Area Task Person Date

Applications due - 11.30.07


Finalize Partner review process Kate, Charlyn, DONE
Jean
Develop Partner review tool Kate, Charlyn DONE
Reminder e-mail to potential applicants Jean, Gina DONE
Small group review of Partner applications TBD Early
Selection of
January
Partners and
SF team meeting to review recommendations for SF team January
Affiliates
partnership
National Partners meeting to review recommendations SF team, ntl. January
for partnership partners
Letters to Affiliates and accepted Partners, including Kate, Jean 02.01.08
what those rejected for partnership can do to become
Partners in 2009
Letter to National Partners informing them about the Jean DONE
network, encouraging support, etc.
Collect one-pager for each National Partner describing Kate 11.30.07
National
connections with SF
Partners
Identify reviewers for Network Partner applications SF team 12.31.08
Discuss role of National Partners with Network SF team, TBD
Partners in first conference call National Partners
Finalize training submission form Kate, Charlyn DONE
Training Develop and finalize protocol for reviewing and listing Kate, Charlyn, 11.14.07
Marketplace trainings in the marketplace Jean
Engage outside folks to help review trainings Kate 11.14.07
One-pager about the purpose and protocol of learning Kate 11.30.07
Learning
circles
Circles
One-pager about each learning circle Kate 11.30.07
Gather general SF materials Kate DONE
Create a skeletal outline for the peer review process for Kate DONE
Electronic
use on the first conference call with Network Partners
Library
Develop peer review process with Network Partners on SF team, TBD
first conference call National Partners
Fee-for- Develop request form for technical assistance Kate 11.30.07
service TA
Discuss data tracking, including items to be tracked SF team, TBD
Data Tracking and mechanisms for collection with Network Partners National Partners
in first conference call
Website posted Camille 01.11.08
Changes to Camille SF Team 01.18.08
Changes posted Camille 01.25.08
Website
Beta testing SF team, select 01.25.08 –
states 02.11.08
Changes posted, public website launch Camille 02.14.08
Publicity Prepare press release(s) for launch Kate et al 02.01.08
SFNN LAUNCH: 02.14.08!