
The butter packaging room is adjacent to production room. Its temperature is
maintained at 4 to 50 C. There are two butter packaging machines in the plant, one for
500gm pack and one for 100gm pack. The machines are completely mechanical. In the
machine hardened butter blocks are placed which are forced forward by screw conveyor
type arrangement through a channel and a piece of it is taken in a groove. It is removed
and wrapped by butter paper by horizontal and vertical rods. The wrapped piece is placed
into outer box manually, it is weight tested and stamped. The boxes are then placed in
cartoons and sent to storage at temperature –18 to –210 C.
Cleaning of churn :-
The churn is filled with hot water and churn is rotated for some time. The water is
drained out and caustic solution is added and again rotated for some time. It is again
washed with hot water.
GHEE SECTION
Introduction :
Gokul Dairy receives bulk amount milk, which is separated in to skim milk and
cream. This cream is used for Butter producing and Butter is used for Ghee manufacture.
The Ghee is produced by creamery butter method.
Melting
(70-80 0C steam pressure 0.5 kg/cm2)
Cooking
(105-109 0C steam pressure 1.5 kg/cm2)
Details of manufacture :
2). Cooking :-
Melted Butter is taken into Ghee boliling of vats. They are given steam in their
jacket at a pressure of 1.5kg/cm2. Ghee is boiled at 105 – 1090 C till nearly all the
moisture get evaporated and it is detected by dark brown color of Ghee residue.
3) Balance tank :
The prepared Ghee lot is taken to filter balance tanks which consists of
metallic sieve aligned with muslin cloth to extract the Ghee residue from Ghee.
4) Filtration :
5) Settling tank :-
The filtered Ghee is stored in settling tank for 4-5 hrs in order to settle down
the Ghee residue. Then Ghee residue is taken out and Ghee sample is sent to lab before
filling and packaging. If sample does not contain Ghee residue and satisfy prescribed
then it is allowed to packaging.
7) Storage:-
Ghee contains 0.5 % (max.) moisture, so it has good shelf life even at room
temperature.
boxes .
LASSI SECTION
Introduction :
Here Lassi is manufactued out of standardized milk and not from the
buttermilk. Gokul Dairy has set its own standards for Lassi. It is being produced
seasonally, as it has tremendous demand in summer season.
Preheating (370 C)
Mixing
Homogenization
(1st stage =100 psi 2nd Stage = 50 psi
Chilling ( below 4º C)
Temporary Storage
Packing(200ml)
Storage (-180 C)
A) Curd setting:-
Parameter Specification
Incubation temperature 37 – 40 ºC
Incubation period 4 – 6 hr.
Inoculation of culture 1–2%
B) Batch pasteurization:-
Parameter Specification
Pasteurization temperature 78 + 2 ºC
Pasteurization time Min. 30 min
C) Homoginisation:-
Parameter Specification
Homogenization pressure 1st’ stage,100 psi 2nd’stage,50 psi
Homogenization temperature 60 – 65 ºC
F) Storage Film:-
1. At dry, Cool and dust free area.
2. Keep wrapped until taking for use.
DAHI SECTION
Introduction :
At Gokul Dairy, Dahi is prepared as per demand, in small batches. Buffalo
milk of fat 6.7 %-6.8% & SNF 9.1% is used for Dahi production. The SNF level is
increased upto 10.1% by adding reconstituted SMP about 1.5% of milk. Also protein
powder is mixed during reconstitution of SMP in the proportion of 1gm protein powder
for 10kg milk i.e. about 0.01% of milk. 30-40kg of Dahi is prepared in each batch.
Generally, two batches of Dahi are prepared per week. Dahi is packed in cups of 100gm
& 250 gm manually.
Standardisation of Milk
QC Check
Preparation & Pasteurisation & Homoginisation
Storage of batch
culture Storage & increase of temp. of milk
in batch pasteurizer
Transfer of milk
Addition of culture Storage of milk in inoculation tank. Storage of
foil & cup
Packing
SHRIKHAND SECTION
Introduction :-
It is semi soft , Sweetish sour ,Whole milk product prepared from
lactic fermented curd.Shrikhand is the most popular product of Gokul dairy. In last few
years many renowned dairy organizations have plunged into the Shrikhand production
but it have shown no effect on effect on the demand for GOKUL SHRIKHAND. This
can be clearly understood by following graph.
Process:-
IN shrikhand pasteurized cow or buffalo milk is inoculated at 37 ºC with
1.0% starter, & kept for setting curd. Time is adujest according to ambient temperature so
that the developed acidity of curd reaches to 0.7- 0.9 % (lactic). The curd is suspended in
muslin cloth until nearly all the whey drained off. The semi dry mass ( chakka) is then
kneaded with sugar 70 % of chakka mass imparts creamish yellow colour.
Chakka:-
Is a white to pale yellow semisolid product of good texture & uniform consistency
obtained by draining of the whey from dahi obtained by lactic fermentation of milk
which has been subjected to minimum heat treatment equivalent to that of pasteurization.
It shall have pleasant dahi like flavor . It shall not contain any ingradient forgien to milk.
It shall be free from moldness & free from sign of fat or water seepage or both. It shall be
smooth & not appeare dry. It shall not contain extraneous colour & flavor.
Manufacturing Parameters:-
Sr Parameter Specification
no.
1. Total solid % by weight Not less than 58
2. Milk fat(on dry basis) % by weight Not less than 8.5
3. Milk protein (on dry basis) % by weight Not less than 9.0
4. Titrable acidity% 1.4 Max.
5. Sugar(sucrose) % by weight Not more than 72.5
6. Total ash % by weight Not more than 0.9
Preheating(400C).
Incubation up to acidity 1 %.
Drainage of whey .
Wrapping in Lyner .
Packaging.
Lidding.
Cartooning.
Storage
PANEER SECTION
Paneer is manufactured from the buffalo milk testing less than 5% fat and 9%
SNF using citric acid as coagulation agent. Draining of whey, moulding, pressing and
packaging follows coagulation.
Whey draining(Coagulation)
Process steps:
Sr. Parameter Specification
no
1 Heating tempature in batch pasteurizer 80+2 c
2 Holding time in batch pasteurizer 10 minuets minimum
3 Coagulation temp 70 to 75 ºC
4 Holding time 10 minuets maximum
5 Pressing of paneer 10 to 20 minutes at air
pressure 4 to 6 kg per
centimeter square.
6 Chilled water temp for putting paneer block 10 ºC maximum(Salt
solution1% Max)
7. Time for putting paneer(blocks in chilled water) 2.5 t0 3 hr
Control point:-
Coagulation temperature.
Cutting of paneer:-
Use sanitized cutting knife.
POWDER SECTION
Introduction :
Both units are accompanied with evaporator assemblies. Both the evaporators are of
falling film type. Mainly SMP is manufactured in the dairy. But sometimes WMP and
Dairy Whitener are manufactured.
Skim milk
Preheating in condenser.
Preheating in calendria No 2
Preheating in calendria No 1.
Holding
Finisher
Mono pump
Air blower
Automizer
Hot filtered air
Hot air and powder particles
Rotary valve
Packging
Dry storage
Feed
Autimization
(rotary disc)
Drying of spray
(moisture evaporation)
Parameters Specification
Condensing Plant
Steam pressure mainline(kg/cm2) 14 – 15
Thermocompressor pressure(kg/cm2) 6–7
Temp. tubular heater 96 ± 2ºC
Temp. Vapour separator-1 71±2ºC
Temp. Vapour separator-2 60 ± 2ºC
Temp. Vapour separator-3
1. When steam jet ejector is in 41 ± 2 ºC
operation
2. When vaccume pump is in 46 ± 2ºC
operation
Vaccume in separator 3rd -1.0 kg/cm2
Cooling water inlet temperature 27 ± 3ºC
Cooling water outlet temp. 3.5 ± 3ºC
Baume reading 22.5 -23.5
Drying plant
Parameter Specification
Condensing plant
Steam pressure mainline(kg/cm2) 10- 14
Thermocompressor pressure(kg/cm2) 7–8
Direct steam injection milk heater temp 95 ± 4ºC
Temp. Vapour separator 1 65 ± 3ºC
Temp. Vapour separator 2 62 ± 3 ºC
Temp. Vapour separator 3 60 ± 3ºC
Temp. Vapour separator 4 52 ± 3ºC
Temp. Vapour separator 5 46 ± 3ºC
Evaporator vaccum 650 – 680 mm Hg
Temp difference between inlet & outlet >5 ºC
condenser water
Baume reading 21 – 24
Drying plant
Inlet air temperature 170 – 200 ºC
Outlet air temp. 90 ± 5 ºC
Chember vaccum(of water) -5 to -10 mmwc
Vibro inlet air temp For hot section(2 stage 95 ± 3ºC
drying)
Vibro inlet air temp For hot section(single Ambient
stage drying)
Vibro exhaust temp.(for single stage) 59 ± 3ºC
Vibro exhaust temp.(for 2 stage) 62 ± 3ºC
Vibro vaccum -10 to – 15 mmwc
Packaging of powder :
Introduction :
Quality of product is must in order the market. This section controls the quality of
production, packaging material. This section carries out tests on products by keeping the
view of quality control and consumer satisfaction. Effluent plant is of more importance
as far as solution for environmental pollution is considered which comes under Quality
Control Section.
In the laboratory various tests are carried out on samples so as to improve the
product quality. All the standard techniques are followed in appropriate manner.
PHYSICAL
Smell Satisfactory(Min.) Satisfactory(Min.)
B) Pasteurized Milk :
Tests Parameters
BIOCHEMICAL.
MBRT 4 Hrs (Min.).
BACTERIOLOGICAL
SPC 30,000 (Max.)
Coliform Absent.
PCT Negative.
BIOCHEMICAL.
MBRT 4.5 Hrs (Min.).
PHYSICAL.
Temperature 36 – 40 0 F
Keeping Quality 10 Hrs.
Tests Parameters
CHEMICAL
Fat 3.5 % (Min.)
SNF 9.3 %(Min.)
A) CREAM
Tests Parameters
CHEMICAL
Fat 35 % (Min.)
Acidity 0.07 – 0.09 %L.A
B) WHITE BUTTER
Tests Parameters
CHEMICAL
Fat 80 % ( Min.)
Moisture 16 % (Max.)
Acidity
PCT Nil / 10 gm.
C) TABLE BUTTER :
Tests Parameters
CHEMICAL
Fat 80 % ( Min.)
Moisture 16 % (Max.)
Curd 1.5 % (Max.)
Salt 3.0 % (Max.)
D ) GHEE :
Tests Parameters
CHEMICAL
Moisture 0.5 % (Max.)
Baudoilin Test Negative.
Acidity 3 % (Max.)
PHYSICAL
Clour Yellowish White.
Sediment No.
E) CHAKKA :
Tests Parameters
CHEMICAL
T. S. 30.0 % (Min)
Milk Fat 33.0 % (Min)
Protein 37.0 % (Min)
Acidity 2.5 % (Min)
Ash 3.5 % (Min)
BACTERIOLOGICAL
Y/M 20/gm (Max)
Coliform Absent
G) LASSI :
Tests Parameters
CHEMICAL :
T. S. 18- 21 %
Fat 1.5 % (Max)
Acidity 0.60 – 0.75 % L. A.
BACTERIOLOGICAL
SPC 10-40 Thousands
PCT Nil
Y/M 1 – 2 (Max.)/ ml
Equipment
1. Milko Tester
2. B.O.D. Incubator
3. Incubator (H.A.O.)
4. Moisture Analyzer
5. Laboratory Centrifuge
6. Gerber Centrifuge
7. Solubility index mixer
8. Electronic Weighing balance
9. Moisture analyzer
10. Hot Water Bath
11. Bulk density apparatus
12. Muffle furnaces
13. Refrigerator
14. Bursting strength tester
15. Sieve Shaker (Table Top)
16. Caliper gauge
17. Distilled water preparation assembly
18. Autoclave
19. Laminar air flow chamber
REFRIGERATION SECTION
5
2
1.Compressor.
2.Condessor.
3.Receiver.
4.Expansion valve.
5.Evaporator.
Compressor:-
In Gokul the compressor are made up of the “ SABRO” company which are
screw type compressor , having capacity 225kr , having motor of 350 Hp is used. The
compressor increases the pressure forming vapour mix liquid.
Compressor Screw Type:-
“SABRO” Specification
1. Max operating pressure 28 bar
2. Test pressure 25 bar
3. Max. operating temperature 130 ºC
4. Min operating temperature 0 ºC
5. Volume 600 lit
Condensor:-
Here tube & shell tube type of condenser are used. The chilled water is circulated
through tube whereas, the NH3 is circulated through shell.The cost NH3 is about
50 Rs/lit. In condenser the liquid i.e water is formed having low temperature.
Receiver:-
The receiver , receives the water which is used as a chilled water for different
process.
BOILER SECTION:-
The main function of boiler is to produce steam. In Gokul there are 3 boilers each of
having capacity 5 ton/hr.
a) In Smoke tube boiler furnace oil is used for combustion having burning point 110 ºC.
b) In this there are 3 passes, which are circulating passes.
c) Here steam pressure is maintained between 10 – 12 kg/cm2 . The boiler have oil pump
, oil filter , electric heater which regulates the temp at 110ºC.
d) The water which is used comes through feed pump having feed check valve.
e) In this section the effiency of boiler is considerd on the basis of the oil consumption,
feed consumption.
MECHANICAL SECTION
Mechanical section provides the services like welding, soldering, filing , cutting,
threading and many more as per requirements. They are supposed to do the job of
regular inspection of machines and do the oiling or greasing as per schedules. They
are also involved in erection of new machinaries. Garage section comes under this
section where the tempos, trucks are serviced at cheaper rates.
CIP SECTION
CIP system is located at right hand side of RMRD. It is having four CIP tanks for
storing different cleaning and sanitizing solutions of various temperatures .These tanks
are connected to processing section through pipelines for cleaning various milk
processing equipment and systems.
Cleaning In Place applied to milk lines. Only cream separator & filters are
cleaned manually after each shift.
CIP Programme for circuit with pipes, tanks & other cold components :
By pump
By Gravity
By pump
Effluent
Recirculation
UASB
500m3
By gravity
Sludge
Recirculation By gravity
9 × 9× 1 net
By gravity
4m3
Treated
Effluent
Tank
The capacity of this ETP plant is about 1400m3/day. The fat obtained in ETP section
is transfer to the soaf industries for further use. The sludge obtained in Different stages of
ETP is used as manure for farming.