Sie sind auf Seite 1von 380

Project Management

Project Mangement
( Notes )

For Private Circulation Only.

Prof. : A .A. Attarwala.

Prepared by – Vinayanand Rele


Page 1 of 380 24/11/2008
Project Management

Syllabus

1. Total Project Management – Concept, relationship with other function and other
organizations, organizing for project management – matrix organization – the
project manager as an entrepreneur.

2. Project identification – Scounting for project ideas and promoters identification of


investment opportunities, basis of governmental regulatory framework, various
acts and laws affecting project identification.

3. Location Decisions – Objectives, factors affecting location, concept of industrially


backward areas, incentives available for appropriate location.

4. Project Appraisal – Market Appraisal, Demand estimation and forecasting,


Technical Appraisal – Raw materials – Technology – Project Mix – plant capacity
– distribution channels.

5. Project financing – Basic concepts of cost of project, profitability analysis, Means


of financing, raising capital, asserting tax burdens and using financial projections,
Appraisal criteria used by lending institutions.

6. Risk analysis of project – measures of risk, use of subjective probabilities,


mathematical analysis, sensitivity analysis, simulation analysis, decision tree
analysis.

7. Project Planning, monitoring and control – network techniques, GATT charts,


network cost system, resource allocation and scheduling, progress reports,
updating, management information system for project.

8. Use of computer in network analysis – project management packages – choosing


and using them.

9. Case Study

University Examination : 100 Marks

Paper Time : 4 hrs

Professor :

Prof. A A Attarwala

Prepared by – Vinayanand Rele


Page 2 of 380 24/11/2008
Project Management

Reference Books :

Book – 1

Project Management - Prasanna Chandra

Material Required –

Scientific Calculator
Pencil & Sharpnor

Prepared by – Vinayanand Rele


Page 3 of 380 24/11/2008
Project Management

4th February, 2008.

Lecture – I.

Define Project Management

By – Project Management Institute ( PMI )

A Project is an entity which is :

a) A Temporary effort ( Unique )


b) Constrains by “Time” & “Resources”
c) Has definite Start & End.

Examples :

Flyovers, Launching a new product ( marketing ), recruitment, Installing a plant.


Anything which satisfy the above a,b,c is project.

Project is a logical activity in order, each activity has the duration.

How the project is presented –

In form of Model
Network diagram

Techniques for Project Presentation.

CPM – Critical Path Method.


PERT - Program Evaluation & Review Technique.

In CPM/PERT method a project is exhibited as a NETWORK.

In CPM/PERT we define a project as a group of activities which are of Interdependent.

Arrow Diagram
PERT Network
Network

What is Activity ?

An activity is a physical task which consumes Time, Money, Resources, Equipment,


Manpower in any combination.

Prepared by – Vinayanand Rele


Page 4 of 380 24/11/2008
Project Management

Activity=Task=Job.

How activity is Represented ?

Hunt For Chief Guest Start Activity Activity


Label

Event Fixed up the Chief Guest (A) Event


Label 1 2
Label
5 Days

Tail / Start Head / End


Event Event

1. First Method

A
1 2
5

2. Second Method

5
1 2

3. Third Method

5
1 2

Prepared by – Vinayanand Rele


Page 5 of 380 24/11/2008
Project Management

In-Correct ways to Represent the Network diagram.

1. A
1 1
5

Both Start & End Labels are Same.

2. A
1 2
5

Cannot go from High Label to Low Label

3.
A

No label names are given

4.
A
1
5

No tail is defined.

5.
A
2
5

No Head is Defined.

6.
A

5
1 2

Extra Event is Defined.

7.
A
1 2
Arrow is shown in the Centre.
5

Prepared by – Vinayanand Rele


Page 6 of 380 24/11/2008
Project Management

Tips for Drawing the Network Diagram.

1. Suppose activity A & B starts together.

2
A

1
B
3

Or
2
B

1
A
3

A
1 2

B
1 3

This is Wrong, Because No event can be Twice

2. Common Start.

2
A

B
1 3
C

Prepared by – Vinayanand Rele


Page 7 of 380 24/11/2008
Project Management

3. Interdependent

Suppose A & B Starts together,


C starts after A is over,
D & E starts after B is over.

This can be mathematically represented as below

A B C D E  Seceding
- - A B B  Presiding

Points to be noted here –

- means does not have any preceding activity


A is the preceding event
C is the succeeding event

C
2 4
A

5
1 D
B

3
E

Very Important :

1 6 Must be from higher to lower


Must be from left to right
And upper to lower.

Question :

What is the difference between arrow and node diagram ?

Prepared by – Vinayanand Rele


Page 8 of 380 24/11/2008
Project Management

4. R starts after P & Q are over.

4
P
R
6 7
Q

Start of R depends upon when BOTH P & Q are over.

5. A & B starts together,


C starts after A is over
D & E starts after B is over
F starts after C & E are over

A B C D E F
- - A B B E

C
2
A C
F
4 6
1 E
B

3
D

Prepared by – Vinayanand Rele


Page 9 of 380 24/11/2008
Project Management

Problem – 1.

Consider the Activities required to complete the processing of Consumer’s order :

Activities Preceding Activities (s)

A. Receipt of order, checking credit rating, etc -


B. Preparation of Material Specification, availability of
Materials etc. A
C. Inspection Packing etc. B
D. Arrangement of transports facilities etc. A
E. Delivery C,D

Draw the arrow Diagram

Solution :

First put the Mathematical equation.

A B C D E
- A B A C,D

Check what is combining two.


E
C, D

There can be 3 ways by this can be drawn.

First way -

E
3 5
D
C

A B
1 2 4

Prepared by – Vinayanand Rele


Page 10 of 380 24/11/2008
Project Management

Second Way –

A B C E
1 2 3 4 5

Third Way –

3
B C

A D E
1 2 4 5

All three ways are correct.

Prepared by – Vinayanand Rele


Page 11 of 380 24/11/2008
Project Management

Problem – 2.

The owner of a chain of fast-food restaurants is considering a new computer system for
accounting and inventory control. A computer company send the following information
about the system installation.

Activity Activity Description Immediate


Identification Predecessor

A Select the Computer Model -


B Design Input / Output system A
C Design Monitoring System A
D Assemble Computer System B
E Develop the main Programs B
F Develop Input / output routines C
G Create Data base E
H Install the System D,F
I Test and Implement G,H

Construct the PERT network for this Problem.

Solution :

A B C D E F G H I
- A A B B C E D,F G,H

5
E

3
G
B \
D
A \
1 2
C
F H I
4 \ 6 7 8

Prepared by – Vinayanand Rele


Page 12 of 380 24/11/2008
Project Management

Problem – 3.

Problem – 3.1.

Activity P Q,R S T U V
Preceding activity - P Q R S,T U

Solution :
3
S
Q

P U V
1 2 5 6 7
R
T
4

Problem – 3.2.

Activity A,B,C D E F G H I K
Preceding activity - A B C D E F G,H,I

Solution :

D
2 5
A G

B E H K
1 3 6 8 9
C
I
F
4 7

Prepared by – Vinayanand Rele


Page 13 of 380 24/11/2008
Project Management

Problem – 3.3.

Activity A B C D E,F G H I J K L
Preceding Activity - A A A B E F G,H C D I,J,K

Solution :
6
H
F

3 8
E G

7 I
B

A C J L
1 2 4 9 10
D
K
5

Problem – 3.4.

Activity A B C D E F G
Linking Events 1-2 1-3 2-4 3-4 3-5 4-5 5-6

Solution :

2
A C

1 4
B D

3 F

E
G
5 6

Prepared by – Vinayanand Rele


Page 14 of 380 24/11/2008
Project Management

Problem – 3.5.

Activity A B C D E F G H I J K L
Linking 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-10 9-10
Events

Solution :

2
A C

F
1 4 9
L
B D

3 10
6
E
G I K

5 8
H J

Prepared by – Vinayanand Rele


Page 15 of 380 24/11/2008
Project Management

Dummy Activity

It is an activity which neither consumes any time nor resources. It is denoted by “Dotted
Line”. It is used for logical purpose.

e.g

Dummy
1 2
0

Note : If dotted line is not drawn then it will be wrong.

Two places where dummy is used.

FIRST. Suppose A & B start together C starts after both A & B are over.

i.e.

A B C
- - A,B

Observe that A & B have Same Tail Events & Head Events.

Shown below Three representations are not allowed.

A
C
1 B 2 3

A
C
1 2 3
B

A
C
1 2 3
B

Prepared by – Vinayanand Rele


Page 16 of 380 24/11/2008
Project Management

Correct Representations

2
A

D1
1
B
C
3 4

3
A

D2
1
B
C
2 4

SECOND. Suppose A is a starting activity

A B C D E F
- - A B C,D D

Observe that Head / End Events of D is in E as well as F

C E

D F

This is wrong because F can be only after D is over.

Prepared by – Vinayanand Rele


Page 17 of 380 24/11/2008
Project Management

Correct is

C E
2 5 6
A

D1
1
B

D F
3 5 6

Prepared by – Vinayanand Rele


Page 18 of 380 24/11/2008
Project Management

Problem – 3.6.

Job A B C D E F G H I J K
Immediate - A B C D E D,F E H G,I J
Predecessors

Solution :

H I

A B C D E F G
1 2 3 4 5 6 7 9

D1
10

11

OR

H I

A B C D E J
1 2 3 4 5 6 9 10

K
F G

8
11

Prepared by – Vinayanand Rele


Page 19 of 380 24/11/2008
Project Management

Problem – 3.7.

Job A B C D E F G H J K L M N O
Preceding Activity - - A B C C D D E E,F G,H H J,K L,M,N

Solution :

J
6 10
E
C
D1 K
2 4
N
A F
7

1 L O
9 11 12

G
B
D
3 5 D2 M

H
8

Prepared by – Vinayanand Rele


Page 20 of 380 24/11/2008
Project Management

5th February, 2008.

Lecture – II.

Problem – 3.8.

Task A B C D E F G
Immediate Activity - - B B B E A,D,C

Solution :

Note that, Two activity starts together & ends together C,D. Hence this requires a
dummy.

A 4
1

C G
B D1

D 6
2 3

F
E

Very Important Note :

There are two ends of the project ( DANGLER )

It is not allowed by default, F & G should meet at one place as they are the final
activities

Prepared by – Vinayanand Rele


Page 21 of 380 24/11/2008
Project Management

Problem – 3.9.

A and B are start jobs


A controls C,D and E
B controls F and K
G depends on C
H depends on D
E and F control J and M
L depends on K
M is also controlled by L
G,H,J and M are last jobs.

Solution :

Job A B C D E F K G H J M L
Preceding Activity - - A A A B B C D E,F E,F,L K

Observer that,

G,H,J,M are the Final activities


E,F

4
G
C

D H
2 5 9
A
E J
1
B M
6
F
3 D1
8
K
L

Prepared by – Vinayanand Rele


Page 22 of 380 24/11/2008
Project Management

Problem – 3.10.

(a) A,C,D Can start immediately


(b) E > B,C
(c) F,G > D
(d) H,I > E,F
(e) J > I,G
(f) K>H
(g) B>A

For Home work

Prepared by – Vinayanand Rele


Page 23 of 380 24/11/2008
Project Management

Problem – 3.11.

(a) A and B start Immediately


(b) C,D > A
(c) E > B,C
(d) F,H > E
(e) G > D,F
(f) J>G
(g) I,K > H
(h) L > J,I

Solution :

Job A B C D E F H G I J K L
Preceding Activity - - A A B,C E E D,F G H H J,I

No Dummy required from both the rules

D G
2 5 6
A J

1 C F 8
B I L
E H
K
3 4 7 9

Prepared by – Vinayanand Rele


Page 24 of 380 24/11/2008
Project Management

Problem – 3.12.

Activity A B C D E F G H
Predecessor - - A A B B C,E D,F

Solution :

Crossing is allowed.

4
C G

2 6
A H

1 D 5
B F

Prepared by – Vinayanand Rele


Page 25 of 380 24/11/2008
Project Management

Critical Path / Critical Activity / Project Duration.

Consider a given below project.

3
B E

7 11
A D 2 G
1 2 5 6
6 C F 5
4 1
4

Now to find out the Critical Path, first define the various Paths & Durations

Paths Durations Total Duration

1-2, 2-3, 3-4, 4-5, 5-6 6+7+2+1+5 = 21 –

Or

1-2, 2-3, 3-5, 5-6 6 + 7 + 11 + 5 = 29 —

Or

1-2, 2-4, 4-5, 5-6 6+4+1+5 = 16 ˜

Now out of the three available paths Path II is most critical as it has longest duration,
that is 29.

Critical path should be shown as below.

3
B E

7 11
A D 2 G
1 2 5 6
6 C F 5
4 1
4

Remember –

Duration of Critical path is the duration of project, therefore above project will be
completed in 29 days.

Prepared by – Vinayanand Rele


Page 26 of 380 24/11/2008
Project Management

Problem – 4.

The following Tables lists the activities of a maintenance project.

Activity 1-2 1-3 1-4 2-5 3-6 3-7 4-7 5-8 6-8 7-9 8-9
Duration
2 2 1 4 5 8 3 1 4 4 3
(in Months)

(i) Draw the project network.


(j) Find the Critical path and duration of the project. ( 15 Months )

Solution :

4
2 5
1

2
8
3
4
2 5
1 3 6 9

1 8 5

3
4 7

Paths Durations Total Duration

1-2, 2-5, 5-8, 8-9 2+4+1+3 = 10 –

1-3, 3-6, 6-8, 8-9 2+5+4+3 = 14 —

1-3, 3-7, 7-9 2+8+4 = 15 ˜

1-4, 4-7, 7-9 1+3+5 = 9 ™

The critical path is 1-3, 3-7, 7-9 (˜) as it has 15 months duration, which is highest.

Prepared by – Vinayanand Rele


Page 27 of 380 24/11/2008
Project Management

Problem – 5.

Draw the network for the following dependencies and identify critical path. Also find the
project duration.

Activity 1-2 1-3 1-4 2-3 2-6 3-5 3-6 4-5 5-6 5-7 6-7
Duration
8 7 3 6 8 6 4 12 0 6 8
(in Months)

( 28 Months )

Solution :

2
8

8
6 6 8
4
7
1 3 0 7
6 6
3 5
12

Tip : Start with Longest route first.

Paths Durations Total Duration

1-2, 2-3, 3-5, 5-6, 6-7 8+6+6+0+8 = 28


1-2, 2-3, 3-5, 5-7 8+6+8+6 = 28
1-2, 2-3, 3-6, 6-7 8+6+4+8 = 26
1-2, 2-6, 6-7
1-3, 3-5, 5-6, 6-7
1-3, 3-5, 5-7
1-3, 3-6, 6-7
1-4, 4-5, 5-6, 6-7
1-4, 4-5, 5-7

There are more than ONE Critical Paths.

Prepared by – Vinayanand Rele


Page 28 of 380 24/11/2008
Project Management

Problem – 6.

(i) Draw the Network for the following data and determine the critical path and
project duration .

Activity Preceding Activity Duration ( Days )


A - 4
B - 5
C A 2
D A 3
E B. C 3
F B, C 4
G D, E 5
H F 2

(Ii) If activity F has to precede activity G, will the critical path Changes ? If it does
change then draw your new network and calculate the length of new critical path.

This problem is for Home work.

Prepared by – Vinayanand Rele


Page 29 of 380 24/11/2008
Project Management

Time Estimates

Time estimates of an Activity

Associated with each activity, there are 4 time estimates, They are :

i) Earliest Start Time

( EST ) Represented as ( )

EST is also knows as “Forward Pass”

ii) Latest Start Time

( LST )

iii) Earliest Finish Time

( EFT )

iv) Latest Finish Time

( LFT ) Represented as ( )

LFT is also knows as “Backward Pass”

Out of the above Four EST & LFT are shown in the Network Diagram.

Prepared by – Vinayanand Rele


Page 30 of 380 24/11/2008
Project Management

Question :

Explain forward pass ( EST ) and Backward pass ( LFT ).

This was asked as a Theory question.

Answer :

Theory Plus explanation.

Suppose process G starts after E & G are completed, E gets over on 13th, F gets over
on 15th. What is the EST of G.

5 E

13
G
7 8
F

6 15

G will start at 15 i.e. after 15 days.

Since G starts from Event 7

Therefore EST of G is written near its tail event 7 in a box Like 15

Explain : Forward pass don’t explain theory, Explain with the help of an example as
follows:

Compute EST
10

3
E
0 6 B 21 25
4 11
A G
1 2 D 2 5 6
6 4
C
F
3
5
4

12

Prepared by – Vinayanand Rele


Page 31 of 380 24/11/2008
Project Management

Suppose we start project at time t=0,


[ t = 0 means end of 0th day, beginning of first day ]

Then all activities from event 1 will start at time t = 0

Therefore activity A will start at t = 0 i.e. EST of activity A is Zero.

This we write near the tail event 1 of activity A in a Box Like 0

Activities B and C start after activity A is completed. There for EST of B and C is :

0 + 6 = 6

Means EST of A + Duration of A.


2 6
This we write near the tail event of B & C in a Box like

Similarly,

EST of D & E is

6 + 3 = 9

EST of F

As F starts after C & D are completed, therefore

via C

EST of F will be 6 + 3 = 9

Via D

EST of F will be 10 + 2 = 12
4 12
Which will be 12, This we write near the tail event of D Like

Now suppose there is another project which starts immediately after G is completed,
Then what is EST of that Project ?

Its EST is 21 + 4 = 25

To compute EST, we move from the first event to the last event. This is called “Forward
Pass”.

Prepared by – Vinayanand Rele


Page 32 of 380 24/11/2008
Project Management

Question – 1.

C E
3
9

3 6
D
F H
B 2
5 4 1
4
A G
1 2 I
7 8
3 6 7

Compute the EST.

Solution :
16

C E
7 3 19
9

3 6
D 9
F H
0 3 B 2
5 4 1 20 27
4
A G
1 2 I
7 8
3 6 7

First Calculate the EST.

Then draw the critical path.

Total project duration is 27.

Prepared by – Vinayanand Rele


Page 33 of 380 24/11/2008
Project Management

Question – 2.

6
4

1 2 2 5
3

7
5 4

4 7 8
9

3 6

Find out the EST.

Solution :
7

0 6 13
3 4

1 2 2 5
3

7 20 29
5 4

4 7 8
9

9
3 6

6
12

There are more than two Critical Paths exists.

Prepared by – Vinayanand Rele


Page 34 of 380 24/11/2008
Project Management

LFT ( Latest Finish Time ) or Backward Pass.

i) LFT Requires EST

ii) LFT is written at Head Event of each activity in a

iii) to Compute LFT we move from the Last Event to the First Event, therefore it is
called the Backward Pass.

How to find out LFT ?

3
B E

7 11
A D 2 G
1 2 5 6
6 C F 5
4 1
4

First Find out the EST

10

3
E
0 6 B 21 25
4 11
A G
1 2 D 2 5 6
6 4
C
F
3
5
4

12

EST = 25.

Suppose we want to complete the project by 25th Day then, all activities which get over
at the last event must get over latest by 25th Day. Therefore G must get over latest by
25th day.

Therefore LFT of G is 25.

Prepared by – Vinayanand Rele


Page 35 of 380 24/11/2008
Project Management

This we write in 25 triangle near Head Event of G.

5
At E & F get over when G starts, therefore LFT of both E & F is

25 - 4 = 21

LFT of G Duration of G

21 5
This we write in like near the head event of E & F

3 10
At D & F start after B is over. Therefore LFT of B is

16
LFT of D - 2 = 14

16
Via E - 11 = 10

So that 10.
3 10
This we write near the head event of B in a like

Now the Network Diagram can be drawn like given below

10

10

0 6 21 25
3
E
0 6 B 21 25
4 11
A G
1 2 D 2 5 6
6 4
C
F
3
5
4

12
16

Prepared by – Vinayanand Rele


Page 36 of 380 24/11/2008
Project Management

Question – 3.

C E
3
9

3 6
D
F H
B 2
5 4 1
4
A G
1 2 I
7 8
3 6 7

Compute EST & LFT.

Solution :

First find the EST of all the activities. ( Refer above answer of question No 1 ).

16

C E
7 3 19
9

3 6
D 9
F H
0 3 B 2
5 4 1 20 27
4
A G
1 2 I
7 8
3 6 7

So EST is 27.
0 27
LFT of at begin & end will be same i.e. &

5 Is 9 15

Prepared by – Vinayanand Rele


Page 37 of 380 24/11/2008
Project Management

15
LFT of D - 2 = 13

20
LFT of G - 6 = 14

19
LFT of E - 3 = 16

There fore For a Critical Path Activity LFT = EST

EST of G 3 + 6 = 9

EST of D 7 +2 = 9

EST of F 3 + 4 = 13

Therefore for a Critical Activity EFT = LST

Now the Network diagram can be drawn as shown below.

16

16

4
7 19
C E
7 3 19
9
15
3 6
0 3 D 9 20 27
F H
0 3 B 2
5 4 1 20 27
4
A G
1 2 I
7 8
3 6 7

Prepared by – Vinayanand Rele


Page 38 of 380 24/11/2008
Project Management

Problem – 7.

Consider the following project.

Activity A B C D E F G H I J K L
Duration 3 2 4 6 3 2 6 4 4 2 2 4
Immediate
None A A A B E C D G D D F,H,I
Predecessor

Compute EST/LFT of each activity of the Project.

Solution :

This problem is for Homework.

Prepared by – Vinayanand Rele


Page 39 of 380 24/11/2008
Project Management

9th February, 2008.

Lecture – III.

D F
5
11

3 7
E
G
B 2
6 3
7 I 4
A
1 2
6
C

3
H J
4 8 9
9 6

Find &

This can be done with help of table shown below.

Start Finish
Activity Duration Earliest Latest Earliest Latest
( EST ) ( LST ) ( EFT ) (LFT) 
A 1-2 6 0 6 6 6
B 2-3 7 6 7 13 13
C 2-4 3 6 7 9 13
D 3-5 11 13 11 24 24
E 3-6 2 13 2 15 15
F 5-7 5 24 5 29 29
G 6-7 3 15 14 18 29
H 4-8 9 9 24 18 33
I 7-8 4 29 4 33 33
J 8-9 6 33 6 39 39

Prepared by – Vinayanand Rele


Page 40 of 380 24/11/2008
Project Management

Steps followed for doing the above,

First –

Find out the EST & LFT, draw them on the Path as shown below and then put the
values in the table.

Draw the Critical Path.

24

24

5
13 29
D F
13 5 29
11 26
3 7
0 6 E 15
G
0 6 B 2
6 3
7 I 4
A
1 2 33
6 24 39
C 33
9 39
3
H J
4 8 9
9 6

Second –

Now Calculate the EFT & LST.

EFT = EST + Duration.

LST = LFT – Duration.

Important Points :

Difference between two start times is equal to two finish times, that is

LST – EST = LFT – EFT

Prepared by – Vinayanand Rele


Page 41 of 380 24/11/2008
Project Management

Another Concept.

Slack of an Event.

For e.g.
4
Slack of event

4 24 - 9 = 15

Slack of event 6

6 26 - 15 = 11

Slack of event 2

2
6 - 6 = 0

Slack of

6 9

6 24
C
2 4
3

So Slack of Tail event of C

C = Slack of event

6 6
2 = - = 0

So Slack of Head event of C

4 = 24 - 9 = 15

Prepared by – Vinayanand Rele


Page 42 of 380 24/11/2008
Project Management

Problem No – 8

For the following project of a repair work, find :

(a) Earliest Start Time.


(b) Latest Start Time.
(c) Earliest Finish Time.
(d) Latest Finish Time.
(e) Total Float.
(f) Free Float.
(g) Independent Float.
(h) Interfering Float.
(i) Project Duration.

Task 1-2 2-3 2-4 3-5 4-5 4-6 4-7 5-7 6-7 7-8
Immediate
1 5 3 4 2 5 9 4 2 2
Activity

Solution :

0 3 10
1

0 1 4 10
5
1 2 5
5 14 16
1
4 4 14 16
3 2
4 7 8
9 2

5
2
6
12 9

Steps followed.

1. Draw the Network Diagram.


2. First Find the EST & LFT, plot them on the Network diagram
3. Find EFT & LST, Next Slack of Tail & Head Event, then find others as per the
chart.

Prepared by – Vinayanand Rele


Page 43 of 380 24/11/2008
Project Management

Start Finish
Slack of Slack of
Total Free Independ Interfeari
Activity Duration Tail Head
Earliest Latest Earliest Latest Float Float ent Float ng Float
Event Event
( EST ) ( LST ) ( EFT ) (LFT) 

(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 ) (11) (12)
1-2 1 0 0 1 1 0 0 0 0 0 0
2-3 5 1 1 6 6 0 0 0 0 0 0
2-4 3 1 2 4 5 0 1 1 0 0 1
3-5 4 6 6 10 10 0 0 0 0 0 0
4-5 2 4 8 6 10 1 0 4 4 3 0
4-6 5 4 7 9 12 1 3 3 0 1~ 0 3
4-7 9 4 5 13 14 1 0 1 1 0 0
5-7 4 10 10 14 14 0 0 0 0 0 0
6-7 2 9 12 11 14 3 0 3 3 0 0
7-8 2 14 14 16 16 0 0 0 0 0 0

Earliest Finish Time ( EFT ) = EST + Duration = (3) + (2)


Latest Start Time ( LST ) = LFT – Duration = (6) – (2)
Total Float = LFT – EST or LST – EST = (4) – (3) or (6) – (5)
Free Float = Total Float – Slack of Head Event = (9) – (8)
Independent Float = Free Float – Slack of Tail Event = (10) – (7)
Interfering Float = Total Float – Free Float ( 9 ) – (10 )

Prepared by – Vinayanand Rele


Page 44 of 380 24/11/2008
Project Management

Problem No – 9

Listed below is a set of activities, sequences of activities and activity duration times.
Construct a network and determine the minimum project time. Also computer EST, EFT,
LST, LFT for each of the activities and calculate the various floats values of the
activities. Tabulate your results.

Activity A B C D E F G H I J
Immediate
- - B A,C B D A.C D E,H F,G,I
Predecessor
Duration ( Days ) 15 15 3 8 5 14 12 1 3 14

Solution :

This problem is for Home work.

Prepared by – Vinayanand Rele


Page 45 of 380 24/11/2008
Project Management

Problem No – 10

For the following network, find the earliest Start Time, Latest Start Time, Earliest Finish
Time. Latest Finish Time, Total Float, Independent Float, Interfering Float Critical Path &
Project duration.

Activity A B C F D G K E H J I
Linking Event 1-2 1-3 1-4 2-6 3-4 3-5 3-6 4-6 5-6 5-7 6-7
Duration 7 8 6 5 0 4 6 3 5 16 10

Solution :

13

F
A
7 5
0 15 18 28

0 8 17 28
B E I
1 4 6 7
6 3 10

C J
D 0 K H 5 16
8 6

G
8 8 3 5
4 12 12

Prepared by – Vinayanand Rele


Page 46 of 380 24/11/2008
Project Management

Start Finish
Slack of Slack of
Total Free Independ Interfeari
Activity Duration Tail Head
Earliest Latest Earliest Latest Float Float ent Float ng Float
Event Event
( EST ) ( LST ) ( EFT ) (LFT) 

(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 ) (11) (12)
A 1-2 7 0 6 7 13 0 6 6 0 0 6
C 1-3 8 0 0 8 8 0 0 0 0 0 0
B 1-4 6 0 9 6 15 0 7 9 2 2 7
F 2-6 5 7 13 12 18 6 1 6 5 -1 ~ 0 1
D 3-4 0 8 15 8 15 0 7 7 0 0 7
G 3-5 4 8 8 12 12 0 0 0 0 0 0
K 3-6 6 8 12 14 18 0 1 4 3 3 1
E 4-6 3 8 15 11 18 7 1 7 6 -1 ~ 0 1
H 5-6 5 12 13 17 18 0 1 1 0 0 1
J 5-7 16 12 12 28 28 0 0 0 0 0 0
I 6-7 10 17 18 27 28 1 0 1 1 0 0

Earliest Finish Time ( EFT ) = EST + Duration = (3) + (2)


Latest Start Time ( LST ) = LFT – Duration = (6) – (2)
Total Float = LFT – EST or LST – EST = (4) – (3) or (6) – (5)
Free Float = Total Float – Slack of Head Event = (9) – (8)
Independent Float = Free Float – Slack of Tail Event = (10) – (7)
Interfering Float = Total Float – Free Float ( 9 ) – (10 )

Prepared by – Vinayanand Rele


Page 47 of 380 24/11/2008
Project Management

Interpretation of Floats.

Question :

What are the Floats available in Numerical Analogy & what are their uses ?

Basically there no difference between slack and float, slack refer to an event. Float
refers to an activity.

A critical activity will have Zero Slack and Zero – Float. A non – Critical activity will have
at least one float positive. All slack may be zero.

Float is measured in units of Time.

e.g. 4 Days Float, 2 Weeks Float, 1 Month Float etc.

Float is a spare time available in a non critical activity which can be utilized either by
delaying the activity or by extending its duration.

Float is utilized for smoothening of resources. The resources are equipments and
manpower.

Total Float.

Consider an activity F

12 18

7 17
F
2 6
5

here now :

its LFT = 18

7
its EFT =
18 7
So maximum time available is - = 11

And its actual duration is = 5

Prepared by – Vinayanand Rele


Page 48 of 380 24/11/2008
Project Management

There fore Spare time = 11 – 5 = 6 days.

This spare time of 6 days is F, if absorbed, then neither it changes the critical path nor
the project duration. This is known a total float of F.

Thus Total Float ( TF ) of an activity is TF = LFT – EST – Duration.

Note : Critical activity has no Float.

Remarks :

(i) If TF = 0 then rest of the floats are zero


(ii) Independent Float ≤ Free Float ≤ Total Float
(iii) An activity is critical if and only if its total float is zero. Activity Critical < = > TF
= 0.

Free Float :

Consider activities F and I. F is preceding activity and I is a succeeding activity.

13 18 28

7 17 28
F I
2 6 7
5 10

Total Float of F = 6
Total Float of I = 1

17 7
Free float of F = EST of I - EST of F – 5 ( Duration of F ) = 17 – 7 – 5 = 5.

“Free Float” is the spare time available in a preceding activity, if absorbed then it will not
delay the start of the succeeding activity.

FF – EST of the succeeding activity – EST of activity ( whose FF we are finding ) –


Duration of the activity.

Prepared by – Vinayanand Rele


Page 49 of 380 24/11/2008
Project Management

Interfering Float :

Free Float + Interfering Float = Total Float or

Interfering Float = Total Float – Free Float

e.g. TF of F = 6, FF of F = 5.

therefore out of 6 days of F, 5 days is allowed to be absorbed. 1 day is disallowed to be


absorbed. This disallowed float of 1 day of F is known as interfering float of F.

Independent Float :

Consider activity K in the network shown below

0 18 28

0 17 28
F
1 6 7
5

F
F
5
5

3 8 8

It has a succeeding activity I, it has a preceding activity C, if K has not to disturb I, then
17
K should allow I to start at the EST . If K has not to disturb its preceding activity C

then K should all C to get over at its LFT 8 . If K does so, then its independent float is

17 - 8 - 6 = 3.

Thus independent float of an activity = EST of the succeeding activity – LFT of the
preceding activity – its duration.

Prepared by – Vinayanand Rele


Page 50 of 380 24/11/2008
Project Management

16th February, 2008.

Lecture – IV.

Crashing.

Crashing is based on only one Principle.

“Maximum Reduction in Duration & Minimum Increase in Cost“.

To Crash means to reduce the duration of the project.

Consider an activity ‘A’

A
1 2
7

Its normal duration is 7 days and its normal cost is Rs 500/-, its crash duration is 4 days
and crash cost is Rs. 620/-

Crash Cost - Normal Cost


Cost Slope = ----------------------------------------------
Normal Duration – Crash Duration

620 - 500
= --------------------- = 40
7– 4

i.e. to reduce the duration of activity A by 1 day, we have to increase the cost by Rs. 40.
Y - axis

620 ( 4, 620 )

Cost

500 ( 7, 500 )

X - axis
4 7
Duration

Prepared by – Vinayanand Rele


Page 51 of 380 24/11/2008
Project Management

From the Following find the Cost slope.

Duration Activity Cost


Activity
Normal Crash Normal Crash
1-2 5 2 600 900
2-4 6 3 700 1000
1-3 4 2 100 200
3-4 7 4 400 800
4-7 9 5 600 920
3-5 12 3 1600 1960
4-6 10 6 1500 1800
6-7 7 4 400 490
7-9 6 4 300 420
5-9 12 7 400 850

Solution :

Crash Cost - Normal Cost


Cost Slope = ----------------------------------------------
Normal Duration – Crash Duration

900 - 600
= --------------------- = 100
5– 2

Duration Activity Cost Cost


Activity
Normal Crash Normal Crash Slope
1-2 5 2 600 900 100
2-4 6 3 700 1000 100
1-3 4 2 100 200 50
3-4 7 4 400 800 133.333
4-7 9 5 600 920 80
3-5 12 3 1600 1960 40
4-6 10 6 1500 1800 75
6-7 7 4 400 490 30
7-9 6 4 300 420 60
5-9 12 7 400 850 90

Prepared by – Vinayanand Rele


Page 52 of 380 24/11/2008
Project Management

Tips for Crashing.

Consider the following Network.

3
E
B
9 11
A G
1 2 D 3 5 6
7 5
C
F
6
5
4

Path Duration Rank

i) 1–2–3–4–5–6 25 —
ii) 1–2–3–5–6 32 –
iii) 1–2–4–5–6 22 ˜

Critical Path 1–2–3–5–6


Normal Duration 32 Days

1) Usually we Crash activities ( CRITICAL ) in order of their cost Slope

Suppose activity ‘C’ ( 2 – 4 ) has the lease cost Slope


Further it is told that it can be crashed by 3 days, if we do so then,

i) Duration of – : 32
ii) Duration of — : 28
iii) Duration of ˜ : 19

Therefore New project duration is 32 days, i.e. there is no change in the


project duration. This is because activity ‘C” is Non Critical.

Therefore in order to reduce the project duration, ALWAYS CRASH A


CRITICAL ACTIVITY.

Prepared by – Vinayanand Rele


Page 53 of 380 24/11/2008
Project Management

2) Suppose critical activity ‘E’ has the least cost slope. Further it is told that it can
be crashed by 6 days. If we do so then.

i) Duration of – : 26
ii) Duration of — : 28
iii) Duration of ˜ : 22

therefore new project duration is 28 days,

As the original project duration was 32 days, the new project duration after
crashing a critical activity by 6 days is 28 days.

Even though we crash a critical activity by 6 days, the overall project duration
reduces by only 4 days. Therefore there is no point of crashing activity ‘E’ by 6
days. Crash it by only 4 days.

TIP :

‘Crash a critical activity in such a way that the original path remains critical. In
the process, if some another path becomes critical, then it OK’.

3) Crash Critical Activity ‘E’ only by 4 days. Now path — also becomes critical.

Therefore whenever there are two critical paths, then either crash A Common
Activity OR Two Un-common activities by the same duration.

Prepared by – Vinayanand Rele


Page 54 of 380 24/11/2008
Project Management

Problem – 1

The following table gives normal & crash times as well as normal and crash costs for the
activities of a project. Draw the network diagram and find the critical path. In case the
project duration is required to be crashed by 2 days, which activity will get the priority in
crashing ?

Duration Activity Cost


Activity
Normal Crash Normal Crash
1-2 5 2 600 900
2-4 6 3 700 1000
1-3 4 2 100 200
3-4 7 4 400 800
4-7 9 5 600 920
3-5 12 3 1600 1960
4-6 10 6 1500 1800
6-7 7 4 400 490
7-9 6 4 300 420
5-9 12 7 400 850

Solution :

First draw the Network diagram.


6

10
2 4 7
6
9
5
7
1 7
6
4
3 5 9
12 12

The Total Paths available are :

Paths Duration

1–2–4–6–7–9 = 39 –
1–2–4–7–9 = 26 ™
1–3–4–6–7–9 = 34 —
1–3–4–7–9 = 26 ™
1–3–5–9 = 28 ˜

Prepared by – Vinayanand Rele


Page 55 of 380 24/11/2008
Project Management

There are two Critical paths viz.

1–2–4–6–7–9
1–3–4–6–7–9

On both the critical paths there are 3 activities which are common activities namely,

Cost Slope

4–6 = 75
6–7 = 30
7–9 = 60

Among the three common activities, activity 6 – 7 has a least cost slope with just 3 days.

Therefore if you want to reduce the project duration by 2 days, then we crash activity 6 –
7 by 2 days.

Therefore activity 6 – 7 will get priority.

Prepared by – Vinayanand Rele


Page 56 of 380 24/11/2008
Project Management

Problem - 2

Following table gives the data on normal time and cost and crash time and cost for a
project.

Duration ( Weeks ) Total Cost ( Rs )


Activity
Normal Crash Normal Crash
1-2 6 5 3000 4500
2-3 6 6 750 750
2-4 10 8 2000 3000
2-5 7 7 1200 1200
3-4 7 4 1000 1900
4-6 6 5 900 1300
5-6 6 4 600 1100

(i) Draw the network and find out the critical path and the normal project duration
(ii) Find out the optimum duration by crashing and the corresponding project cost.

Solution :

First find out the Cost Slope

Maximum Crashing
Activity Cost Slope
Possible
1-2 6-5=1 (4500 - 3000 ) / ( 6 - 5 ) = 1500
2-3 6-6=0 0
2-4 10 - 8 = 2 500
2-5 - 0
3-4 7-4=3 300
4-6 6-5=1 400
5-6 6-4=2 250

Now draw the Network diagram

Prepared by – Vinayanand Rele


Page 57 of 380 24/11/2008
Project Management

7
6

1 2 4 6
6 6
10

7
6

The Total Paths available are :

Paths Duration

1–2–3–4–6 = 25 –
1–2–4–6 = 22 —
1–2–5–6 = 14 ˜

– 1–2–3–4-6 25 / 22 / 21 / 20

Critical Activity Max Crashing Cost Rank Remarks


Available slope

1–2 1 1500 „ ( iii )


2–3 - -
3–4 3 300 ‚ (i)
4–6 1 400 ƒ ( ii )

— 1–2–4–6 22 / 22 / 21 / 20

1–2 1 1500 „ ( iii )


2–4 2 500 ƒ
4–6 1 400 ‚ ( ii )

˜ 1–2–5–6 19 / 19 / 19 / 18

1–2 1 1500 ( iii )


2–5 - -
5–6 2 250

Prepared by – Vinayanand Rele


Page 58 of 380 24/11/2008
Project Management

Step – i

Usually we crash critical activity in order of their Cost – Slope.

On CP (–)

Activity 3 – 4 has the least slope & it is available for crashing for 3 days.

So if we crash it by 3 days then duration of

– = 22
— = 22
˜ = 19

Therefore New project duration will be 22 days


And ) in cost 3 x 300 = 900.

Now path — also becomes critical.

Step – ii

On both the Critical paths crash the common activity 4 - 6 by one day.

– = 21
— = 21
˜ = 19

Therefore New project duration 21 days.


And ) in cost 1 x 400 = 400.

No other Path becomes critical.

Step – iii

Now on both the critical path crash activity 1 – 2 by 1 day.

– = 20
— = 20
˜ = 18

∴ New Project duration 20 days.

And ) in cost 1 x 1500 = 1500/-.

Prepared by – Vinayanand Rele


Page 59 of 380 24/11/2008
Project Management

Now since all activities on Critical Path (–) are already crashed therefore crashing is
over.

Conclusion :

Normal Path Duration = 25 Days


Normal Cost = Rs. 9450/-
Crash Path Duration = 20 Days
Crash Cost =

9,450 /-
+ 900 /-
+ 400 /-
+ 1,500 /-
------------
12,250/-

Prepared by – Vinayanand Rele


Page 60 of 380 24/11/2008
Project Management

Problem - 3

The following table gives time ( in days ) and cost of activities ( in Rs ) of a project.

Normal Crash
Activity
Time ( Days ) Cost ( Rs ) Time ( Days ) Cost ( Rs )
1-2 12 1,250 9 1,490
1-3 11 1,125 8 1,335
1-4 14 1,200 10 1,500
2-4 7 1,050 5 1,170
3-4 12 800 8 920
4-5 3 1,100 1 1,200

(i) Draw the network for the project


( ii ) Find the critical path and the normal project length.

Determine the minimum cost and the corresponding duration in days.

Solution :

Maximum Crashing
Activity Cost Slope
Possible
1-2 12 - 9 = 3 (1490 - 1250 ) / ( 12 - 9 ) = 80
1-3 11 - 8 = 3 70
1-4 14 - 10 = 4 75
2-4 7-5=2 60
3-4 12 - 8 = 4 30
4-5 3-1=2 50

11 12

1 4 5
3
14

12
7

Prepared by – Vinayanand Rele


Page 61 of 380 24/11/2008
Project Management

The Total Paths available are :

Paths Duration

1–3–4–5 = 26 –
1–4–5 = 17 ˜
1–2–4–5 = 22 —

– 1–3–4-5 26 / 22 / 20 / 17

Critical Activity Max Crashing Cost Rank Remarks


Available slope

1–3 3 70 „ ( iii )
3–4 4 30 ‚ (i)
4–5 2 50 ƒ ( ii )

— 1–2–4–5 22 / 22 / 20 / 17

1–4 3 80 „
2–4 2 60 ƒ ( iii )
4–5 2 50 ‚ ( ii )

˜ 1–4–5 17 / 17 / 17 / 17

1–4 4 75 ( iii )
4–5 2 50

Step – i

On CP (–)

Activity 3 – 4 has the least slope & it is available for crashing for 4 days.

So if we crash it by 3 days then duration of

– = 22
— = 22
˜ = 17

Prepared by – Vinayanand Rele


Page 62 of 380 24/11/2008
Project Management

Therefore New project duration will be 22 days


And ) in cost 4 x 30 = 120/-.

Now path — also becomes critical.

Step – ii

On CP (–) & (—) activity 4 – 5 is common activity. Hence crash 4 – 5 by one


day.

– = 20
— = 20
˜ = 17

Therefore New project duration 20 days.


And ) in cost 2 x 50 = 100/-.

No other Path becomes critical.

Step – iii

On CP (–) Crash Activity 1 – 3 by One Day


On CP (—) Crash Activity 2 – 4 by Two Days
On CP (˜) Crash Activity 1 – 2 by One Day

– = 17
— = 17
˜ = 17

∴ New Project duration 17 days.

And ) in cost 3 x 70 = 210/- +


2 x 60 = 120/- +
1 x 80 = 80/- = 310/-

Now since all activities on Critical Path (–) are already crashed ∴ crashing is over.

Prepared by – Vinayanand Rele


Page 63 of 380 24/11/2008
Project Management

Conclusion :

Normal Path Duration = 26 Days


Normal Cost = Rs. 6525/-
Crash Path Duration = 17 Days
Crash Cost =

6,525 /-
+ 120 /-
+ 100 /-
+ 310 /-
------------
6,935/-

Prepared by – Vinayanand Rele


Page 64 of 380 24/11/2008
Project Management

23th February, 2008.

Lecture – V.

Problem - 4

The following table gives the activities in a construction project and other relevant
information.

Preceding
Activity Normal Time Crash Time Normal Crash
Activity
( Days ) ( Days ) Cost ( Rs ) Cost ( Rs )
1 - 2 - 20 17 600 720
1 - 3 - 25 25 200 200
1 - 4 1-2 10 8 300 440
2 - 4 1-2 12 6 400 700
3 - 4 1-3 2-3 5 2 300 420
4 - 5 2-4 3-4 10 5 300 600

(a) Draw the Activity Network for the project


(b) Find the critical path
(c) Using the above information crash or shorten the activity step by step until the
shortest duration is reached.

Solution :

20 12

1 4 5
10
10

25
5

Prepared by – Vinayanand Rele


Page 65 of 380 24/11/2008
Project Management

The Total Paths available are :

Paths Duration

1–2–3–4 -5 = 45 –
1–2–4-5 = 42 —
1–3–4–5 = 40 ˜

Maximum Crashing
Activity Cost Slope
Possible
1-2 20 - 17 = 3 (720 - 600 ) / ( 20 - 17 ) = 40
1-3 25 - 25 = Nil 0
2-3 10 - 8 = 2 70
2-4 12 - 6 = 6 50
3-4 5-2=3 40
4-5 10 - 5 = 5 60

– 1–2–3–4-5 45 / 42 / 39 / 34 / 32

Critical Activity Max Crashing Cost Rank Remarks


Available slope

1–2 3 40 ‚ (i)
2–3 2 70 „ ( iv )
3–4 3 40 ƒ ( ii )
4–5 5 60 … ( iii )

— 1–2–4–5 42 / 39 / 39 / 34 / 32

1–2 3 40 (i)
2–4 62 50 ( iv )
4–5 5 60 ( iii )

˜ 1–3-4–5 40 / 40 / 37 / 32 / 32

1–3 -- 0
3–4 3 40 ( ii )
4–5 5 60 ( iii )

Prepared by – Vinayanand Rele


Page 66 of 380 24/11/2008
Project Management

Step – i

On CP (–) & CP (—) Crash Activity 1 – 2 by 3 days.

– = 42
— = 39
˜ = 40

∴ New project duration will be 42 days, And ) in cost 3 x 40 = 120/-.


No other path becomes critical

Step – ii

On CP (–) & CP (˜) crash activity 3 – 4 by 3 days.

– = 39
— = 39
˜ = 37

∴ New project duration will be 39 days, And ) in cost 3 x 40 = 120/-.

Now both CP (–) & CP (—) are critical.

Step – iii

On CP (–) Crash Activity 4 – 5 by 5 days.

– = 34
— = 34
˜ = 32

∴ New Project duration 34 days.

And ) in cost 5 x 60 = 300/-

No other path becomes critical

Prepared by – Vinayanand Rele


Page 67 of 380 24/11/2008
Project Management

Step – iv

On CP (–) Crash Activity 2 – 3 by 2 days &


CP (—) Crash Activity 2 – 4 by 2 days

– = 32
— = 32
˜ = 32

∴ New Project duration 32 days.

And ) in cost 2 x 70 = 140/- + 2 x 50 = 100. i.e. 240/-

Now since all activities on CP (–) are crashed, Crashing is over.

Conclusion :

Normal Path Duration = 45 Days


Normal Cost = Rs. 2100/-
Crash Path Duration = 32 Days
Crash Cost =

2,100 /-
+ 120 /-
+ 120 /-
+ 300 /-
+ 240 /-
------------
2,880/-

Prepared by – Vinayanand Rele


Page 68 of 380 24/11/2008
Project Management

Problem - 5

The table below provides cost and time estimates of seven activities of a project.

Time Estimates ( Weeks ) Direct cost Estimates ( Rs in Thousands )


Activity
Normal Crash Nomal Crash
1-2 2 1 10 15
1-3 8 5 15 21
2-4 4 3 20 24
3-4 1 1 5 7
3-5 2 1 8 15
4-6 5 3 1 16
5-6 6 2 1 36

(i) Draw the project network corresponding to the normal time.


( ii ) Determine the critical path and the normal duration and normal cost of the
project.
( iii ) Crash the activities so that the project completion time reduces to 9 weeks
with minimum additional cost.

Solution :
2

4
2
4
1
5
8 1
6
3

2 6
5

The Total Paths available are :

Paths Duration

1 – 2 – 4- 6 = 11 ˜
1–3–4-6 = 14 —
1–3–5–6 = 16 –

Prepared by – Vinayanand Rele


Page 69 of 380 24/11/2008
Project Management

Maximum Crashing
Activity Cost Slope
Possible
1-2 2-1=1 (15 - 10 ) / ( 2 - 1 ) = 5
1-3 8-5=3 2
2-4 4-3=1 4
3-4 1-1=0 0
3-5 2-1=1 7
4-6 5-3=2 3
5-6 6-2=4 6

– 1–3–5-6 16 / 13 / 11 / 9

Critical Activity Max Crashing Cost Rank Remarks


Available slope

1–3 3 2000 ‚ (i)


3–5 1 7000 „ ( iii )
5–6 4
/ 2 6000 ƒ ( ii )

— 1–3–4–6 14 / 13 / 11 / 9

1–3 3 2000 (i)


3–4 0 0 ( iii )
4–6 2 3000 ( ii )

˜ 1–2-4–6 11 / 11 / 11 / 9

1–2 1 5000
2–4 1 4000
4–6 2 3000 ( iii )

Step – i

On CP (–) Crash Activity 1 – 3 by 3 weeks.

– = 13
— = 11
˜ = 11

∴ New project duration will be 13 weeks, And ) in cost 3 x 2000 = 6000/-.


No other path becomes critical.

Prepared by – Vinayanand Rele


Page 70 of 380 24/11/2008
Project Management

Step – ii

On CP (–) crash activity 5 – 6 by 2 weeks.

– = 11
— = 11
˜ = 11

∴ New project duration will be 11 days, And ) in cost 2 x 6000 = 12,000/-.

Now all paths are critical.

Step – iii

On CP (–) Crash Activity 5 – 6 by 2 weeks.


CP (—) Crash Activity 4 – 6 by 2 weeks
CP (˜) Crash Activity 4 – 6 by 2 weeks

– = 9
— = 9
˜ = 9

∴ New Project duration 11 days.

And ) in cost 2 x 6000 + 2 x 3000 + 2 x 3000 = 18,000/-

Now since all activities on CP (–) are crashed, Crashing is over.

Conclusion :

Normal Path Duration = 16 weeks


Normal Cost = Rs. 82,000/-
Crash Path Duration = 11 weeks
Crash Cost =

82,000 /-
+ 6,000 /-
+ 12,000 /-
+ 18,000 /-
--------------
1,18,000/-

Prepared by – Vinayanand Rele


Page 71 of 380 24/11/2008
Project Management

Problem - 6

The Basic Time Data for the Jobs in a project are as follows :

Normal Crash
Activity
Time ( Days ) Cost ( Rs ) Time ( Days ) Cost ( Rs )
A 3 140 2 210
B 6 215 5 275
C 2 160 1 240
D 4 130 3 180
E 2 170 1 250
F 7 165 4 285
G 4 210 3 290
H 3 110 2 160

The activity (Job) dependencies are as follows :

(i) A,B,C are starting activities


(ii) Activities D,F,E can start when A is completed.
(iii) Activity G can start after B and D are completed.
(iv) Activity H can start after C and E are completed.
(v) Activity F,G and H are the final activities.

(a) Draw the Network and indicate critical path ( A – D – G )


(b) What is the total time required to complete the project
(c) If the project is to be completed in 9 days, what is the minimum cost
to be incurred ?
(d) What is the least cost schedule ?

Solution :
A B C D E F G H
- - - A A A B,D C,E

G
B
D 4 4
6

A F
1 2 5
3 7

C E H
2
2
6

Prepared by – Vinayanand Rele


Page 72 of 380 24/11/2008
Project Management

Paths Duration

1–3–5 = 10 ˜
1–2–5 = 10 —
1–4–5 = 5 š
1–2–4–5 = 8 ™
1–2–3–5 = 11 –

Maximum Crashing
Activity Cost Slope
Possible
1-2 3-2=1 70
1-3 6-5=1 60
1-4 2-1=1 80
2-3 4-3=1 50
2-4 2-1=1 80
2-5 7-4=3 120
3-5 4-3=1 80
4-5 3-2=1 50

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–2–3-5 11 / 10 / 9 / 8

1–2 1 70 ƒ ( iii )
2–3 1 50 ‚ (i)
3–5 1 80 „ ( ii )

— 1–2–5 10 / 10 / 9 / 8

1–2 1 70 ( iii )
2–5 /3 2 120 ( ii )

˜ 1–3-5 10 / 10 / 9 / 8

1–3 1 60 ( iii )
3–5 1 80 ( ii )

™ 1–2–4-5 8/8/8/8

1–2 1 70
2–4 1 80
4–5 1 50

Prepared by – Vinayanand Rele


Page 73 of 380 24/11/2008
Project Management

š 1–4-5 5/5/5/5

1–4 1 80
4–5 1 50

Step – i

On CP (–) Crash Activity 2 – 3 by 1 day.

– = 10
— = 10
˜ = 10

∴ New project duration will be 10 days, And ) in cost 1 x 50 = 50/-.


No other paths — & ˜ becomes critical.

Now there are 2 critical activities which are common on 2 paths, that is :

Activity 1 – 2 is common on CP (–) & CP (—)


3 – 5 is common on CP (–) & CP (˜)

So,

Option – 1.

If we crash on CP (–) & CP (—),

1 – 2 by 1 day, ) in cost Rs. 70/-


1 – 3 by 1 day, ) in cost Rs. 60/-
---------
130/-

Option – 2.

If we crash on CP (–) & CP (˜),

3 – 5 by 1 day, ) in cost Rs. 80/-


2 – 5 by 1 day, ) in cost Rs. 40/-
---------
120/-

As the cost is less on option 2, we prefer option 2.

Prepared by – Vinayanand Rele


Page 74 of 380 24/11/2008
Project Management

Step – ii

On CP (–) & CP (˜) 3 – 5 by 1 day,


CP (—) 2 – 5 by 1 day

New project duration 9 days.


) in cost Rs. 80/- + 40/- = 120/-

Note : Double crashing is not permitted and once a path is made critical it
should remain critical throughout.

No other path becomes critical.

Step – iii

On CP (–) & CP (—) Crash Activity 1 – 2 by 1 day and


CP (˜) Crash Activity 1 – 3 by 1 day

∴ New Project duration 8 days.

And ) in cost 1 x 90 + 1 x 60 = 130/-

Now since all activities on CP (–) are crashed, therefore Crashing is over.

Conclusion :

Normal Path Duration = 11 Days


Normal Cost = Rs. 1,300/-
Crash Path Duration = 8 Days
Crash Cost =

1,300 /-
+ 50 /-
+ 120 /-
+ 130 /-
--------------
1,600 /-

Prepared by – Vinayanand Rele


Page 75 of 380 24/11/2008
Project Management

Problem - 7

Normal Crash time and Cost are given below for a plant expansion project.

Preceding Normal
Activity Normal Time Crash Time Cost Crash Cost
Activity
( Months ) ( Months ) ( Rs 000 ) ( Rs 000 )
A - 3 2 40 50
B A 6 4 200 300
C - 3 2 20 35
D C 2 1 20 32
E A 1 1 20 20
F D 5 3 150 190
G D,E 7 6 120 150
H B,F,G 4 3 160 195

If the company has Rs. 7,76,000/- available for this project, how should the funds be
allocated to minimize overall completion time, to the nearest 0.1 month ? What is the
minimum completion time ?

Solution :

A B C D E F G H
- A - C A D D,E B,F,G

B
A E
3 1 6

G H
1 5 6 7
4
7
C
F
3 D0 0
5
D
3 4
2

Prepared by – Vinayanand Rele


Page 76 of 380 24/11/2008
Project Management

Total available paths are

Paths Duration

1–2–5–6-7 = 15 —
1–2–6-7 = 13 ™
1 – 3 – 4- 5 – 6 - 7 = 16 – Critical Path
1–3–4–6–7 = 14 ˜

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–3–4–5–6-7 16 / 15 / 14 / 13.7

1–3 1 15 ƒ ( ii )
3–4 1 12 ‚ (i)
4–5 - -
5–6 /
1 0.7 30 „ ( iii )
6–7 1 35 …

— 1–2–5–6-7 15 / 15 / 14 / 13.7

1–2 1 10 ( ii )
2–5 - -
5–6 /
1 0.7 30 ( iii )
6–7 1 35

˜ 1–3-4–6-7 14 / 14 / 12 / 12

1–3 1 60 ( ii )
3–4 1 80
4–6 2 60
6–7 1 60

™ 1–2–6-7 13 / 13 / 13 / 13

1–2 1 10
2–6 2 50
6–7 1 35

Prepared by – Vinayanand Rele


Page 77 of 380 24/11/2008
Project Management

Step – i

On CP (–) Crash Activity 3 – 4 by 1 month.

∴ New project duration will be 15 months,


And ) in cost 1 x 12,000 = 12,000/-.

Leftover is 46,000 – 12,000 = 34,000

Now path — also becomes critical.

Now there are two options.

Option – 1.

If we crash Un common activities that is,

Crash on CP (–) activity C ( 1 – 3 ) by 1 month and


on CP (—) activity A ( 1 - 2 ) by 1 month

) in cost will be 1 x 15,000 + 1 x 10,000 = 25,000/-

Option – 2.

If we crash common activities that is,

Crash on CP (–) & CP (—) activity C ( 6 – 7 ) by 1 month.

) in cost will be 1 x 35,000 = 35,000/-

So option 1 is preferred.

Step – ii

On CP (–) activity C ( 1 – 3 ) by 1 month and


CP (—) activity A ( 1 - 2 ) by 1 month

New project duration 14 Months


) in cost will be 1 x 15,000 + 1 x 10,000 = 25,000/-

No other path becomes critical.

Now leftover fund will be 34,000 – 25,000 = 9,000/-

Prepared by – Vinayanand Rele


Page 78 of 380 24/11/2008
Project Management

Step – iii

Now activity G ( 5 – 6 ) has the least cost slope and which is common to both
critical paths.

But for crashing 5 – 6 by 1 month ) in cost will be Rs 30,000/- however


leftover fund is Rs. 9,000/-.

9,000
So 1 month x ---------- = 0.3 months
30,000

So crash 5 – 6 by 0.3 months

∴ New Project duration 13.7 months.

And ) in cost 9,000/-

Now since No fund is available for crashing, no further crashing is possible.

Conclusion :

Normal Path Duration = 16 months


Normal Cost = Rs. /-
Crash Path Duration = 13.7 months
Leftover fund is nil

Prepared by – Vinayanand Rele


Page 79 of 380 24/11/2008
Project Management

Problem – 8

The time-cost estimates for the various activities of a project are given below :

Preceding Time ( In weeks ) Cost ( In Rs )


Activity
Activity
Normal Crash Normal Crash
A - 8 6 8,000 10,000
B - 7 5 6,000 8,400
C A 5 4 7,000 8,500
D B 4 3 3,000 3,800
E A 3 2 2,000 2,600
F D.E 5 3 5,000 6,600
G C 4 3 6,000 7,000

The project manger wishes to complete the project in the minimum possible time.
However he is not authorised to spend more than Rs. 5,000/- on crashing.

Suggest the least – Cost schedule for achieving the objective of the project manager.
Assume that there is no indirect or utility cost.

Solution :

A B C D E F G
- - A B A D,E C

4
G
C
4
5 6
2
E F
A
3 5
8
5
1
B D
7 4
3

Prepared by – Vinayanand Rele


Page 80 of 380 24/11/2008
Project Management

Total available paths are

Paths Duration

1–2–4–6 = 17 – Critical Path


1–2–5-6 = 16 —
1–3–5-6 = 16 ˜

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–2–4–6 17 / 16 / 15 / 14

A 1–2 /2 1 1,000 ‚ ( ii ) ( iii )


C 2–4 1 1,500 „
G 4–6 1 1,000 ƒ (i)

— 1–2–5–6 16 / 16 / 15 / 14

A 1–2 /
2 1 1,000 „ ( ii ) ( iii )
E 2–5 1 600 ‚
F 5–6 1 300 ƒ

˜ 1–3-5–6 16 / 16 / 15 / 14

B 1–3 1 1,200 „ ( iii )


D 3–5 1 800 ‚ ( ii )
F 5–6 2 800 ƒ

We can crash either A or C as cost slope are disadvantage of A. Only part crashing can
crash only by 1 day. – & — become critical advantage of G all 3 becomes critical and
more combination allowed full crashing possible.

Step – i

On CP (–) Crash Activity G ( 4 – 6 ) by 1 week.

∴ New project duration will be 16 weeks,


And ) in cost 1 x 1,000 = 1,000/-.

Now path — & ˜ also becomes critical. Leftover fund will be Rs, 4000/-

Prepared by – Vinayanand Rele


Page 81 of 380 24/11/2008
Project Management

Now there are two options.

Option - 1.

On CP (–) crash 1 – 2 by 1 week Rs 1,000/-


CP (˜) crash 3 – 5 by 1 week Rs 800/-
-----------
1,800/-
Option - 2.

On CP (—) crash 5 – 6 by 1 week Rs 800/-


CP (˜) crash 2 – 4 by 1 week Rs 1,500/-
-----------
2,300/-

So choose option 1.

Step – ii

On CP (–) activity C ( 1 – 2 ) by 1 week and


CP (—) activity A ( 3 - 5 ) by 1 week

New project duration 15 weeks


) in cost will be Rs. 1800 /-

Now leftover fund will be Rs 4,000 – Rs 1,800 = Rs 2,200/-

Now again we have two options.

Option - 1.

On CP (–) crash 1 – 2 by 1 week Rs 1,000/-


CP (˜) crash 1 – 3 by 1 week Rs 1,200/-
-----------
2,200/-
Option - 2.

On CP (—) crash 5 – 6 by 1 week Rs 800/-


CP (˜) crash 2 – 4 by 1 week Rs 1,500/-
-----------
2,300/-

So option 1 is suitable.

Prepared by – Vinayanand Rele


Page 82 of 380 24/11/2008
Project Management

Step – iii

CP (–) crash 1 – 2 by 1 week


CP (˜) crash 1 – 3 by 1 week

∴ New Project duration 14 weeks.

And ) in cost 2,200/-

Now since No fund is available for crashing, no further crashing is possible.

Conclusion :

Prepared by – Vinayanand Rele


Page 83 of 380 24/11/2008
Project Management

1st March, 2008.

Lecture – VI.

Problem - 9

The table below gives durations, costs of activities of a project.

Time in days Cost in Rs.


Activity
Normal Crash Normal Crash
1 - 2 2 1 100 150
1 - 3 8 5 150 210
2 - 4 4 3 200 280
3 - 4 1 1 70 70
3 - 5 2 1 80 150
4 - 6 5 3 100 190
5 - 6 6 2 120 360

(a) Draw a network for the project and determine the critical path
(b) What are the normal project duration and the associated cost ?
(c) Crash the activities of the project to find the minimum cost and the
corresponding duration given that indirect cost per day is Rs. 40/-.

Solution :

4
2
4
1
5
4 1
6
3

2 6
5

Total available paths are

Paths Duration

1–2–4–6 = 11 ˜
1–3–4-6 = 14 —
1–3–5-6 = 16 – Critical Path

Prepared by – Vinayanand Rele


Page 84 of 380 24/11/2008
Project Management

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–3–5–6 16 / 13 / 15 / 14

1–3 3 20 ‚ (i)
3–5 1 70 ƒ
5–6 4 60 „

— 1–3–4–6 14 / 13 / 15 / 14

1–3 3 20 ƒ ( ii ) ( iii )
3–4 - -
4–6 2 25 ‚

˜ 1–2-4–6 11 /

1–2 ( iii )
2–4 ( ii )
4–6

Duration
Direct Cost Indirect Cost Total Cost
Days
16 820 16 x 40 = 640 1460
15 820 + 20 ( 1 – 3) = 840 15 x 40 = 600 1440
14 840 + 20 ( 1 – 3) = 860 14 x 40 = 560 1420
13 860 + 20 ( 1 – 3) = 880 13 x 40 = 520 1400
12

In complete problem.

Prepared by – Vinayanand Rele


Page 85 of 380 24/11/2008
Project Management

Problem - 10

The detailed activities in building project are given below :

Preceding Normal Crash


Activity
Activity
Time ( In Days) Cost ( In Rs ) Time ( In Days) Cost ( In Rs )
A - 9 12,000 6 18,000
B A 14 14,000 4 24,000
C A 4 2,000 3 2,400
D C 6 44,000 4 56,000
E - 14 1,600 13 1,800
F E 6 4,000 6 4,000
G B,C 5 4,000 3 4,800
H F,G 2 12,000 1 14,000

(i) Obtain critical Path


(ii) Indirect Cost Per day Rs. 5,000/-
(iii) Find the Minimum time schedule and corresponding cost.

Prepared by – Vinayanand Rele


Page 86 of 380 24/11/2008
Project Management

Problem - 11

A Small marketing project consists of the jobs in the table given below. With each job is
listed its normal time and minimum or crash time (in days). The cost (in Rupees per day)
of crashing each job is also given.

Minimum
Normal Cost of
( Crash )
Job Duration Crashing
Duration (
( Days ) ( Rs. Per Day )
Days )
1 - 2 9 6 20
1 - 3 8 5 25
1 - 4 15 10 30
2 - 4 5 3 10
3 - 4 10 6 15
4 - 5 2 1 40

(a) What is the normal project length and the minimum project length ?
(b) Overhead costs total Rs. 35/- per day, what is the optimal length schedule ?

Solution :

5
9

1 4 5
15 2

10
8

Total available paths are

Paths Duration

1–2–4–5 = 16 ˜
1–4-5 = 17 —
1–3–4-5 = 20 – Critical Path

Prepared by – Vinayanand Rele


Page 87 of 380 24/11/2008
Project Management

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–3–4–5 20 / 17 / 16 / 15 / 12

1–3 3 25 ƒ ( iv )
3–4 /
4 1 15 ‚ ( i ) ( iii )
4–5 1 40 „ ( ii )

— 1–4–5 17 / 17 / 16 / 15 / 12

1–4 / /
5 4 1 30 ‚ ( iii ) ( iv )
4–5 1 40 ƒ ( ii )

˜ 1–2-4–5 16 / 16 / 15 / 15 / 12

1–2 /32 2 20 ƒ ( iv )
2–4 10 ‚ ( iv )
4–5 1 40 „ ( ii )

Step – i

On CP (–) Crash Activity 3 – 4 by 3 days.

∴ New project duration will be 17 days,


And ) in cost 3 x 15 = Rs 45/-.

Now path — also becomes critical.

Step – ii

On Both Critical Paths crash activity 4 – 5 by 1 day.

New project duration 16 days.


) in cost will be Rs. 1 x 40 = Rs 40/-

No other Path becomes critical.

Prepared by – Vinayanand Rele


Page 88 of 380 24/11/2008
Project Management

Step – iii

CP (–) crash 3 – 4 by 1 day


CP (—) crash 1 – 4 by 1 day

∴ New Project duration 15 weeks.


And ) in cost will be 1 x 15 + 1 x 30 = Rs 45/-

Now path ˜ also becomes critical.

Step – iv

On CP (–) Crash Activity 1 – 3 by 3 days &


CP (—) Crash Activity 1 – 4 by 2 days &
CP (˜) Crash Activity 2 – 4 by 2 days &
CP (˜) Crash Activity 1 – 2 by 1 day

∴ New Project duration 12 days.

And ) in cost 3 x 25 + 3 x 30 + 2 x 10 + 1 x 20 = Rs 205/-.

Now since all activities on CP (–) are crashed, Crashing is over.

Conclusion :

Normal Path Duration = 20 days


Normal Cost = Rs. 5,000/- ( Around )
Crash Path Duration = 12 days.
Crash Path Cost =
5,000 /-
+ 45 /-
+ 40 /-
+ 45 /-
+ 205 /-
--------------
5,335 /-

In step 4 we did 3 days crashing from 15 to 12 days.

Prepared by – Vinayanand Rele


Page 89 of 380 24/11/2008
Project Management

15 to 14 Days

On CP (–) 1–3 1 25/-


CP (—) 1–4 1 30/-
CP (˜) 2–4 1 10/-
-------
65/-
14 to 13 Days

On CP (–) 1–3 1 25/-


CP (—) 1–4 1 30/-
CP (˜) 2–4 1 10/-
-------
65/-
13 to 12 Days

On CP (–) 1–3 1 25/-


CP (—) 1–4 1 30/-
CP (˜) 1–2 1 20/-
-------
75/-

Duration
Steps Direct Cost Indirect Cost Total Cost
Days
20 5000 ( around ) 35 x 20 = 700 5700
19 5000 + 15 ( 3 – 4 ) = 5015 35 x 19 = 665 5680
i 18 5015 + 15 ( 3 – 4 ) = 5030 35 x 18 = 630 5660
17 5030 + 40 ( 4 – 5 ) = 5045 35 x 17 = 595 5640 ”
ii 16 5000 + 45 ( 4 – 5 ) = 5085 35 x 16 = 560 5645
15 5085 + 45 ( 3 – 4 ) 15
iii ( 1 – 4 ) 30 = 35 x 15 = 525 5655
5030
14 5130 + 65 ( 1 – 3 ) 25
( 1 – 4 ) 30
35 x 14 = 490 5685
( 2 – 4 ) 10 =
5195
13 5195 + 65 ( 1 – 3 ) 25
( 1 – 4 ) 30
iv 35 x 13 = 455 5715
( 2 – 4 ) 10 =
5260
12 5260 + 75 ( 1 – 3 ) 25
( 1 – 4 ) 30
35 x 12 = 420 5755
( 1 – 2 ) 20 =
5335

Prepared by – Vinayanand Rele


Page 90 of 380 24/11/2008
Project Management

Optimum cost is 5,640/-

Optimum duration = 17 days.

Prepared by – Vinayanand Rele


Page 91 of 380 24/11/2008
Project Management

Problem - 12

List of activities for constructing canteen in a factory is given below with other relevant
details. Job A must precede all other jobs while Job E must follow all other jobs apart
from the jobs can run concurrently.

Normal Crash
Code Job Description
Duration Cost Duration Cost
( Days ) ( Rs. ) ( Days ) ( Rs. )
A Lay foundation & build Walls 5 3000 4 4000
B Tile roofing 6 1200 2 2000
C Install Electricity 4 1000 3 1800
D Installl Plumbing 5 1200 3 2000
E Connect sevices to Finish 3 1000 3 1600

i) Draw the Network & identify critical Path

ii) Crash the Network fully to find out minimum duration

iii) If indirect costs are Rs 300/- per day. Determine time – Cost trade off for the
project.

Solution :

A B C D E
- - A A B,C,D

3
D1
B
0
6
A E
C
1 2 5 6
5 3
4
D
D2
5
0

Prepared by – Vinayanand Rele


Page 92 of 380 24/11/2008
Project Management

Paths Duration

1–2–5–6 = 12 ˜
1–2-3 –5–6 = 14 – Critical Path
1–2-4–5–6 = 13 —

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–2-3–5–6 14 / 13 / 12 / 11 / 10

1–2 1 1000 ƒ ( iii )


2–3
3–5
/ / /
4 3
-
2 200
-
‚ ( i ) ( ii ) ( iv )
( ii )
5–6 - -

— 1–2-4–5–6 13 / 13 / 12 / 11 / 10

1–2 1 1000 ƒ ( iii )


2–4 / /
2 1 400 ‚ ( ii ) ( iv )
4–5 - -
5–6 - -

˜ 1–2-5–6 12 / 12 / 12 / 11 / 10

1–2 1 1000 ƒ ( iii )


2–5 1 800 ‚ ( iv )
5–6 - -

Step – i

On CP (–) Crash Activity 2 – 3 by 1 day.

∴ New project duration will be 13 days,


And ) in cost 1 x 200 = Rs 200/-.

Now path — also becomes critical.

Step – ii

On CP (–) Crash Activity 2 – 3 by 1 day.


CP (—) Crash Activity 2 – 4 by 1 day.

Prepared by – Vinayanand Rele


Page 93 of 380 24/11/2008
Project Management

New project duration 12 days.


) in cost will be Rs. 1 x 200 + 1 x 400 = Rs 600/-

Now all 3 paths are critical.

Step – iii

Crash on all paths activity 1 – 2 by 1 day

∴ New Project duration 11 days.


And ) in cost will be 1 x 1000 = Rs 1,000/-

Step – iv

On CP (–) Crash Activity 2 – 3 by 1 day &


CP (—) Crash Activity 2 – 4 by 1 day &
CP (˜) Crash Activity 3 – 5 by 1 day

∴ New Project duration 10 days.

And ) in cost 1 x 200 + 1 x 400 + 1 x 800 = Rs 1,400/-.

Now since all activities on CP (˜) are crashed, Crashing is over.

Conclusion :

Normal Path Duration = 14 days


Normal Cost = Rs. 8,000/-
Crash Path Duration = 10 days
Crash Cost = Rs. 11,200/-

Duration
Direct Cost Indirect Cost Total Cost
Days
14 8000 14 x 300 = 4,200/- 12,200
13 12,200 +
13 x 300 = 3,900/-
( 2 – 3 ) 200 = 14,400/-
12
11
10

Prepared by – Vinayanand Rele


Page 94 of 380 24/11/2008
Project Management

Problem - 13

The following tables gives the activities in a construction project and other relevant
information.

Immediate Time ( Days ) Direct Cost ( Rs )


Activity
Predecessors
Normal Crash Normal Crash
A - 4 3 60 90
B - 6 4 150 250
C - 2 1 30 60
D A 5 3 150 250
E C 2 2 100 100
F A 7 5 115 175
G D,B,E 4 2 100 240

Indirect Costs vary as follows :

Days 15 14 13 12 11 10 9 8 7 6
Cost ( Rs. ) 600 500 400 250 175 100 75 50 35 25

(a) Draw an arrow diagram for the project.


(b) Determine the project duration which will result in minimum total project cost.

Solution :

A B C D E F G
- - - A C A D,B,E

F
2 5
7
D
A G
5
4 4
B
1 4
6
C
E
2
2
3

Prepared by – Vinayanand Rele


Page 95 of 380 24/11/2008
Project Management

Paths Duration

1–2–4–5 = 13 – Critical Path


1–2-5 = 11 —
1–3-4–5 = 8 ™
1-4–5 = 10 ˜

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–2-4–5 13 / 12 / 10 / 10

1–2 1 30 ‚ (i)
2–4 2 50 ƒ ( ii )
4–5 2 70 „ ( iii )

— 1–2–5 11 / 10 / 10 / 10

1–2 1 30 ‚ (i)
2–5 2 30 ƒ ( iii )

˜ 1–4–5 10 / 10 / 10 / 10

1–4 2 50 ‚
4–5 2 70 ƒ ( iii )

Step – i

On CP (–) Crash Activity 1 – 2 by 1 day &


CP (—) Crash Activity 1 – 2 by 1 day

∴ New project duration will be 12 days,


And ) in cost 1 x 30 + 1 x 30 = Rs 60/-.

No other path becomes critical.

Step – ii

On CP (–) Crash Activity 2 – 4 by 2 days.

New project duration 10 days.


) in cost will be Rs. 2 x 50 = Rs 100/-

Now all 3 paths are critical.

Prepared by – Vinayanand Rele


Page 96 of 380 24/11/2008
Project Management

Step – iii

On CP (–) Crash Activity 4 – 5 by 2 days &


CP (—) Crash Activity 2 – 5 by 2 days

∴ New Project duration 8 days.


And ) in cost will be 2 x 70 + 2 x 30 = Rs 200/-

Conclusion :

Normal Path Duration = 13 days


Normal Cost = Rs. 705/-
Crash Path Duration = 8 days.
Crash Path Cost = Rs 1035/-

Duration
Direct Cost Indirect Cost Total Cost
Days
13 705 400 1105
12 705 + ( 1 – 2 ) 30 = 735 250 985
11 735 +

Prepared by – Vinayanand Rele


Page 97 of 380 24/11/2008
Project Management

7th March, 2008.

Lecture – VII.

Problem - 14

Consider the following activities, associated normal time and cost together with extra
cost of saving a day on selected activities.

Extra Cost of Reducing


Normal Cost of Normal Time in
Activity Normal Time by one Day
Activities Days
( Rs )

A to B 10000 4 3000
A to C 12000 6 2000
A to D 5000 2 800
B to C 6000 5 600
B to E 9000 2 2000
B to F 5000 7 900
C to D 4000 4 700
C to F 3000 3 200
D to F 5000 7 2200
E to F 6000 12 500

No single activity can be reduced by more than one day.


In addition site costs will be incurred at the rate of Rs. 3,500 for every day that the work
is in progress on the site irrespective of how many activities are in progress.

Calculate and state :

(a) The Critical path using normal times, the time taken and the total cost of
completing the project.

(b) The shortest time in which the project can be completed the associated cost and
the critical path.

(c) The lowest cost for which the project can be completed and associated time.

Prepared by – Vinayanand Rele


Page 98 of 380 24/11/2008
Project Management

Solution :

B E
8

10 6 12
5

A C F
7 3

4
9
7

Paths Duration

A–B–C–D–F = 26 –
A–B–C–F = 18 ˜ Critical Path
A–B-E–F = 25 —
A–B–F = 11
A–C-D–F = 18
A–C–F = 10
A–D–F =

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– A–B-C–D–F 26 / 25 / 24 / 23 / 22

A–B 1 3000 … ( iii )


B–C 1 600 ‚ (i)
C–D 1 700 ƒ ( ii )
D–F 1 2200 „ ( iv )

— A–B–E–F 25 / 25 / 24 / 23 / 22

A–B 1 3000 „ ( iii )


B–E 1 2000 ƒ ( iv )
E–F 1 500 ‚ ( ii )

Prepared by – Vinayanand Rele


Page 99 of 380 24/11/2008
Project Management

Step – i

On CP (–) Crash Activity B – C by 1 day &

∴ New project duration will be 25 days,


And ) in cost 1 x 600 = Rs 600/-.

Now both path will be critical.

Step – ii

On CP (–) Crash Activity C – D by 1 day &


CP (—) Crash Activity E – F by 1 day

∴ New project duration will be 24 days,


And ) in cost 1 x 700 + 1 x 500 = Rs 1,200/-.

No other path becomes critical.

Step – iii

On CP (–) & (—) Crash common Activity A – B by 1 day

∴ New Project duration 23 days.


And ) in cost will be 1 x 3000 = Rs 3,000/-

No other path becomes critical.

Step – iv

On CP (–) Crash Activity D – F by 1 day &


CP (—) Crash Activity B – E by 1 day

∴ New Project duration 22 days.


And ) in cost will be 1 x 2,200 + 1 x 2,000 = Rs 4,200/-

Now since all activities on CP (–) are crashed crashing is over.

Conclusion :

Normal Path Duration = 26 days


Normal Cost = Rs. 65,000/-
Crash Path Duration = 22 days.
Crash Path Cost = Rs 74,000/-

Prepared by – Vinayanand Rele


Page 100 of 380 24/11/2008
Project Management

Duration
Direct Cost Indirect Cost Total Cost
Days
26 65,000/- 26 x 3,500/- = 91,000/- 1,56,000/-
25 65000 +
25 x 3,500/- = 87,500/- 1,53,100/-
( B – C ) 600 = 65,600/-
24 65600 + ( C – D ) 700
+ ( E – F ) 500 24 x 3,500/- = 84,500/- 1,50,800/-
= 66,800/-
23
22

Optimum Duration is 23 Days.

Optimum Cost Rs 1,50,300/-

Prepared by – Vinayanand Rele


Page 101 of 380 24/11/2008
Project Management

Problem - 15

The time cost estimates of different activities of a project and their precedence
relationship are given below.

Preceding Time ( In weeks ) Cost ( Rs. )


Activity
Activity
Normal Crash Normal Crash
A - 6 4 10000 14000
B - 2 1 5000 8000
C A 4 3 4000 5000
D B 8 3 1000 6000
E B 14 6 9000 13000
F C,D 6 2 7000 8000

Overhead costs amount to Rs. 1,000 per week.

It is stipulated that the contractor will have to pay a penalty of Rs 2,000/- per week for
completing the project beyond 12 weeks.

(i) Draw the Network


(ii) What is the duration of the critical path ?
(iii) Crash the project so that the project including penalty is minimum.

Solution :

2
C
A
4
6

1 4
F
B
D 6
2
8
3 E
5
14

Prepared by – Vinayanand Rele


Page 102 of 380 24/11/2008
Project Management

Paths Duration

1–2–4–5 = 16 ˜
1–3–4–5 = 16 –
1–3–5 = 16 —

All 3 are the Critical Paths

Critical Activity Max Crashing Cost Rank Remarks


Available slope

– 1–2-4–5 16 / 12 / 11 / 9

1–2 2 2000 „ ( iii )


2–4 1 1000 ƒ ( ii )
4–5 4 250 ‚ (i)

— 1–3–4–5 16 / 12 / 11 / 9

1–3 1 3000 „
3–4 / /
5 4 2 1000 ƒ ( ii ) ( iii )
4–5 4 250 ‚ (i)

˜ 1–3–5 16 / 12 / 11 / 9

1–3 1 3000 ƒ
3–5 / / 3/
8 4 1 500 ‚ ( i ) ( ii ) ( iii )

Step – i

On CP (–) & CP (—) Crash Activity 4 – 5 by 4 weeks &


CP (˜) Crash Activity 3 – 5 by 4 weeks

∴ New project duration will be 12 weeks,


And ) in cost 4 x 250 + 4 x 500 = Rs 3,000/-.

Prepared by – Vinayanand Rele


Page 103 of 380 24/11/2008
Project Management

Step – ii

On CP (–) Crash Activity 2 – 4 by 1 week &


CP (—) Crash Activity 3 – 4 by 1 week &
CP (˜) Crash Activity 3 – 5 by 1 week

∴ New project duration will be 11 weeks,


And ) in cost 1 x 1000 + 1 x 1000 + 1 x 500 = Rs 2,500/-.

Step – iii

On CP (–) Crash Activity 1 – 2 by 2 weeks &


CP (—) Crash Activity 3 – 4 by 2 weeks &
CP (˜) Crash Activity 3 – 5 by 2 weeks

∴ New Project duration 9 weeks.


And ) in cost will be 2 x 2000 + 2 x 1000 + 2 x 500 x = Rs 7,000/-

Now since all the Activities on CP (–) are crashed crashing is over.

Conclusion :

Normal Path Duration = 16 weeks


Normal Cost = Rs. 36,000/-
Crash Path Duration = 9 weeks.
Crash Path Cost = Rs 36,000/-
+ 3,000/-
+ 2,500/-
+ 7,000/-
---------------
Rs 47,500/-

Prepared by – Vinayanand Rele


Page 104 of 380 24/11/2008
Project Management

Penalty @ Rs
2,000/- per
Duration Total
Direct Cost Indirect Cost week after
weeks Cost
delay of 12
Weeks
16 36,000/- ( 16 -12 ) = 4 Rs.
16 x 1,000/- =
weeks i.e. 60,000/-
16,000/-
Rs 8,000/-
15 36,000 + ( 15 -12 ) = 3 Rs.
15 x 1,000/- =
( 4 – 5 ) 250 + weeks i.e. 57,750/-
15,000/-
( 3 – 5 ) 500 = 36,750/- Rs 6,000/-
14 36,750 + ( 14 -12 ) = 2 Rs.
14 x 1,000/- =
( 4 – 5 ) 250 + weeks i.e. 55,500/-
14,000/-
( 3 – 5 ) 500 = 37,500/- Rs 4,000/-
13 37,500 + ( 13 -12 ) = 1 Rs.
13 x 1,000/- =
( 4 – 5 ) 250 + weeks i.e. 53,250/-
13,000/-
( 3 – 5 ) 500 = 38,250/- Rs 2,000/-
12 38,250 + Rs.
12 x 1,000/- =
( 4 – 5 ) 250 + 51,000/-
12,000/-
( 3 – 5 ) 500 = 39,000/-
11 39,000 + Rs.
( 2 – 4 ) 1000 + 11 x 1,000/- = 52,500/-
( 3 – 4 ) 1000 + 11,000/-
( 3 – 5 ) 500 = 41,500/-
10 41,500 + Rs.
( 1 – 2 ) 2000 + 10 x 1,000/- = 55,000/-
( 3 – 4 ) 1000 + 10,000/-
( 3 – 5 ) 500 = 45,000/-
9 45,000 + Rs.
( 1 – 2 ) 2000 + 9 x 1,000/- = 57,500/-
( 3 – 4 ) 1000 + 9,000/-
( 3 – 5 ) 500 = 48,500/-

Optimum Duration is 12 weeks


Optimum cost is Rs. 51,000/-

Prepared by – Vinayanand Rele


Page 105 of 380 24/11/2008
Project Management

Network

A Network is a graphic representation of all the tasks that must be completed to achieve
the end object of a project, showing their interdependence and interrelation. The
components, which make up a network are events and activities.

PERT

In 1958, the United States Navy needed a way to monitor and control the Prolaris
Missile Programme. It especially needed a method for minimizing the conflicts, delays
and interruptions that so frequently plague accomplish that, the Navy developed the
Program Evaluation and Review Technique (PERT).

ACTIVITY

An Activity is performance of work between any two events. It is a time consuming and
resource consuming element in a Network Plan. An Activity is represented by means of
an arrow.

DUMMY ACTIVITY

There is another component of Network, which is called ‘ZERO’ time activity. It is an


activity which consumes neither time nor resources. This is known as Dummy Activity. It
is represented by means of broken arrow in a Network Diagram.

CPM

E I DU PONT DE NUMERIOUR & CO a huge chemical company, sought to devise a


way to determine accurate time and cost estimates for the construction of several
chemical plants. The firm needed some way to ascertain whether work was falling
behind schedule at any given point in time and whether to action to bring the work back
on schedule. Between 1956 and 1958, it developed the famous Critical Path Method
(CPM).

EVENT

An event is specific definable accomplish in a project, recognizable at a particular


instant of time. An event does not consume either time or response. It is a point in time
and not a passage of time. Examples of events on a Project Network are either a
commencement point or a completion point of a task to be performed.

Prepared by – Vinayanand Rele


Page 106 of 380 24/11/2008
Project Management

RULES FOR DEVELOPING A NETWORK

1. An event can not occur until all the activities leading to it are completed.
2. An activity can not start unless and until its preceding event has occurred.
3. An event once having occurred can not occur again.
4. Time flows from left to right.
5. Arrow flows from left to right.
6. Every activity will have to be completed to reach end event of the Network.
7. Length of arrows has no significance and they do not represent the duration.

CPM PERT

i) CPM is activity oriented i) PERT is event oriented


ii) The duration of each activity is ii) PERT allows uncertainly in the
assumed to be constant. duration.
iii) A Single time estimates is established iii) In PERT each activity is assigned three
for each activity. time estimates i.e. optimistic, most
likely and pessimistic.
iv) CPM places dual emphasis on time iv) PERT is primarily concerned with time.
and cost and evaluates the trade-off It describes basic network technique
between project cost and project time. Which includes, Planning, Monitoring,
and control of Projects.
v) CPM is widely used in construction v) PERT is widely used in R & D Projects
projects.

Prepared by – Vinayanand Rele


Page 107 of 380 24/11/2008
Project Management

PERT

(1) Optimistic Time ( a or to ) :

This is the shortest time an activity can take to complete. For this estimate, no
provision for daily or setbacks are made. It represents an ideal estimates.

(2) Most Likely Time ( m or tm ) :

This refers to the time that would be expected to occur most often if the activity
where frequently repeated under exactly the same conditions. It assumes that
things go in a normal way with few setbacks. It is the modal time.

(3) Pessimistic Time ( b or tp ) :

This is the longest time the activity could take to finish. If everything went wrong
and abnormal situations prevailed, this would be the time estimate.

Using the values of a, b and m the expected time of various activities and their
standard deviations are calculated as follows. The times estimates are reduced
into a single expected time ( te ) with the weighted average formula.

a + 4m + b
t e
=
6

The standard deviation σ i of the completion time of an activity is calculated as


follows.

b−a
σ i
=
6

From this, the variance =


2 b−a  is calculated.
σ =
i
 6 
Once the expected time of the activities are obtained, the critical path of the
project network is determined using these time estimates. Having found the
critical path, the PERT methodology assumes that the sum of the mean times
and the summation of the variance of critical jobs would yield the expected
project duration and its variance.

Prepared by – Vinayanand Rele


Page 108 of 380 24/11/2008
Project Management

To solve the problem on PERT following steps are important.

Step - –

Arrange the activities in order of their events.

e.g. So write them as

1–2 1–2
2–4 2–3
5–6 2–4
2 – 3 ….. 5–6

Or
B 2

A
1 3
C

So write them as,

B1–2
A1–3
C1–4

Step - —

Arrange 3 time estimates in order of a /m/b

Step - ˜

Compute
a + 4m + b 2
and σ =
b−a 
t
 6 
e
=
6 i

for each activity ( prepare table )

Step - ™

Draw Network considering the te value of each activity find ONLY critical path.
Compute expected project completion time ( t ) & Standard deviation ( s )

Prepared by – Vinayanand Rele


Page 109 of 380 24/11/2008
Project Management

Problem – 1

The following table gives the relevant data of the activities in a PERT project.

(i) Draw an arrow diagram of the project.


(ii) Calculate the Expected Duration and Variance of the critical path.
(iii) Assess the probability that the project will take more than 41 days.
(iv) What is the Probability that project will be completed in 31 days or less time ?

Duration ( Days )
Activity Optimistic Most Likely Pressimistic
1 - 2 3 6 15
7 - 8 4 19 28
2 - 3 6 12 30
4 - 5 3 6 15
3 - 5 5 11 17
5 - 8 1 4 7
1 - 6 2 5 14
2 - 4 2 5 8
6 - 7 3 9 27

Solution :
2

a + 4m + b 2
b− a 
σi  6 
=
Duration ( Days ) t e
=
6
Activity a m b
1 - 2 3 6 15 7 4
1 - 6 2 5 14 6 4
2 - 3 6 12 30 14 16
2 - 4 2 5 8 5 1
3 - 5 5 11 17 11 4
4 - 5 3 6 15 7 4
5 - 8 1 4 7 4 1
6 - 7 3 9 27 11 16
7 - 8 4 19 28 8 16

Prepared by – Vinayanand Rele


Page 110 of 380 24/11/2008
Project Management

11
14

2 5

7 5
7
4 4
1

6 7 8
11 18

Paths Duration

1–2–3–5–8 = 36 Critical Path


1–2–4–5-8 = 23
1–6–7–8 = 35

2
Critical Activity te σi

1–2 7 4
2–3 14 16
3–5 11 4
5–8 4 1
---------- ------------
2
t = 36 σ = 25
i

Expected project completion time = t = 36

2
Variance of the Critical path = σ = 25
i

Standard deviation of Critical path = s = 25 = 5 Days

Prepared by – Vinayanand Rele


Page 111 of 380 24/11/2008
Project Management

t = 36
s= 5

Now let x be the project duration.

P (x > 41 )

x−µ x − 36
Z= =
σ 5

So when x = 41

41 − 36
z= =1
5

∴ P ( x > 41 ) = P ( z > 1 )
Now 1 will lye on the right side of the bell curve.

P1

P2

Now P1 + P2 = 0.5

P2 = 0.5 – 0.3413
= 0.1587

∴ P ( x > 41 ) = 0.1587
= 15.87 %

∴ There is 16 % chance that project will be extended.

Prepared by – Vinayanand Rele


Page 112 of 380 24/11/2008
Project Management

Same way what is the probability that the project will be completed by 31 days.

∴ P ( x ≤ 31 )

x−µ x − 36
Z= =
σ 5

So when x = 31

31 − 36
z= = -1
5

∴ P ( x ≤ 41 ) = P ( z ≤ -1 )

P1

P2

Now P1 + P2 = 0.5

P2 = 0.5 – 0.3413
= 0.1587

∴ P ( x > 41 ) = 0.1587
= 15.87 %

∴ Project may be competed in 31 days has16 % chance.

Prepared by – Vinayanand Rele


Page 113 of 380 24/11/2008
Project Management

12th March, 2008.

Lecture – VIII.

Problem - 2

The data for PERT network is displayed in the table. Determine the critical path and the
expected duration of completion of the entire project.

Give Answers to the Followings :

(i) What is the probability that the project will exceed 60 days ?
(ii) What is the chance of completing the project between 45 days and 54 days ?
(iii) If it becomes known later that the duration of the three time estimates for
activity 4 – 6 has to be revised to 14-20-32. What impact does this have on
project completion time? What is the probability that the project can now be
completed on or before 46 days ?

Time Duration ( Days )


Activity a b c
1 - 2 2 4 6
1 - 3 6 6 6
1 - 4 6 12 24
2 - 3 2 4 8
2 - 5 11 14 23
3 - 4 15 24 45
3 - 6 3 6 9
3 - 6 9 15 27
5 - 6 4 10 16

( a = optimistic, b = most likely, c = pessimistic )

Prepared by – Vinayanand Rele


Page 114 of 380 24/11/2008
Project Management

Solution :

a + 4m + b σ 2
b− a 
 6 
=
Duration ( Days ) t e
=
6
i

Activity a m b
1-2 2 4 6 4 4/9
1-3 6 6 6 6 0
1-4 6 12 24 17 9
2-3 2 5 8 5 1
2-5 11 14 23 15 4
3-4 15 24 45 26 25
3-6 3 6 9 6 1
4-6 9 15 27 16 9
5-6 4 10 16 10 4

2 5
15

5 10
4

1 3 6
6 6

26
13 16

Paths Duration

1–2–3–4–6 = 51 Critical Path


1–2–3–6 = 15
1–2–5–6 = 29
1–3–4–6 = 48
1–3–6 = 12
1–4–6 = 29

Prepared by – Vinayanand Rele


Page 115 of 380 24/11/2008
Project Management

2
Critical Activity te σ i

1–2 4 4/9
2–3 5 1
3–4 26 25
4–6 16 9
---------- ------------
2
t = 51 σ = 35.44
i

t = 51

s= 35,44 = 5.95

So let the t = 51 & s = 5.95


Expected project duration t = 51 days.

Standard diviation of the Critical Path is 5.95 days

(i) Find probability that Project Duration exceeds 60 days.

Now let x be the project duration.

P (x > 60 )

x−µ x − 51
Z= =
σ 5.95

So when x = 60

60 − 51
z= = 1.51
5.95
P1 = 0.4345
∴ P ( x > 60 ) = P ( z > 1.51 )

P2 = 1.51

Prepared by – Vinayanand Rele


Page 116 of 380 24/11/2008
Project Management

As 1.51 will left side ( Table value 0.4345 )

Now we have P1 + P2 = 0.5

P2 = 0.5 – 0.4345
= 0.0655

So probability

P ( x > 60 ) = 0.0655
= 6.55 %

(ii) Find probability that Project gets completed between 45 and 54 Days.

Now let x be the project duration.

Let P ( 45 ≤ x ≤ 54 )

x−µ x − 51
Z= =
σ 5.95

So when x = 45

45 − 51
z= = -1.01
5.95

So when x = 54

54 − 51
z= = 0.50
5.95

∴ P ( 45 ≤ x ≤ 54 ) = p ( -1.01 ≤ z ≤ 0.50 )

P1 = 0.1915
P2 = 0.3438

0 Z = 0.5
Z = -1.01

Prepared by – Vinayanand Rele


Page 117 of 380 24/11/2008
Project Management

∴ The required probability

= 0.3438 + 0.1915
= 0.5353
= 53.53 %

(iii) Sensitivity Analysis.

Please note that the activity 4 – 6 is on the Critical path.

a + 4 m + b σ2 b− a 
 6 
=
Duration ( Days ) t e
=
6
i

Activity a m b
4-6 9 15 27 16 9 old
14 20 32 21 9 New

Now

2
Critical Activity te σ i

1–2 4 4/9
2–3 5 1
3–4 26 25
4–6 21 9
---------- ------------
2
t’ = 56 σ = 35 + 4/9
i

t’ = 56

s’ = 35.44 = 5.95

Now what is the probability that project can now be completed on or before 46 days ?

Let P ( x ≤ 46 )

x−µ x − 56
Z= =
σ 5.95

Prepared by – Vinayanand Rele


Page 118 of 380 24/11/2008
Project Management

46 − 56
Z= = - 1.68
5.95

So p ( x ≤ 46 ) = p ( x ≤ -1.68 )

P1

P2

Z = -1.68 0

P2 = 0.5 – 0.4535
= 0.465

p ( x ≤ 46 ) = 0.465

= 4.65 %

Prepared by – Vinayanand Rele


Page 119 of 380 24/11/2008
Project Management

Problem - 3

A project is characterized by the following activity time :

Optimistic Time Pessimistic Most Likely


Activity
to Days Time to Days Time to Days

1 - 2 1 5 3
1 - 3 3 7 5
2 - 4 4 8 10
3 - 4 9 11 3
3 - 5 1 5 12
4 - 5 10 20 5
4 - 6 5 13 6
5 - 6 5 9 5.5

a) Find the critical path and the project completion time (34 days)
b) Find the standard deviation of the expected project length (1.94)
c) What is the probability that the project will be completed in 35 days. (69.85 %)
d) What is the expected project completion time if you are allowed to qualify the
same with a chance of 95%. (37.18 Days)

Solution :

a + 4 m + b σ2 b− a 
 6 
=
Duration ( Days ) t e = i

Activity a m b
6
1 - 2 1 3 5 3 0.44
1 - 3 3 5 7 5 0.44
2 - 4 4 6 8 6 0.44
3 - 4 9 10 11 10 0.11
3 - 5 1 3 5 3 0.44
4 - 5 10 12 20 13 2.78
4 - 6 5 6 13 7 1.78
5 - 6 5 5.5 9 6 0.44

Prepared by – Vinayanand Rele


Page 120 of 380 24/11/2008
Project Management

2
6
3

4
1 7
10
5
13 6
3

3 6
5

Paths Duration

1–2–4–6 = 16
1–2–4–5–6 = 28
1–3–4–6 = 22
1–3–4–5–6 = 34 Critical Path
1–3–5–6 = 14

2
Critical Activity te σ i

1–3 5 0.44
3–4 10 0.11
4–5 13 2.78
5–6 6 0.44
---------- ------------
2
t = 34 σ = 1.94 days
i

(i) Find probability that Project will be completed in 35 days.

Now let x be the project duration.

P (x ≤ 35 )

x−µ x − 34
Z= =
σ 1.96

So when x = 35

35 − 34
z= = 0.52
1.96

Prepared by – Vinayanand Rele


Page 121 of 380 24/11/2008
Project Management

∴ P ( x ≤ 35 ) = P ( z ≤ 0.52 )

P1
P1 = 0.1985
P2 = 0.5

0 Z = 0.52

∴ Required probability
= 0.5 + 0.1985
= 0.6985
= 69.85 %

Note : If the problem says that what is the probability that project gets completed
on 35th Day then the answer is Zero.

(ii) What is the expected project completion time if you are allowed to qualify the
same with a chance of 95%

Now let x be the project duration.

P (x ≤ K ) = 0.95

0.95
- 0.50 Standard Deduction
----------
0.45

Z = 1.64

x − 34
Z=
1.94

Prepared by – Vinayanand Rele


Page 122 of 380 24/11/2008
Project Management

x − 34
∴ 1.64 =
1.94

x – 34 = 1.94 x 1.64

x = 37.18

So chance that 95 % the project will be completed in 37.18 days.

Prepared by – Vinayanand Rele


Page 123 of 380 24/11/2008
Project Management

Problem - 4

A small project is composed of eight activities whose time estimate are given below :

Duration ( Days )
Activity
Pressimistic Most Likely Optimistic
1 - 2 21 7.5 3
1 - 3 27 8 3
2 - 4 8 8 8
2 - 5 3.5 2 0.5
3 - 5 10 10 10
4 - 5 1.7 1 0.3
4 - 8 9 7.5 3
5 - 6 5 3 1

i) Draw the project network and identify all paths through it.
ii) What is the expected project completion time? (24 weeks)
iii) What is the expected project completion time with a confidence of 90 %.

Solution :

a + 4m + b σ2 b− a 
 6 
=
Duration ( Days ) t e = i

Activity a m b 6
1-2 3 7.5 21 9 9
1-3 3 8 27 10 16
2-4 8 8 8 8 0
2-5 0.5 2 3.5 2 0.25
3-5 10 10 10 10 0
4-5 0.3 1 1.7 1 0.05
4-6 3 7.5 9 7 1
5-6 1 3 5 3 0.44

Prepared by – Vinayanand Rele


Page 124 of 380 24/11/2008
Project Management

4
7

8
1 6
2

2 3
9
5
1

10 10
3

Paths Duration

1–2–4–6 = 24 Critical Path


1–2–4–5–6 = 21
1–2–5–6 = 15
1–3–5–6 = 23

2
Critical Activity te σ i

1–2 9 9
2–4 8 0
4–6 7 1
---------- ------------
2
t = 24 σ = 10 days
i

Standard deviation of Critical path = s = 10 = 3.16 Days

(ii) What is the expected project completion time with a confidence of 90 %.

Now let x be the project duration.

P (x ≤ K ) = 0.90

0.90
- 0.50 Standard Deduction
----------
0.40

Prepared by – Vinayanand Rele


Page 125 of 380 24/11/2008
Project Management

Z = 1.28

x − 24
Z=
3.16

x − 24
∴ 1.28 =
3.16

x – 24 = 3.16 x 1.28

x = 28.04

So chance that 90 % the project will be completed in 28.04 days.

Prepared by – Vinayanand Rele


Page 126 of 380 24/11/2008
Project Management

Problem – 13 ( University Paper )

A project consists of eight activities with following relevant information.

Immediate Estimated Duration ( Days )


Activity
Predecessor Optimistic Pessimistic Most likely
A - 2 4 3
B - 8 8 8
C - 7 11 9
D A 6 6 6
E B 10 18 14
F C 4 6 5
G D,E 1 1 1
H F,G 3 5 4

i) Draw the PERT network and find expected project completion time.
ii) What duration will have 97.7% chance of completion ?

( Area from Z = 0 to Z = 2 is 0.477 )

Solution :

a + 4m + b σ 2 b− a 
 6 
=
Duration ( Days ) t e
=
6
i

Activity a m b
A 2 3 4 3 0
B 8 8 8 8 0
C 7 9 11 9 0
D 6 6 6 6 0.00
E 10 14 18 14 2
F 4 5 6 5 0.11
G 1 1 1 1 0
H 3 4 5 4 0.11

A B C D E F G H
- - - A B C D,E F,G

Prepared by – Vinayanand Rele


Page 127 of 380 24/11/2008
Project Management

3
E
B
14
8

A G
D H
1 2 5 6 7
3 6 1 4

C F
9
5

Paths Duration

1–3–5–6–7 = 27 Critical Path


1–2–5-6–7 = 14
1–4–6–7 = 18

2
Critical Activity te σ i

1–3 8 0
3–5 14 2
5–6 1 0
6–7 4 0.11
---------- ------------
2
t = 27 σ = 2.11 days
i

Standard deviation of Critical path = s = 2.11 = 1.45 Days

Now let x be the project duration.

P (x ≤ K ) = 0.9770

0.9770
- 0.5000 Standard Deduction
-------------
0.4770

Prepared by – Vinayanand Rele


Page 128 of 380 24/11/2008
Project Management

Z = 2

x − 27
Z=
1.45

x − 27
∴ 2 =
1.45

x – 27 = 2 x 1.45

x = 29.9

So chance that 97.7 % the project will be completed in 29.9 days.

Prepared by – Vinayanand Rele


Page 129 of 380 24/11/2008
Project Management

Problem – 14 ( University Paper )

A project has the following activities and other characteristics.

Immediate Estimated Duration ( Days )


Activity
Predecessor Optimistic Pessimistic Most likely
A - 2 14 2
B - 2 14 3
C - 4 16 4
D A 2 2 2
E B 4 28 10
F C 4 16 10
G D,E 6 30 12
H F,G 2 26 8

i) Draw the PERT network and identify the critical path.


ii) Find the expected duration and variance of the project.
iii) Find the probability that the project duration will exceed 36 days
iv) What is the expected project completion time with a chance of 90%?.

Solution :

a + 4m + b σ2 b− a 
 6 
=
Duration ( Days ) t e = i

Activity a m b
6
A 2 2 14 4 4
B 2 8 14 8 4
C 4 4 16 6 4
D 2 2 2 2 0
E 4 10 28 12 16
F 4 10 16 10 4
G 6 12 30 14 16
H 2 8 26 10 16

A B C D E F G H
- - - A B C D,E F,G

Prepared by – Vinayanand Rele


Page 130 of 380 24/11/2008
Project Management

3
E
B
12
8

A G
D H
1 2 5 6 7
4 2 14 10

C F
6
10

Paths Duration

1–3–5–6–7 = 44 Critical Path


1–2–5-6–7 = 30
1–4–6–7 = 26
2
Critical Activity te σ i

1–3 8 4
3–5 12 16
5–6 14 16
6–7 10 16
---------- ------------
2
t = 44 σ = 52 days
i

Standard deviation of Critical path = s = 52 = 7.21 Days

Now let x be the project duration.

P (x > 36 )

x−µ x − 44
Z= =
σ 7.21

So when x = 60

36 − 44
z= = -1.11
7.21
P1 = 0.4345

Prepared by – Vinayanand Rele


Page 131 of 380 24/11/2008
Project Management

P2 = 0.5
P1 = 0.3685

0
Z = -1.11

∴ Required probability
Now we have P1 & P2

P2 = 0.5 + 0.3685
= 0.8665

So probability

P ( x > 36 ) = 0.8665
= 86.65 %

(iv) P (x ≤ K ) = 0.90

0.90
- 0.50 Standard Deduction
-------------
0.40

Z = 1.28

x − 44
Z=
7.21
x − 44
∴ 1.28 =
7.21

x – 44 = 1.28 x 7.21

x = 53.23

So chance that 90 % the project will be completed in 53.23 days.

Prepared by – Vinayanand Rele


Page 132 of 380 24/11/2008
Project Management

Problem – 5

A project is composed of eight activities whose time estimates are given below :

Immediate Estimated Duration ( Days )


Activity Predecessor
Optimistic Most likely Pessimistic
Activity
A - 1 3 5
B - 2 4 6
C A 3 6 15
D A 5 6 7
E C 5 7 9
F D 6 8 10
G B 7 9 11
H E,F,G 2 3 4

i) Draw the project and identify all the paths through it.
ii) What is expected project completion time ? ( 20 days )
iii) Find the probability of completing the project no more than 4 weeks later than
expected. ( There are two critical path : A-C-E-H and A-D-F-H with respective
variance 5 and 10 / 9 so we choose 5. The required probability = .9633 )

Solution :
2

a + 4m + b σ 2
b− a 
 6 
=
Duration ( Days ) t e
=
6
i

Activity a m b
A 1 3 5 3 4/9
B 2 4 6 4 4/9
C 3 6 15 7 4
D 5 6 7 6 1/9
E 5 7 9 7 4/9
F 6 8 10 8 4/9
G 7 9 11 9 4/9
H 2 3 4 3 1/9

A B C D E F G H
- - A A C D B E,F,G

Prepared by – Vinayanand Rele


Page 133 of 380 24/11/2008
Project Management

4
C
7 E
7
2
D
A
6 F H
3 5 6 7
8 3
1
B G
4 9
3

Paths Duration

1–2–4-6–7 = 20 A-G-E-H Critical Path


1–2–5–6–7 = 20 A-D-F-H
1–3–6–7 = 16

2
Critical Activity te σ CP ( 1 – 2 – 4 – 6 – 7 )
i

A-G-E-H

1–2 3 4/9
2–4 7 4
4–6 7 4/9
6–7 2 4/9
---------- ------------
2
t = 20 σ = 5 days
i

2
Critical Activity te σ CP ( 1 – 2 – 5 – 6 – 7 )
i

A-D-F-H
1–2 3 4/9
2–5 6 1/9
5–6 8 4/9
6–7 3 1/9
---------- ------------
2
t = 20 σ = 10/9 days
i

Now to select the CP which has larget variance with is 5 days.

Prepared by – Vinayanand Rele


Page 134 of 380 24/11/2008
Project Management

Now t = 20 & Standard deviation of Critical path = s = 5 = 2.24 Days

Now let x be the project duration.

Find probability that Project will be completed in 4 weeks.

As the problem has mentioned 4 weeks means 24 days.

Now let x be the project duration.

P (x ≤ 24 )

x−µ x − 20
Z= =
σ 2.24

So when z = 24

x − 20
24 =
2.24

x = 1.79

∴ P ( x ≤ 24 ) = P ( z ≤ 1.79 )

P1
P1 = 0.4633
P2 = 0.5

0 Z = 1.79

∴ Required probability

= 0.5 + 0.4633
= 0.9623

= 96.23 %

Prepared by – Vinayanand Rele


Page 135 of 380 24/11/2008
Project Management

15th March, 2008.

Lecture – IX.

Problem - 6

(i) A PERT activity has optimistic, most likely and pessimistic duration of 6 weeks,
15 weeks and 30 weeks respectively. Find the expected duration of this
activity and its variance.

(ii) One of the activities in a PERT project has an estimated average duration of
16 weeks, with a standard deviation of 4 weeks. The most likely time estimates
of this activity is 15 weeks. What will be the optimistic & pessimistic time
estimates of this activity.

(iii) One of the activities in a PERT project has an expected duration of 12 weeks
with a standard deviation of 2 weeks. The most likely time estimates of this
activity is 12 weeks calculate the optimistic and pessimistic time estimates for
this activity.

(iv) If in a PERT network the expected duration of the critical path is 36 months
and sum of the variances of the activities on the critical path is 25 ( months )2
than what is the probability that the project will be completed not earlier than
30 months and not later than 42 months.

(v) PERT calculation yields the critical path length of a project to be 24 months
with a variance of 9. What is the probability of its completion of 20 months ?
with in how many months would you expect the project to be completed with
probability of 0.99 ?

Solution :

(i) a = 6
m = 15
b = 30

2
te = ? & σ = ?
i

a + 4m + b 6 + 4(15) + 30
t e
= = = 16
6 6

Prepared by – Vinayanand Rele


Page 136 of 380 24/11/2008
Project Management

2 2
2 b−a  =
 30 − 6  = 16
σ =
 6 
i
 6 

(ii) Homework

(iii) te = 0
σi = 2
m = 12
a = ?
b = ?

a + 4m + b
t e
=
6

a + 4(12) + b
12 =
6

12 x 6 = a + b + 48

a + b = 24 (–)

b−a
σ i
=
6

b−a
2=
6

2x6=b-a

b – a = 12 (—)

Prepared by – Vinayanand Rele


Page 137 of 380 24/11/2008
Project Management

Now,

a+b = 12
b–a = 12
----------------------------
2b = 36

b = 18

Now replacing with Value of b to find out the a.

a+b = 24
a + 18 = 24
a = 6

So,

a = 6
b = 18

(iv)

t = 36
s2 = 25
∴ s = 5

P ( 30 ≤ x ≤ 42 )

x−µ x − 36
Z= =
σ 5

So when x = 30

30 − 36
Z= = -1.12
5

So when x = 42

42 − 36
Z= = 1.2
5

Prepared by – Vinayanand Rele


Page 138 of 380 24/11/2008
Project Management

∴ P ( 30 ≤ x ≤ 42 ) = P ( -1.2 ≤ z ≤ 1.2 )

P1
P1 = 0.3849
P2 = 0.3849

Z = -1.12
0 Z = 1.2

∴ P ( 30 ≤ x ≤ 42 ) = 0.3849 + 0.3849
= 0.7698
= 76.98 %

(v)

t = 24
s2 = 9
s = 3

P ( x ≤ 20 )

x−µ x − 24
Z= =
σ 3

So when x = 20

20 − 24
Z= = -1.33
3
∴ P ( x ≤ 20 ) = P ( z ≤ -1.33 )

P1 = 0.4082

P2

Z = -1.33
0

Prepared by – Vinayanand Rele


Page 139 of 380 24/11/2008
Project Management

Now P1 + P2 = 0.5

P2 = 0.5 – 0.4082
= 0.0918

∴ P ( x ≤ 20 ) = 0.0918
= 9.81 %

Now with in how many months would you expect the project to be completed with
probability of 0.99 ?

To find K such that,


P(x≤k) = 0.99
x−µ x − 24
Z= = (–)
σ 3

0.99
- 0.50
------
0.49

P1 = 0.49

0 z=?

z = 2.33 (—)

x − 24
∴ = 2.33
3

∴ x - 24 = 2.33 x 3
x = 30.99

so with probability of 0.99 the project would get completed on or before 31 months.

Prepared by – Vinayanand Rele


Page 140 of 380 24/11/2008
Project Management

Problem – 7.

The Arcot Machinery Company has been offered a contract to build and deliver nine
extruding process to the Home Bottling Company. The Contract price negotiated is
contingent upon meeting a specified delivery time with a bonus offered for early
delivery. The marketing department has established the following cost and time
information.

Normal Crash Crash


Normal Time ( Weeks )
Activity Cost Time Cost
(a) (b) (c) Rs ( Weeks ) Rs.
1–2 1 5 3 5,000 1 9,000
2–3 1 7 4 8,000 3 14,000
2–4 1 5 3 4,000 2 6,000
2–5 5 11 8 5,000 7 6,000
3–6 2 6 4 3,000 2 5,000
4–6 5 7 6 2,000 4 3,000
5–7 4 6 5 10,000 4 14,000
6–7 1 5 5 7,000 1 10,000

Normal delivery time is 16 weeks for a contact price of Rs. 62,000/-.

On the basis of the calculated profitability for each delivery time specified in the
following table, what delivery schedule do you recommend that the company
implement ?

Contact Delivery Time Contract Amount


( Weeks ) ( Rs )
15 62,500
14 65,000
13 70,000
12 72,500

( Here a = Optimistic Time, b = pessimistic time, c = most Likely time )

Solution :

This problem is for Homework.

Prepared by – Vinayanand Rele


Page 141 of 380 24/11/2008
Project Management

Problems on CPM / PERT


( University Questions )

For Homework.

Problem – 1. ( University Paper )

Draw the network for the following dependencies.

Activity A B C D E F G H
Preceding Activity - A A,B - A,D B E,F D

Problem – 2. ( University Paper )

The Project information for the customer order project of the Air Control Compnay is
presented here. Draw a project network for the Project.

ID Activity Predecessor Time


A Order Review None 2
B Order Standard Parts A 15
C Produce Standard Parts A 10
D Design Custom Parts A 13
E Software Development A 18
F Manufacture Custom Hardware C,D 15
G Assemble B,F 10
H Test E.G 5

Draw the network and find the Critical path and project duration, also compute various
floats of the activities. Tabulate your results.

Problem – 3. ( University Paper )

Activities of a project are described in the table below. Calculate the following .

a) Total time for completing the project.


b) Critical path
c) Early start, Early Finish, Late Start & Late Finish time for all activities
d) Total Float and Free Float available for Non-Critical activities.

Prepared by – Vinayanand Rele


Page 142 of 380 24/11/2008
Project Management

Activity Estimated Duration Immediate Predecessors


A 3 -
B 1 A
C 2 B
D 7 -
E 8 D
F 3 B
G 1 E,F
H 2 D

Problem – 4. ( University Paper )

Referring to the list of activities below, draw a network in Arrow Diagram (AOA)
convention. Find out the Total Time for project completion. Critical Path and Total Float
available on non critical path.

Activity Duration ( Weeks ) Immediate Predecessors


A 3 -
B 5 A
C 7 A
D 4 B
E 6 C
F 4 C
G 5 D,E
H 8 G,F
K 2 G
L 4 H,K

Prepared by – Vinayanand Rele


Page 143 of 380 24/11/2008
Project Management

Problem – 5. ( University Paper )

The following tables gives normal & crash times as well as Normal & Crash Costs for
the activities of the Project. Draw the Network Diagram and find the critical path. In
case, the project duration is required to be crashed by 2 days, which activities will get
the priority in crashing ?

Estimated Activity Cost


Activity
Normal Crash Normal Crash
1–2 5 2 600 900
2–4 6 3 700 1000
1–3 4 2 100 200
3–4 7 4 400 800
4–7 9 5 600 920
3–5 12 3 1600 1960
4–6 10 6 1500 1800
6–7 7 4 400 490
7–9 6 4 300 420
5–9 12 7 400 850

Problem – 6. ( University Paper )

A marketing project consists of 7 activities A to G with the following sequences, normal


duration, normal cost, crash time and crash cost.

Preceding Normal Time Crash Time Normal Crash Cost


Activity
Activity ( Days ) ( Days ) Cost ( Rs. ) ( Rs )
A None 4 3 60 90
B None 6 4 150 250
C None 2 1 30 60
D A 5 3 150 250
E C 2 2 100 100
F A 5 3 115 175
G B,D,E 4 1 100 310

Draw the network diagram for the project and find the normal duration and normal cost
of the project. Also find the critical path. Find the corresponding cost of the project on
crashing the project by 3 days.

Prepared by – Vinayanand Rele


Page 144 of 380 24/11/2008
Project Management

Problem – 7. ( University Paper )

The details of project activities are given in the table below :

Duration ( Days ) Crash Cost


Activity Predecessor
Normal Crash ( Per day )
A - 9 6 Rs. 20,000/-
B - 8 5 Rs. 25,000/
C - 15 10 Rs. 30,000/
D A 5 3 Rs. 10,000/
E B 10 6 Rs. 15,000/
F C,D,E 2 1 Rs. 40,000/

Draw the project network using “Activity on Arrow” convention and find out.

i) Normal, Crash and Optimum duration of the project.


ii) Amount of maximum savings in project cost at optimum duration. Assume indirect
cost = Rs. 35/- per day.

Problem – 8. ( University Paper )

The table below defines the activities for a small project.

Immediate Duration ( Days ) Cost ( Rs. ‘000 )


Activity
Predecessors Normal Crash Normal Crash
A - 6 4 24 34
B - 4 3 12 22
C A 5 3 20 28
D A 7 4 29 47
E B 6 5 26 34
F B 8 5 34 52
G C,E 10 6 27 47
H D,F 9 7 34 48

The project attracts a penalty of Rs. 10,000/- per day for project completion beyond 18
days. Draw the project network by precedence diagramming method ( i.e Activity Node
Method ) and find out the number of days delay intended beyond the schedule date to
minimize total project cost.

Prepared by – Vinayanand Rele


Page 145 of 380 24/11/2008
Project Management

Problem – 9. ( University Paper )

The table below gives activities, their normal estimated duration and their relationships
for a small project. It also indicates the minimum possible durations if crashed and extra
costs incurred for such crashing. The management desires the project to be completed
in a shorter duration than the normally expected. But the extra funds available for this
purpose are limited to Rs. 5,00.000/-. Only what would be shortest of the project after
the crashing under the budget limitations ?

Immediate Duration ( Days ) Cost ( Rs. ‘000 )


Activity
Predecessors Normal Crash Normal Crash
A - 5 3 400 600
B - 5 1 300 500
C A 10 5 400 700
D B 7 2 400 600
E A 6 2 300 500
F C,D 11 5 600 930
G C,D 6 4 300 600
H E,F 5 1 200 400
I G 4 1 200 500

Problem – 10. ( University Paper )

The following table provides normal and crash times as well as normal and crash costs
for the activities of a project.

Normal Time Normal Cost Crash Time Crash Cost


Activity
( weeks ) ( Rs. Lakhs ) ( Weeks ) ( Rs. Lakhs )
1-2 3 5 1 9
2-3 4 8 3 14
2–4 3 4 2 6
2–5 8 5 7 6
3–6 4 3 2 5
4–6 6 2 4 3
5–7 5 10 4 14
6–7 3 7 1 10

i) Draw the Network diagram and Find critical Path


ii) Using the above information, crash or shorten the activities step by step until
the shortest duration is reached.

Prepared by – Vinayanand Rele


Page 146 of 380 24/11/2008
Project Management

Problem – 11. ( University Paper )

The following table gives data on Normal time, Crash Time, Normal Cost and Crash
Cost for a project.

Normal Time Crash Time Normal Cost Crash Cost


Activity
( Days ) ( Days ) ( Rs. ) ( Rs. )
A 1–2 3 2 8,000 10,000
B 1–3 3 2 4,000 7,000
C 2–5 1 1 4,000 4,000
D 2–6 6 4 40,000 60,000
E 3–4 2 1 4,000 6,400
Dummy 4–5 - - - -
F 4–6 5 3 30,000 38,000
G 5–6 7 6 24,000 30,000
H 6–7 4 3 32,000 39,000

i) Draw the network and find out the critical path and the Normal project duration.
ii) What is the minimum length of the project and the corresponding cost when all the
critical activities are crashed to the maximum extent ?
iii) If the indirect costs are Rs. 6,000/- per day then what is the project – Cost Trade –
Off Point of the Project ?

Prepared by – Vinayanand Rele


Page 147 of 380 24/11/2008
Project Management

Problem – 12. ( University Paper )

Following table gives the list of project activities, estimated duration of individual
activities and relationships by defining their successor activities.

Activity Estimated Duration ( weeks ) Successor Activities


A 5 D,E
B 4 F
C 6 G
D 4 I
E 4 J
F 6 J
G 5 H,G
H 2 J
I 5 L
J 11 N
K 4 M
L 6 N
M 9 N
N 5 -

i) Identify the critical paths and the project completion time.


ii) Find the project completion time in following cases :

a) If activity I is delayed by Three weeks.


b) If activity K is delayed by Two weeks.
c) If activity M is crashed by One Week.
d) If activity G is crashed by Three weeks.

Prepared by – Vinayanand Rele


Page 148 of 380 24/11/2008
Project Management

PERT Related Problems.

Problem – 13 & 14 . ( University Paper ) Already solved above.

Problem – 15. ( University Paper )

Following table lists various details of the project activities.

Duration in Weeks
Activity Predecessors
Optimistic = to Most Likely = tm Pessimistic = tp
A - 1 1 7
B - 1 4 7
C - 2 2 8
D A 1 1 1
E B 2 5 14
F C 2 5 8
G D,E 3 6 15

i) Draw the project network using ‘Activity convention and Identity” and Identify all
paths though it.

ii) Find expected ( average ) duration and variance for each activity.

iii) What is the expected duration of project with 50 % chance of completion ?

iv) What should be your level of confidence to accept the project deadline of 20
weeks ?

( Note : A normal distribution curve covers 50.0%, 84.1% and 97.7% area to its left for 0
+ 1 and +2 standard deviations from the mean respectively )

Prepared by – Vinayanand Rele


Page 149 of 380 24/11/2008
Project Management

Problem – 16. ( University Paper )

Referring to the activity table given below. Find the expected time for completion of the
project with 84.1% probability.

Estimation Activity Duration


Activity
to tm tp
1–2 3 6 15
1–6 2 5 14
2–3 6 12 30
2–4 2 5 8
3–5 5 11 17
4–5 3 6 15
6–7 3 9 27
5–8 1 9 7
7–8 4 19 28

Note : A standard deviation of +1.0 to mean value under “Normal Distribution Curve”
Covers 84.1% of area to its left.

Prepared by – Vinayanand Rele


Page 150 of 380 24/11/2008
Project Management

Problem – 17. ( University Paper )

A new pharmaceutical product is to be released on a deadline for which 44 days are left.
Activities involved in Product launch with their interdependence and probabilistic time for
completion are given in the table. Draw a project network and find the probability of
completing the project in time.

Predecessors Time ( In Days )


Activity
Activities Optimistic Most Likely Pessimistic
A - 6 10 14
B A 1 2 3
C A 16 20 30
D B 3 5 7
E D 2 3 4
F C 7 10 13
G D 1 2 3
H G 1 3 5
I C,G 2 2 2
J I 2 3 4
K H 1 1 1
L J,K 1 2 3

Prepared by – Vinayanand Rele


Page 151 of 380 24/11/2008
Project Management

Resource Allocation.

Introduction

To be able to schedule the resource requirements for a project the following details are
required.

(a) The customary activity times, descriptions and sequences as previously


described.
(b) The resource requirements for each activity showing the classification of the
resource and the quantity required.
(c) The resources in each classification that are available to the project. If variations
in availability are likely during the project life, these must also be specified
(d) Any management restrictions that need to be considered e.g. which activities
may or may not be split or any limitations on labour mobility.

Resource Allocation

Resource Smoothing Resource Leveling

Time is the constraint but Resource are the constraints


resources are not the constraints. while the time is available in
plenty

Resource Smoothing :

It is a network technique used for smoothing peak resource requirements during


different periods of the project network. Under this technique the total project duration is
maintained at the minimum level. For example if the duration of a project is 15 days,
then the project duration is maintained, but the resources required for completing
different activities of a project are smoothened by utilizing floats available on non critical
activities. These non-critical activities having floats are rescheduled or shifted so that a
uniform demand on resources is achieved. in other words, the constraint in the case of
resource smoothing operation would be on the project duration time Resource
smoothing is a useful technique for business managers to estimate the total resource
requirements for various project activities.

Prepared by – Vinayanand Rele


Page 152 of 380 24/11/2008
Project Management

In resource smoothing, the time scale diagram of various activities and their floats (if
any), along with resource requirements are used. The periods of maximum demand for
resources are identified and non-critical activities during these periods are staggered by
rescheduling them according to their floats for balancing the resource requirements.

Resource Leveling :

It is also a network technique which is used for reducing the requirement of a particular
resource due to its paucity. The process of resource leveling utilizes the large floats
available on non-critical activities of the project and thus cuts down the demand on the
resource . In resource leveling the maximum demand of a resource should not exceed
the available limit at any point of time. In order to achieve this, non critical activities are
re-scheduled by utilizing their floats. Sometimes, the use of resource leveling may lead
to enlarging the completion time of the project. (Delay)

Rules for Scheduling :

(a) Assign the resource to the activity that has the least float
(b) If activities have equal float, give the resources to the longest activity.
(c) Where there is conflict between activities, give the resources to the activity that
uses the largest amount of the resource.
(d) Sequence code.

Updating the network

The progress of various activities in a project network is measured periodically.


Normally, either most of the activities are ahead or behind the schedule. It is therefore,
necessary to update or redraw the network periodically to know the exact position of
completion of each activity of the project. The task of updating the network may be
carried out once in a month. Sometimes the updating of the network may provide useful
information to such an extent that it may demand the revision of even those very
activities which have not started. Even the logic may also change i.e. some of the
existing activities may have to be dropped and new activities may be added up. In brief,
the network should be amended accordingly in the light of new developments.

Updating is done by assigning zero values to the duration of the completed


activities. Partially completed activities are assigned times equivalent to their
unfinished portions. Changes in the arrow diagram such as addition or deletion of
any future activities must also be made. By repeating the usual computations on
the arrow diagram with its new time elements, we can determine the new time
schedule and possible changes in the duration of the project. Such information is
used until it is again necessary to update the time schedule. In real situations
many revisions of the time schedule are usually required at the early stages of
the execution phase. A stable period follows in which little revision of the current
schedule may be required.

Prepared by – Vinayanand Rele


Page 153 of 380 24/11/2008
Project Management

3
E
B
7 11
A G
1 2 D 5 5 6
6 5
C
F
2
3
4

Find EST, LST & CP

13 13

0 6 3 24 29

B E
0 6 24 29
7 11
A G
1 2 D 5 5 6
6 5
C
F
2
3
4

18 21

Prepared by – Vinayanand Rele


Page 154 of 380 24/11/2008
Project Management

Question – 1.

E G
11
5

3 8
F
H K
B 6
7 5 4
7
A C I
1 2 L
4 9 10
6 3 7 8

D
J
2 2

18

18

6
29
13
E G
29
13 11
5 26

0 6 3 8
F 19 33 41
H K
0 6 B 6 33 41
7 5 4
7
A C I L
1 2 4 9 10
6 3 7 8
9
26
D
J
2 2

21 18

Prepared by – Vinayanand Rele


Page 155 of 380 24/11/2008
Project Management

Total Float = LFT – EST – Duration

At C total Float = 26 - 6 - 3 = 17

6
TC of D = 31 - - 2 = 23

TC of F = 24 - 13 - 6 = 5

Note : All Critical activity will have ZERO total Float.

Problem – 1.

(a) Draw network of the following activities.

(i) Activities A and B start simultaneously.


(ii) C follows A
(iii) D and E can only commence when B and C are completed.
(iv) D gives rise to F and E gives rise to G and is the final activity.
(v) H is dependent on F and is the final activity

(b) Find also the critical path if the duration of activities is as follows :

Activity A B C D E F G H
Duration
6 8 3 12 9 7 15 8
( Weeks )

(C) At the end of 12 th week, project progress and review have taken place.
Following are the observations.

(i) Activities 1-2, 1-3, 2-3 are completed.


(ii) Activity 3-5 has been progressing for 3 weeks and needs 8 more
weeks for completion.
(iii) Activity 3-4 has been in progress for 3 weeks and since a new
machine has been commissioned, the present estimate is that it can
be completed in 6 more weeks.
(iv) Re-assessment of activity 6-7 has revealed that it can be completed
in 7 weeks.

On the basis of these information, update the network & indicate change in
critical path if there by any.

Prepared by – Vinayanand Rele


Page 156 of 380 24/11/2008
Project Management

Solution : 6 6

2
0 21 28
A //
0 6 21 18 28 25
C 3
F
1 4 6
B
// 7 H
0
D
8 // 12 6 8 36 35
// 7
3
3 7
21
3 // E
G
12 9 18 20
9
15
8
5

How it is Solved ?

1. Draw the network diagram.


2. Workout LST EFT.
3. Find the CP.
4. Mentioned in BLUE is the Work Remaining & GREEN is work Completed.
5. Work out new EFT
6. Now the Non critical path will become Critical.

Hence New Project duration will be 35 Days. New Critical path will be 1 - 3 – 5 – 7.

Prepared by – Vinayanand Rele


Page 157 of 380 24/11/2008
Project Management

Another Method to Solve this Problem.

A
0 6 18 25
C 3
F
1 4 6
B 7 H
D
8 9 7 35

3 7
E
9 G
20
11
15
5

How it is Solved ?

1. Draw the network diagram.


2. Write the Duration considering the New duration ( Mentioned in BLUE )

Prepared by – Vinayanand Rele


Page 158 of 380 24/11/2008
Project Management

Problem – 2.

The following table lists the activities of a maintenance project :

Activity 1-2 1-3 1-4 2-5 3-6 3-7 4-7 5-8 6-8 7-9 8-9
Duration
2 2 1 4 5 8 3 1 4 5 3
( Month )

(i) Draw the project network.


(ii) Find the critical path and duration of the project.
(iii) Suppose we require to employ, a special piece of equipment on activities
1-3, 3-6, 2-5, 5-8 and 8-9 one at a time. Will it affect duration of the
project? Explain.

Solution :

7 11

2 7 6 11
5
2 5
4
1

0 5 2 8 1 12

0
2
2 7 11 12
1 1
1 3 6 8
2 5 4
1
7 10 15
8 3
1
1 10 15

4 7 9
3 5

Now as given in the problem, special piece of equipment on activities 1-3, 3-6, 2-5,
5-8 and 8-9 one at a time. Hence,

Prepared by – Vinayanand Rele


Page 159 of 380 24/11/2008
Project Management

At Time t = 0, we start activity 1 – 3, with special equipment & complete it at t = 2, (


because duration of 1 – 3 is 2 ).

At t = 2 there is a tie, both the activities 2 – 5 and 3 – 6 requires the special equipment &
2
they have same EST i.e.

5 1
Now total Float of 2 – 5 is and that of 3 – 6 is therefore we delay 2 – 5 by
5 days & start 3 – 6 at t = 2 with special equipment and compute it at t = 7.

At t = 7 start 2 – 5 with special equipment and complete it at t = 11.

At t = 11 we start 5 – 8 with special equipment and complete it at t = 12.

Finally we start 8 – 9 at t = 12 with special equipment and complete it at t = 15.

The other activities will start at their EST and finish at there EFT.

There by utilizing total float at 2 – 5 we can manage with the special equipment. There
is NO DELAY in Project.

Activities EST EFT Remarks

1–3 0 2 With Special Equipment

3–6 2 7 With Special Equipment, delay 2 – 5 as it has


Largest TF of 5 day.

2–5 7 11 With Special Equipment

5–8 11 12 With Special Equipment

8–9 12 15 With Special Equipment

Prepared by – Vinayanand Rele


Page 160 of 380 24/11/2008
Project Management

Problem – 3.

A protect has the following time schedule.

Activity Time (in months) Activity Time (in months)


1-2 2 3-7 5
1-3 2 4-6 3
1-4 1 5-8 1
2-5 4 6-9 5
3-6 8 7-8 4
8-9 3

Construct PERT Network and compute :

(i) Total float for each activity


(ii) Critical path and its duration.

Also find the minimum number of cranes the project must have for its activities
2-5, 3-7 and 8-9 without delaying the project.

Does any change require in PERT network ? If so, indicate the name.

Solution :

7 11

2 6
5
2 5
4
5
0 5 2 8 1 12

0
2
2 7 11
1 1
1 3 7 8
2 5 4
1
6 10 15
7
8 3
1
1 10 15
6
4 6 9
3 5

Prepared by – Vinayanand Rele


Page 161 of 380 24/11/2008
Project Management

Activities EST EFT Remarks

3–7 2 7 Start at t = 2, 3 – 7 With Crane Machine &


Delay 2 – 5 as it has larger TF of 5 days.

2–5 7 11 With Crane Machine.

5–8 11 12 With Crane Machine.

8–9 12 15 With Crane Machine.

Activities will be as per the schedule.

Prepared by – Vinayanand Rele


Page 162 of 380 24/11/2008
Project Management

18th March, 2008.

Lecture – X.

Problem – 4.

For a project consisting of several activities, the duration and required resources
to carry out each of the activities and their availabilities are given below :-

(a) Draw the network, identify the critical path and compute the total float for
each of the activities.

(b) Draw the time Scale Diagram:

Resources Require
Activity Duration in Days
( Crew Size )
1-2 6 30
1-6 7 20
2-3 12 30
2-4 5 20
3-5 4 30
4-5 6 20
5-7 3 30
6-7 9 20
7-8 5 20

Resource Availability : - No. of Crew member = 50

Solution :
18 18

6 22
3

6 22
12 4
0 2 5
16 25 30
0
6 11 3 25 30
5 6
1
4 7 8
5
16

7 7 9

Prepared by – Vinayanand Rele


Page 163 of 380 24/11/2008
Project Management

Total Nos of Paths :

1–2–3–5–7–8 = 30 Critical path


1–2–4–5–7–8 = 25
1–6–7–8 = 21

Activities EST EFT - - - Duration

1 – 2 0 6 0
1 – 6 0 7 16 –0–7=9
2 – 3 6 18 0
2 – 4 6 11 16 –6–5=5
3 – 5 18 22 0
4 – 5 11 17 22 – 11 – 6 = 5
5 – 7 22 25 0
6 – 7 7 16 25 –7–9=9
7 – 8 25 30 0

Note : For Critical Path Float will be Zero.

Prepared by – Vinayanand Rele


Page 164 of 380 24/11/2008
Project Management

Time Scale Diagram

20 20
4
5 6

30 30 30 30 20
1 2 3 5 6 8
6 12 4 3 5

20 20
6
7 9

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
50 50 50 50 50 50 70 70 70 70 70 70 70 70 70 70 50 30 30 30 30 30 30 30 30 20 20 20 20 20

Class Intervals Nos of Workers

0 – 6 50
6 – 17 70
16 – 17 50
17 – 25 30
25 – 30 20

Prepared by – Vinayanand Rele


Page 165 of 380 24/11/2008
Project Management

Gantt Chart
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1-2
6

1-6
7

2-3
6 18

2-4
6 11

3-5
18 22

4-5
11 17

5-7
22 25

6-7
8 16

7-8
25 30

50 50 50 50 50 50 70 70 70 70 70 70 70 70 70 70 50 30 30 30 30 30 30 30 30 20 20 20 20 20

Prepared by – Vinayanand Rele


Page 166 of 380 24/11/2008
Project Management

Histrogram

75

70

65

60

55

50

45

40

35

30

25

20

15

10

0
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34

Prepared by – Vinayanand Rele


Page 167 of 380 24/11/2008
Project Management

Resource Graph.

75
70
65
60
55
Maximaum Available 50
50
45
40
35
30
25
20
15
10
5
0
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34

Prepared by – Vinayanand Rele


Page 168 of 380 24/11/2008
Project Management

Problem – 5.

The following table gives for each activity of a project. its duration and
corresponding resources requirement as well as total availability of each
resources :

Resources Required
Activity Duration
Machines Men
1-2 7 2 20
1-3 7 2 20
2-3 8 3 30
2-4 6 4 30
3-6 9 2 20
4-5 3 2 20
5-6 5 2 20
Maximum Resource Available 4 40

(a) Draw the network, compute earliest start time, latest finish time for each
activity, total float for each activity and identify the critical path assuming
that there are no resource constraints.

(b) Draw the Time Scale Diagram along with resource accumulation table.
Comment on demand for the machines and men for the entire project
duration.

Solution :

7 16

7 13
3
0 2 4 19
6 3
0 // 16
7 3

1
// 8 5
3 24
15
5 24
7
15

3 // 6
9

Prepared by – Vinayanand Rele


Page 169 of 380 24/11/2008
Project Management

Activities EST EFT - - - Duration

1 – 2 0 7 0
1 – 3 0 7 15 –0–7=8
2 – 3 7 15 0
2 – 4 7 13 16 –7–6=3
3 – 6 15 24 0
4 – 5 13 16 19 – 13 – 3 = 3
5 – 6 16 21 24 – 16 – 5 = 3

Prepared by – Vinayanand Rele


Page 170 of 380 24/11/2008
Project Management

Time Scale Diagram

4 - 30 2 - 20
4 5

2 - 20 3 - 30
1 2 3 6
7

2 - 20

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Machines 4 4 4 4 4 4 4 7 7 7 7 7 7 5 5 4 4 4 4 4 4 2 2 2
Men 40 40 40 40 40 40 40 60 60 60 60 60 60 50 50 40 40 40 40 40 40 20 20 20
Demand Exceeds Supply

Prepared by – Vinayanand Rele


Page 171 of 380 24/11/2008
Project Management

Gantt Chart
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
2 - 20
1-2
7
2 - 20
1-3
7
3 - 30
2-3
7 15
4 - 30
2-4
7 13
2 - 20
3-6
15 22
2 - 20
4-5
13 16
2 - 20
5-6
16 21

Machines 4 4 4 4 4 4 4 7 7 7 7 7 7 5 5 4 4 4 4 4 4 2 2 2
Men 40 40 40 40 40 40 40 60 60 60 60 60 60 50 50 40 40 40 40 40 40 20 20 20

Prepared by – Vinayanand Rele


Page 172 of 380 24/11/2008
Project Management

Problem – 6.

A small project consists of seven activities for which the relevant data are given
below :

Activity Preceding Activity Activity Duration Days


A - 4
B - 7
C - 7
D A,B 5
E A,B 7
F C,D,E 6
G C,D,E 5

(i) Draw the network and find the project completion time
(ii) Calculate total float for each of the activities.
(iii) Draw Time Scaled Diagram

Solution :

7 14 20

4 12 20

2 4 6

7
0
A D
4 D1 0 7
0 5
D2 0 F D3 0
B 14
1 3 6
7
E 14
C 7 20
7
5 G 7
20
5

Prepared by – Vinayanand Rele


Page 173 of 380 24/11/2008
Project Management

Activities EST EFT Total Float

1 – 2 0 4 3
1 – 3 0 7 0
1 – 5 0 7 7
2 – 3 4 4 -
3 – 4 7 12 2
3 – 5 7 14 0
4 – 5 12 12 -
5 – 6 14 20 0
5 – 7 14 19 1
6 – 7 20 20 -

Critical Path : 1 – 3 – 5 – 6 – 7 that is B – E – F – D 3

Time Scale Diagram

A
2 D
4 4
5
D1 D2

B E F
1 3 5 6
7 7 6

D3

C G
7
7 5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Prepared by – Vinayanand Rele


Page 174 of 380 24/11/2008
Project Management

Gantt Chart

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A
4

B
7

C
7

D
7 12

E
7 14

F
15 20

G
16 19

Prepared by – Vinayanand Rele


Page 175 of 380 24/11/2008
Project Management

Problem – 7.

Draw a 'Gantt Chad' and 'Resource Graph' for the project schedule based on the
table below and find out the following :

(i) Total time for completion.


(ii) Days of over allocation of resources if maximum workers available are 20.

IMMEDIATE ALLOCATED
ACTIVITY PREDECESSORS DURATION WORKERS
A - 8 4
B - 7 8
C A 6 5
D B 8 4
E B 4 8
F B 8 6
G C,D 5 5
H E 6 4
I F 6 5
J G,H,I 10 6

Solution :
10

2 16
C
0 15
A 6
8
0
4

1
G
7 D 16
B 21 31
8 5
7 7 11 21 31

E H J
3 5 7 8
4 10
5

F 15
I
8 15 6

Prepared by – Vinayanand Rele


Page 176 of 380 24/11/2008
Project Management

Activities EST EFT Total Float

A 1 – 2 0 8 2
B 1 – 3 0 7 0
C 2 – 4 8 14 2
D 3 – 4 7 15 1
E 3 – 5 7 11 4
F 3 – 6 7 15 0
G 4 – 7 15 20 1
H 5 – 7 11 17 4
I 6 – 7 15 21 0
J 7 – 8 21 31 0

Critical Path : 1 – 3 – 6 – 7 – 8 that is B – F – I – J

( Rest for Home work. )

Prepared by – Vinayanand Rele


Page 177 of 380 24/11/2008
Project Management

Problem – 8.

The following table gives the activity schedule and resource requirement for a
project. Draw a Gantt Chart representing the schedule and resource loading
chart. What is the peak requirement of the resource and on which day it occurs?

ACTIVITY DURATION START FINISH RESOURCE


A 3 1 3 3
B 2 2 3 2
C 4 4 7 4
D 5 4 8 5
E 3 7 9 3
F 2 8 9 2
G 2 10 11 6
H 3 10 12 3
I 2 12 13 2
J 3 12 14 5
K 1 15 15 3

Note : Assume Start at the beginning and Finish at the end of the day numbers
mentioned in the table.

Solution :

Since NO LOGICAL connections are given there is no need of Network diagram


hence start directly with activity. ( Resource is for per day. )

Activities EST EFT Total Float

A 0 3 3
B 1 3 2
C 3 7 4
D 3 8 4
E 6 9 3
F 7 9 2
G 9 11 2
H 9 12 3
I 11 13 2
J 11 14 3
K 11 15 1

( Now Draw the Gantt Chart ) – Home work.

Prepared by – Vinayanand Rele


Page 178 of 380 24/11/2008
Project Management

Problem – 9.

The table below gives the project time table that is to commence in May 2001.
The budgeted costs for various activities as indicated are to be spent uniformly
over their duration.

DURATION START 1 FINISH ACTIVITY


ACTIVITY MONTH MONTH
MONTH COST
A 4 May 01 Aug. 01 Rs.80,000

B 2 Sep. 01 Oct. 01 Rs.60,000

C 6 Sep. 01 Feb. 02 Rs.90,000

D 9 Mar. 02 Nov.02 Rs.45,000

E 2 May 01 June 01 Rs.50,000

F 5 Jul. 01 Nov. 01 Rs.1,00,000

G 3 Nov. 01 Jan. 02 Rs.75,000

H 7 Jul. 01 Jan. 02 Rs.70,000

I 10 Feb.02 Nov. 02 Rs.1,50,000

J 1 Dec. 02 Dec. 02 Rs.40,000

Note : Assume the activity starting at the beginning and finishing at the end
of the month.
(a) Draw a "Gantt Chart' for project schedule and work out the monthly aid
cumulative cash flows for the project.
(b) Draw the 'S' curve for cash flows. What does this curve indicate ?

Solution :

Activity Cost is for full activity, hence first workout…

Prepared by – Vinayanand Rele


Page 179 of 380 24/11/2008
Project Management

Gantt Chart

05-01

06-01

07-01

08-01

09-01

10-01

11-01

12-01

01-02

02-02

03-02

04-02

05-02

06-02

07-02

08-02

09-02

10-02

11-02

12-02
A 20

B 30

C 15

D 5

E 25

F 20

G 25

H 10

I 15

J 40

Prepared by – Vinayanand Rele


Page 180 of 380 24/11/2008
Project Management

Problem – 10.

The direct Cost estimates for various activities of a project network are as given
below :

Duration in Direct Cost ( Rs )


Activity
Months Per Month
A 1-2 4 80,000
B 1-3 7 40,000
C 2-6 3 40,000
D 2-4 3 80,000
E 3-4 2 120,000
F 3-5 2 60,000
G 4-5 2 60,000
H 5-6 3 20,000

(i) Draw the network, find critical path and project duration.
(ii) Compile monthly and cumulative monthly cash flow requirements for the
early start schedule.
(iii) Determine a near uniform cash flow schedule.

Solution :

11 14

4 14
C
2 6
3
0 A
D 9
0 4
3
9

1 H 3
4

B 7 G
E
7 2 2
7
11

3 F 5 11

Prepared by – Vinayanand Rele


Page 181 of 380 24/11/2008
Project Management

Total Nos of Paths :

1–2–4–5–6 = 12
1–2–6 = 7
1–3–4–5-6 = 14 Critical path
1–3–5–6 = 12

Activities EST EFT Total Float

A 0 4 2
B 0 7 0
C 4 7 2
D 4 7 7
E 7 9 0
F 7 9 2
G 9 11 0
H 11 14 0

Prepared by – Vinayanand Rele


Page 182 of 380 24/11/2008
Project Management

Gantt Chart

1 2 3 4 5 6 7 8 9 10 11 12 13 14

A 80
4

B 40
7

C 40
4 7

D 80
4 7

E 120
7 9

F 60
7 9

G 60
9 11

H 80
11 14

Monthly Cash flow 120 120 120 120 160 160 160 180 180 60 60 80 80 80
Cummulative Cash Flow 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 1680

Prepared by – Vinayanand Rele


Page 183 of 380 24/11/2008
Project Management

S Curve

170
Cummulative Cash Flow

160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
( Duration )

Prepared by – Vinayanand Rele


Page 184 of 380 24/11/2008
Project Management

Problem – 11.

The direct estimates for various activities of a pipeline project are as given
below:

Activity ( I – J ) Duration ( Months ) Direct Cost ( Rs )

1–2 13 26,00,000

1–3 12 60,00,000

2–4 2 20,00,000

3–4 8 20,00,000

2–5 15 15,00,000

4–5 2 15,00,000

Project overheads are Rs.3.00,000/- per month

(i) Draw network. find critical path, project duration and total float of each
activity.

(ii) On graph paper compile monthly, cumulative monthly, cash flow requirement
for early start and late start schedule.

(iii) Draw cumulative cash flow requirements on graph for early and late start
schedule.

(iv) The government will release the amount in the following manner.

1st Year Rs.69,00,000 for Direct + Rs.36,00,000 Overhead.

2nd Year Rs.68,00,000 far Direct + Rs.36,00,000 Overhead.

3rd Year RS.19,00,000 for Direct + Rs.12,00,000 Overhead

Unspent amount if any will lapse and hence cannot be carried forward Schedule
the activities on graph to match release of funds

It is possible to schedule the project without extending project duration. (Assume


funds for an activity are required uniformly throughout its time duration)

Prepared by – Vinayanand Rele


Page 185 of 380 24/11/2008
Project Management

Solution :

13 28

13 28

2 5
15
0
26
0 13
2 2
20

1
4

18
12
12 8

Total Nos of Paths :

1–2–4–5 = 17
1–2–5 = 28 Critical path
1–3–5-6 = 22

Activities EST EFT Total Float

1 – 2 0 13 0
1 – 3 0 12 6
2 – 4 13 15 11
3 – 4 12 20 6
2 – 5 13 28 0
4 – 5 20 22 6

Prepared by – Vinayanand Rele


Page 186 of 380 24/11/2008
Project Management

Time Scale Diagram

2L 1L
1 2 5
13 15

5L 2.5 L 7.5 L
3 4
12 8 8

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
7 7 7 7 7 7 7 7 7 7 7 7 4.5 13.5 13.5 3.5 3.5 3.5 3.5 3.5 8.5 8.5 1 1 1 1 1 1 Add Rs 3 L Every Month

7 14 21 28 35 42 49 56 63 70 77 84 88.5 102 115.5 119 122.5 126 129.5 133 141.5 150 151 152 153 154 155 156 Add Rs 3 L Every Month

Prepared by – Vinayanand Rele


Page 187 of 380 24/11/2008
Project Management

Gantt Chart

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

1-2 2L
13

1-3 5L
12

2-4 10 L
13 15

2-5 1L
13 28

3-4 2.5 L
12 20

4-5 7.5 L
20 22

Monthly Cash flow Add Rs 3 L


Cumm. Cash Flow Add Rs 3 L

Prepared by – Vinayanand Rele


Page 188 of 380 24/11/2008
Project Management

Problem – 12.

The following table gives the activity schedule and manpower requirement for a
project. Draw the Gnat Chart representing the schedule and resource loading
chart. What is the peak requirement of the resource and on which day (s) it
occurs ?

Duration Total Man Power


Activity Preceding Activity
Days Required
A - 3 60
B - 4 84
C A 2 22
D A 3 36
E B 6 72
F D,E 3 18
G C 5 35
H F 6 42
I G,H 7 56

Solution :

For Homework.

Prepared by – Vinayanand Rele


Page 189 of 380 24/11/2008
Project Management

29th March, 2008.

Lecture – XI.

Project Control
Variance Analysis Approach

The traditional approach to project control involves a comparison of the actual cost with
the budgeted cost to determine the variance. An example of variance analysis is as
follows :

Activity A Activity B
Budgeted Cost in the period 50,000 30,000
Cumulative budget to date 200,000 75,000
Actual Cost in the Period 55,000 28,000
Cumulative actual Cost to Date 240,000 80,000
Variance for the period (5,000) 2,000
Cumulative variance to date (40,000) (5,000)

The variance analysis approach is inadequate for project control for the following
reasons :

1. It is backward looking rather than forward looking. It tells only what happened in
the past but does not answer the following questions: What will happen in future?
Is the rate of work accelerating or decelerating ?

2. It does not use the data effectively to provide integrated control. The traditional
variance analysis shows whether in the time period under analysis more or less
resources were expended than budgeted. However, it does not indicate the value
of work done. This information is vital for purposes of control.

Prepared by – Vinayanand Rele


Page 190 of 380 24/11/2008
Project Management

Performance Analysis: Modern Approach to Control

Effective control over a project requires systematic 'performance analysis' This calls for
answering the following questions :

• Is the project as a whole (and its individual parts) on schedule, ahead of schedule,
or behind schedule? If there is' a variation, where did it occur, why did it occur, who
is responsible for it, and what would be its implications ?

• Has the cost of the project as a whole (and its individual parts) been as per budget
estimates, less than the budget estimates, or more than the budget estimates? If
there is a variation, where did it occur, why did it occur, who is responsible for it,
and what would be its implications ?

• What is the trend of performance? What would be the likely final cost and
completion date for the project and its individual parts ?

For small and simple projects, the project managers would do performance analysis for
the project as a whole, or for its major components. As the project becomes larger and
more complex, performance analysis needs to be done for individual segments of the
projects which are referred to as 'cost accounts'.

Method of Analysis

For analyzing the performance at cost account and higher levels of the work breakdown
structure, we employ a method of analysis which takes into account the value of work
that has been done. In the traditional method of analysis, the project manager measured
the actual progress against the predetermined schedule and the actual cost against the
budget estimate. This did not enable him to know systematically whether the
expenditure incurred was commensurate with progress. He perhaps relied on subjective
estimates.

Earned Value Analysis / Earned Value Management

A method for measuring project performance. It compares the amount of work that was
planned with what was actually accomplished to determine if cost and schedule
performance is as planned.

It helps us to determine how much volume and how much value of work has been done
on a particular day of an activity / project.

Prepared by – Vinayanand Rele


Page 191 of 380 24/11/2008
Project Management

It is a cost performance measure which helps the project manager to understand the
total cost performance. It is achieved by integrating the scope, cost and the schedule
measures of work. In EVA, we calculate :

(i) Budget Cost


(ii) Actual Cost
(iii) Budgeted cost estimate
(iv) Cost Variance.

Earned value is the percentage of the total cost budgeted against the total cost incurred.

The Budgeted Cost of each activity is considered as its value for the project. hence
completion of an activity is considered to contribute equivalent to its value to the total
value of the project. In other words, an activity earns value, equivalent to its budgeted
cost on its completion. An activity that is partially completed on a particular date is also
considered to have earned value equivalent to its percentage completion on the given
date multiplied by its total budgeted cost.

In case Actual Expenditure incurred for completion of an activity exceeds its budgeted
cost, the project does 'not earn any additional benefit since activity parameters are well
specified. The variance therefore indicates cost over-run.

The total value earned for the project on any given date is the total of earned values of
all the completed activities till date as well as the total of earned values to date for
partially completed activities.

Performance Analysis seeks to remove this subjectivity by employing an analytical


frame work based on the following terms :

(1) SCWS (Budgeted Cost of Work Schedule)


[ Schedule Expenditure] (Planned Value) ( PV) :

It is the budgeted cost of work to be completed till given date if the project runs
on schedule.

(2) SCWP (Budgeted Cost of Work Performed)


[Earned Value] (EV) :

It is the budgeted cost for the completed work. When any of the activity is
completed, it is considered to have "earned value" equivalent to its budgeted
cost. Therefore the total of budgeted cost for the work performed to date is the
total "earned value" of the project.

Prepared by – Vinayanand Rele


Page 192 of 380 24/11/2008
Project Management

(3) ACWP (Actual Cost of Work Performed)


[ Project Expenditure] (Actual Cost) (AC) :

It is the actual cost incurred in completing the work. It covers total cost of work
done, goods received and services used, whether: or not these have been
paid for.

(4) BCTW (Budgeted Cost for Total Work)

This is simply the total budgeted cost for the entire project work.

(5) ACC (Additional Cost for completion)

This represents the estimate for the additional cost required for completing the
project. Given the above terms, the project may be monitored along the following
lines :

Cost Variance : BCWP - ACWP

( if ACWP > BCWP, it indicates cost over run)

OR

Cost variance = Difference between the estimated cost of the activity and the
actual cost of the activity.

Schedule Variance (in cost terms) : BCWP – BCWS

Any difference between the schedule completion of an activity and the actual
completion of that activity.

If BCWP < BCWS, it indicates schedule delay.

BCWP
Cost Performance index (CPI) = ---------
ACWP

BCWP
Schedule Performance Index (SPI) = ---------
BCWS

Prepared by – Vinayanand Rele


Page 193 of 380 24/11/2008
Project Management

Theory

Experienced project managers utilize a technique called earned value management


(EVM) to assess a project's progress over time and allow project teams to understand
the health and performance 01 their projects EVM is also a good metric to share with
management. According to the Project Management Body of Knowledge:

Earned Value Management (EVM) is a method for integrating scope, schedule, and
resources for measuring project performance. It compares the amount of work or effort
that was planned with what was actually earned and spent to determine if cost and
schedule performance are as planned.

By comparing planned value (the ideal progress of the project) to the earned value (the
value of the project to date based on work or effort expanded), a project manager can
detect early if the project is going awry. If the schedule performance index is less than
1.0, then the project is in danger of going over schedule. If the cost performance index
is less than 1.0, then the project is in danger of going over budget. By monitoring and
reviewing these metrics, a project manager can report these statistics to management
so that they can determine whether to continue with the project: The process may be
revised for similar projects by learning from the statistics and modifying expectations.

Prepared by – Vinayanand Rele


Page 194 of 380 24/11/2008
Project Management

Problem – 1.

A company has obtained a fixed cost contract for the supply, installation, testing and
commissioning of 200 computers of the same specification at a cost of RS.600 Lakhs.
The company had estimated that it could supply, install, test and commission 10
computers per day so that the entire work can be completed in 20 days. The project
status was reviewed after the completion of 16 days. It was noted at the time of review
that 120 computers have been installed and the cost incurred was RS.380 Lakhs. It was
estimated at the time of the review that a sum of RS.260 Lakhs would be required for
completion of the pending work i.e. installation of the remaining 80 computers. Find :- .

Activity A Activity B
Budgeted cost in the period 50,000 30,000
Cumulative budget to date 200,000 75,000
Actual cost in the period 55,000 1,28,000
Cumulative actual cost to date 240,000 80,000
Variance for the period (5,000) 2,000
Cumulative variance to date (40,000) (5,000)

(i) Budgeted Cost of Work Scheduled (BCWS)


(ii) Budgeted Cost of Work Performed (BCWP)
(iii) Actual Cost of Work Performed (ACWP)
(iv) Cost Variance
(v) Schedule Variance
(vi) Cost Performance Index (CPI)
(vii) Schedule Performance Index (SPI)

Solution :

1. Project :

To install 200 computers in 20 days @ 10 computers per day.

Project Duration 20 days.

Rs, 600 Lakhs


2. Cost per computer = -------------------- = Rs. 3 Lakhs
200

Prepared by – Vinayanand Rele


Page 195 of 380 24/11/2008
Project Management

3. Review Period :

After 16 days

4. Budgeted Cost of Work Schedule (BCWS) (Schedule Expenditure).


[Planned Value (PV)]

= 16 Days x 10 Computers per day x RS.3 Lakhs per computer


= Rs.480 Lakhs.

= It is the budgeted cost of work to be completed till given date if the


project runs on schedule.

5. Budgeted Cost of Work Performed (BCWP) [ Earned Value (EV)]

= 120 Computers x RS.3 Lakhs / Computer = RS.360 Lakhs

It is the budgeted cost for the completed work. When any of the activity is
completed it is . considered to have "earned value" equivalent to its budgeted
cost. Therefore the total of budgeted cost of the work performed to date is the
total "earned value" of the project.

6. Actual Cost of Work Performed [ACWP]


[Project Expenditure] [ Actual Cost]

= Rs.380 Lakhs

It is the actual cost in completing the work. It covers total cost of work done,
goods received and serviced used, whether or not these have been paid for.

7. Budgeted Cost for Total Work (BCTW)

This is simply the total budgeted cost for the entire project work: RS.600 Lakhs.

8. Additional Cost for Completion (ACC)

(200 - 120) x RS.3 Lakhs per computer Computers yet to be installed = RS.240
Lakhs This represents the estimate for the additional cost required for completing
the project.

In the problem, it is given to be Rs.260 Lakhs.

Prepared by – Vinayanand Rele


Page 196 of 380 24/11/2008
Project Management

9. Cost Variance (CV) :

= BCWP - ACWP
= Rs.360 Lakhs - Rs.380 Lakhs
= (- Rs.29 ) Lakhs

if CV is negative, it indicates cost over run i.e. over the budget.


If CV is positive then it means' it is under the budget

10. Schedule Variance (SV) (in cost terms)

= BCWP - BCWS
= Rs. 360 Lakhs - Rs. 480 Lakhs
= ( - RS.120 Lakhs )

i.e. if SV is negative then it indicates that the project is behind the schedule, if it is
positive then the project is ahead of the schedule.

11. Cost Performance Index (CPI)

BCWP 360
= --------- = ------ = 0.9474 = 0.95
ACWP 380

For everyone rupee spent, we have done 95 paise worth of the work done or
achieved or for every one rupee spent, we received Re.0.95 worth of cost
performance.

A value > 1 indicates that the work is being completed better than planned,
whereas value < 1 indicates means that work is costing more than and / ore
proceeding more slowly than planned.

Prepared by – Vinayanand Rele


Page 197 of 380 24/11/2008
Project Management

12. Schedule Performance Index (SPI)

BCWP 360
= --------- = ------ = 0.75
BCWS 480

It is a measure of schedule efficiency.


[ Project is progressing at 75% of the rate originally planned ].

Or

For every rupee spent, we are only receiving Re.0.75 of schedule


performance.

13. Estimated Cost at Completion

Budgeted Cost for total work (BCTW)


= --------------------------------------------------
CPI

600 600
= ------ = ------------ = Rs. 633.33 Lakhs
0.95 360 / 380

∴ Cost over run = RS.633.33 - RS.600 = RS.33.33 Lakhs.


Or

ACC = RS.33.33 Lakhs

14. Estimated Time at Completion

Project Duration 20 Days


= ---------------------- = ----------- = 26.67 Days
SPI 0.75

∴ Time over run = 26.67 - 20 = 6.67 Days.

Prepared by – Vinayanand Rele


Page 198 of 380 24/11/2008
Project Management

Problem – 2.

A project was begun on 1st January 2005 and was expected to be completed by 30th
September 2005. The project is being reviewed on 30th June 2005 when the following
information has been developed.

( Rs )
Budgeted cost for work scheduled (BCWS) 15,00,000
Budgeted cost for work performed (BCWP) 14,00,000
Actual cost of work performed (ACWP) 16,00,000
Budgeted cost for total work (BCTW) 25,00,000
Additional cost for completion (ACC) 12,00,000

Solution :

Cost variance :

= BCWP - ACWP
= (1,400,000 - 1,600,000)
= - 200,000

Schedule variance in cost terms :

= BCWP - BCWS
= (1,400,000 - 1,500,000)
= - 100,000

Cost performance index (CPI) :

= BCWP / ACWP
= 1,400,000 / 1,600,000
= 08075

Schedule performance index (SPI) :

= BCWP / BCWS
= 1,400,000 / 1,500,000
= 0.933

Prepared by – Vinayanand Rele


Page 199 of 380 24/11/2008
Project Management

Problem – 3.

A project has begun on 1st April 2006 and was expected to be completed by 31st
December 2006. The project is being reviewed on 30th September 2006 when the
following information has been developed :

• Budgeted cost for work scheduled (BCWS) : Rs.6,000,000


• Budgeted cost for work performed (BCWP) : Rs.5,500,000
• Actual cost of work performed (ACWP) : Rs.5,800,000
• Budgeted cost for total work (BCTW) : Rs.10,000,000
• Additional cost for completio'n (ACC) : Rs.5,00,000

Determine the following :

i) Cost variance
ii) Schedule variance in cost term
iii) Cost performance index
iv) Schedule performance index

Solution :

This Problem is for Homework.

Prepared by – Vinayanand Rele


Page 200 of 380 24/11/2008
Project Management

Problem – 4.

A project with a total budget cost of Rs. 250 crores is scheduled to be completed in 80
weeks. A periodic review taken at the end of 50 weeks after commencement indicate
the following :

Earned value BCWP = Rs. 170 Crores


Actual Expenditure ACWP = Rs. 180 Crores
Scheduled earned value BCWS = Rs. 187 Crores

What do you interpret about the project progress till date with regard to time and cost on
the basis of following calculations.

(A) Cost Performance Index (CPI)


(B) Schedule Performance Index (SPI)
(C) Estimated Cost to complete
(D) Estimated time to complete

Solution :

This Problem is for Homework.

Prepared by – Vinayanand Rele


Page 201 of 380 24/11/2008
Project Management

Problem – 5.

A project comprising of 10 activities with total expected duration of 35 weeks was


reviewed on completion of 20 weeks after start The physical progress of various
activities as assessed and actual costs incurred till date are compared with expected
progress and budgeted figures as under :

Activity % Completion Cost (in Rs. Lakhs)


Schedule Actual Budgeted Actual
Total Till date
1 100 100 10.0 12.0
2 100 100 12.0 12.5
3 70 60 18.0 12.0
4 55 50 25.0 13.0
5 30 25 20.0 6.0
6 10 0 15.0 0.0
7 0 0 10.0 0.0
8 0 0 8.5 0.0
9 0 0 6.5 0.0
10 0 0 5.0 0.0
TOTAL 0 0 130.00 55.5

If the cost are incurred linearly in proportion to activity completion, find out the :

i) Budgeted Cost of Work Scheduled (BCWS)


ii) Budgeted Cost of Work Performed (BCWP)
iii) Cost Variance
iv) Cost Performance Index (CPI)
v) Schedule Performance Index (SPI)

Prepared by – Vinayanand Rele


Page 202 of 380 24/11/2008
Project Management

Solution :

BCWS BCWP
Schedule Actual Actual Budget Schedule Budget Schedule
Budget
Activity Completion Completion Cost Till Cost * Schedule Cost * Actual
Cost
% % date Competion % Competion %
1 100 100 10 12 10 x 100 % = 10 10 x 100 % = 10
2 100 100 12 12.5 12 x 100 % = 12 12 x 100 % = 12
3 70 60 18 12 18 x 70 % = 12.6 18 x 60 % = 10.8
4 55 50 25 13 25 x 55 % = 13.75 25 x 50 % = 12.5
5 30 25 20 6 20 x 30 % = 6 20 x 25 % = 5
6 10 0 15 0 15 x 10 % = 1.5 0
7 0 0 10 0 0 0
8 0 0 8.5 0 0 0
9 0 0 6.5 0 0 0
10 0 0 5.0 0 0 0
55.85 ( BCWS ) 50.3 ( BCWP )

Project Duration ( PD ) = 35 Weeks


BCTW = 130
BCWS = 55.85
BCWP = 50.3
Review period = 20 Weeks

Prepared by – Vinayanand Rele


Page 203 of 380 24/11/2008
Project Management

Cost Performance Estimated Cost At Additional Cost at


Cost Variance Remarks
Index Competion Completion

BCWP BCTW
= BCWP - ACWP CPI = ---------- = ----------
ACWP CPI

50.3 130
There is a Cost
= 50.3 - 55.5 = ------- = ---------- = 142.86 - 130
Overrun
55.5 0.91

= ( - 5. 2 ) = 0.91 = 142.86 = 12.86

Schedule Estimated Time At


Schedule Variance Additional Duration Remarks
Performance Index Competion

BCWP PD
= BCWP - BCWS SPI = ---------- = ----------
BCWS SPI

50.3 35
There is a DELAY
= 50.3 - 55.85 = ---------- = ---------- = 38.89 - 35
in the Project
55.85 0.9

= ( - 5. 55 ) = 0.9 = 38.89 = 3.89

Prepared by – Vinayanand Rele


Page 204 of 380 24/11/2008
Project Management

Problem – 6.

The progress observed at the end of the Seventeenth day from the beginning of a 12
day duration project is as given in the following table. The actual cost incurred till date is
reported to be Rs.3,100.

Draw a Gantt chart for the project and find the project performance on the basis of Cost
and Schedule performance Indices.

( Assume the activity costs are incurred uniformly over its duration ).

Estimated Budgeted Actual %


Immediate
Activity Duration in Cost of completion at
Predecessors
Days Activity the end of day 7
A - 3 500 100 %
B - 1 200 100 %
C A 4 800 75 %
D B 4 700 100 %
E B 5 500 95 %
F D 2 200 80 %
G E 3 500 50 %
H C 4 400 0%
I F 2 600 0%
J G 3 300 0%

Solution :

A B C D E F G H I J
- - A B B D E C F G
3 4 C 7 8
2 4
4
0 A H 12
8 10
0 3 4
12
5 7

1 F I
5 7 9
2
2
B 1
D
1 4
1

J
3 6 9 3
E
6 9
5
G
6 8
3
Prepared by – Vinayanand Rele
Page 205 of 380 24/11/2008
Project Management

BCWS BCWP
Schedule Actual Actual Budget Schedule Budget Schedule
Budget
Activity Completion Completion Cost Till Cost * Schedule Cost * Actual
Cost
% % date Competion % Competion %
A 100 100 600 600 x 100 % = 600 600 x 100 % = 600
B 100 100 200 200 x 100 % = 200 200 x 100 % = 200
C 100 75 800 800 x 100 % = 800 800 x 75 % = 600
D 100 100 700 700 x 100 % = 700 700 x 100 % = 700
E 100 95 500 500 x 100 % = 500 500 x 95 % = 475
F 100 80 200 200 x 100 % = 200 200 x 80 % = 160
G 33.33 50 500 500 x 33.33 % = 166.65 500 x 50 % = 250
H 0 0 400 0 0
I 0 0 600 0 0
J 0 0 300 0 0
3166.65 ( BCWS ) 2985 ( BCWP )

Project Duration ( PD ) = 12 Days


BCTW = 4,700
BCWS = 3,166.65
BCWP = 2,985
Review period = 7 Days

Prepared by – Vinayanand Rele


Page 206 of 380 24/11/2008
Project Management

Cost Performance Estimated Cost At Additional Cost at


Cost Variance Remarks
Index Competion Completion

BCWP BCTW
= BCWP - ACWP CPI = ---------- = ----------
ACWP CPI

2985 4700
There is a Cost
= 2985 - 3100 = ------- = ---------- = 4895 - 4700
Overrun
3100 0.96

= ( - 115 ) = 0.96 = 4895.83 = 195

Schedule Estimated Time At


Schedule Variance Additional Duration Remarks
Performance Index Competion

BCWP PD
= BCWP - BCWS SPI = ---------- = ----------
BCWS SPI

2985 12
There is a DELAY
= 2985 - 3166.85 = ---------- = ---------- = 12.76 - 12
in the Project
3166.85 0.94

= ( - 181. 85 ) = 0.94 = 12.76 0.76

Prepared by – Vinayanand Rele


Page 207 of 380 24/11/2008
Project Management

Problem – 7.

The following information is available at the end of 40th Day of a New Plant eraction
project. Determine, if the project is under control base on the named value evaluation
system. If not what is the likely extent of cost and time over runs at completion.

Activity Predecess Duration Total Budget Actual Cost Actual %


for Activity Till Date completion
( Rs ‘000 ) till Date
A - 10 330 250 100
B A 8 400 450 100
C A 2 350 380 100
D C 0 0 0 0
E B.D 18 405 400 70
F E 16 460 - 0
1905 1480

Solution :

This is for Home work

Prepared by – Vinayanand Rele


Page 208 of 380 24/11/2008
Project Management

Problem – 8.

A project has a budget of Rs 5,00,000 and is scheduled to be completed in one year.


The following table shows cumulative values of p!anned costs. Earned value and actual
costs at the end of each of the first four months.

Planned cost Earned Value Actua! Cost


Month No
(Rs.'000) (Rs.'000) (Rs.'000)
1 20 24 23.5
2 60 58 62
3 110 95 105
4 120 190 205

Calculate following values :

i) Cost performance index for each of the Four Months


ii) Schedule performance index for each of the four months
iii) Estimated Cost at complete based on the performance at the end of the fourth
month.
iv) Estimated time to complete based on the performance at the end of the fourth
month.

Solution :

This is for Home work

Prepared by – Vinayanand Rele


Page 209 of 380 24/11/2008
Project Management

Problem – 9.

A project with a total budget cost of Rs.25 crores is scheduled to be completed in 80


weeks. A periodic review taken at the end of 50 weeks after commencement indicate
the following :

Earned Value BCWP = Rs.17 Crores


Actual Expenditure ACWP = Rs.18 Crores
Schedule Earned Value BCWS = Rs.19 Crores

Compute and interpret the following :

(i) Cost Performance Index (CPI)


(ii) Schedule Performance Index (SPI)
(iii) Estimated Cost to Complete
(iv) Estimated time to-Complete.

Solution :

This is for Home work

Prepared by – Vinayanand Rele


Page 210 of 380 24/11/2008
Project Management

Problem – 10.

A project consisting of eight activities was revised on completion of 12 days after its
start.

Find the project performance on the basis of cost and schedule performance indices.
What is the estimated duration of the project ?

Actual %
Budgeted Cost Actual Cost of
Duration completion at
Activity of Activity Activity
( In days ) the end of day
( Rs. ‘000 ) ( till date )
12
A 1–2 5 60 62 100 %
B 2–3 7 70 70 100 %
C 2–4 5 73 73 100 %
D 2–5 7 82 70 90 %
E 3–6 6 69 0 0%
F 4–6 8 54 10 20 %
G 5–7 6 50 0 0%
H 6–7 5 40 0 0%

Solution :

This is for Home work

Prepared by – Vinayanand Rele


Page 211 of 380 24/11/2008
Project Management

PROJECT APPRAISAL
(Theory Notes)

Project appraisal is an appraisal of project objective, project design, project finance,


Economic, Technical and Commercial feasibility and project’s cost, benefit and profit.

It is a complete and systematic review of all aspects of a project.

It is a second look at the project feasibility report by a person other than one who is
associated with its concepts and preparations.

Market Appraisal

Market and commercial appraisal focuses on the following issues :

(1) Scope of Market Is the demand - supply gap substantial in growing market?
(2) Completion Will there be new entrants, expansion of existing ones, which will
enlarge the competition ?
(3) Prices Have the prices trends been favourable? Going up ?
(4) Exports Does the product have prospects of entering in to export market?
(5) Customers List of principal customers, their requirements. nature and selling
arrangement made with them.
(6) Selling Distribution Arrangement The arrangement made / proposal to be
made by the company is to be reviewed for its adequacy and efficiency.
(7) Government's Role Is there any government control on pllce / distribution /
allocation / imports or exports ?

Prepared by – Vinayanand Rele


Page 212 of 380 24/11/2008
Project Management

Technical Appraisal

Technical evaluation has direct bearing on the financial viability of the project: Field /
Areas covered by technical appraisal are :

(1) Location :

- Investigation with respect to suitability of location.

- Proximity to sources of raw material and markets, availability of power, fuel,


water and transport facilities, manpower availability and adequacy of
arrangement of disposal of wastes etc. are some of the critical elements to be
evaluated.

(2) Appropriate Technology :

- Is technology chosen appropriate and compatible with eauipments and raw


material to be used ?

- Is technology suitable from the point of view of size of plant and economic
operation of the plant ?

- Is technical - know how tie up adequately done and is providing necessary


guarantees ?

- In case of new process, has the project sponsor arranged the participation of
process supplier as a party in the project.

- Design and layout aspects of the projects are also examined. Will it suit to
product for maximum changes ?

- Will it be modifiable without much changes for accommodating new product


introduction. Can it be a Multi product design ?

- The design and layout is examined to see if minimum time is taken in


handling equipment, raw material, consumable and stores ?

- Technical appraisal also focuses on suitability and adequacy of the plant and
machinery, basis of selection, reasonabliness of cost, reputation and ability of
supplier, performance guarantee and operational efficiency of the
equipments.

Prepared by – Vinayanand Rele


Page 213 of 380 24/11/2008
Project Management

Finance Appraisal

Financial appraisal consists of issues like :

(1) Whether means of financing are adequately tied up and assured.

(2) Whether the structuring of the capital of the project is done in such a way that
acceptable debt: equity norm is used.

The project should have capacity to generate revenues and not cash flow such
that debt is serviced.

(3) Whether cash flows are estimated with reasonable underlying a assumptions.

(4) Applying the break-even point and studying margin of safety.

(5) Employing discounting criteria for acceptability of the project.

(a) NPV criterion


(b) Benefit cost ratio
(c) Internal rate of return.

(6) Use of non - discounting criteria :

(a) Payback period


(b) Accounting period
(c) Urgency

Prepared by – Vinayanand Rele


Page 214 of 380 24/11/2008
Project Management

APPRAISAL TECHNIQUES OTHER THAN FINANCIAL

Management and Organizational Appraisal

 Not quantifiable, but relies on judgment.

 Evaluation of technical and managerial competence, knowledge of the project,


integrity and past records.

 Do the promoters have adequate financial resources for the project ?

 Do the promoters / company envisage and plan an organizational structure


suitable for the proper management of the project during operational phase ?

 Information required for managerial appraisal will be through analysis of financial


position of existing business company / associate / sister companies / Bankers'
report etc. (from credit's angle)

 Performance and growth records of associated companies with which promoters


are connected. It shows entrepreneurial and managerial capability of promoters.

Prepared by – Vinayanand Rele


Page 215 of 380 24/11/2008
Project Management

Economic Appraisal

It involves the following questions :

 Would the project contributed any sector's development significantly ?

 Would the project contribute to the industrial development of the concerned


region ?

 \/Vhether project outlay will improve the socio - economic status of people, by
providing jobs.

 Does project have a favourable impact on export promotion, import substitution


and BOP status ?

Some of the measures used to evaluate economic viability are as follows :

(1) Economic Rate of Return (ERR)


(2) Domestic Resource Cost (DRC)
(3) Effective Rate of Production (ERP)
(4) Investment of Employment Ratio (IER)

Prepared by – Vinayanand Rele


Page 216 of 380 24/11/2008
Project Management

Environmental Analysis

The growing concern of environment, resource depletion and pollution have forced the
planners, policy makers and prc~ect implements to take care of impacts of the project
on environment :

The appraisal therefore evaluates project impact on :

(1) Air
(2) Water
(3) Monumental resources
(4) Land
(5) Sound
(6) Human inhabitation nearby
(7) Animals and Birds

The appraisal often relies upon environmental impact assessment (EIA) conducted by
independent body Such studies are conducted to reveal whether there is any impact of
project in a long run on environment If it is revealed that there will be no harmful change
in various social economic and physical attributes of environment of the project then the
project will be considered favourably.

Prepared by – Vinayanand Rele


Page 217 of 380 24/11/2008
Project Management

Forecasting Techniques

A time series is the data on any variable recorded over a constant time interval. The
time-frame of data recording may be an hour, a day, a week, a month, or a year,
depending on the type of event the data refer to. Hourly temperature in a particular city,
weekly earnings of workers in an industrial town, monthly prices of wheat, and annual
production of rice may be cited as examples.

All time series are subject to variations whose pattern and amplitude differ from one
period to another. Given this, the object of dealing with a time series is to study and
anlayse these variations with a view to knowing its past behaviour. A knowledge about
the past behaviour is useful for drawing inferences about its future course.

In an ever changing business and economic environment, it is necessary to have an


idea about what the future is going to bring forth. The anlaysis of time series is a means
to do so, especially as it acts as the basis to make a forecast. Economic and business
forecasts are made for being used by the policy makers to decide the future course of
action to survive and grow in a competitive environment.

The analysis of time series is useful not only for individual business concerns, it is
equally important for the Central and State Government for devising appropriate future
growth strategies. A close understanding of time series data on major national
aggregates such as population, national income, capital formation, etc. not only
provides crucial information about the strength or weakness of strategies adopted in the
past, but also help in setting future growth targets.

Time series is made up of four components

• Trend (T) represents the long term behavior of a time series. This would tell
whether the time series data reveal a steady upward or downward movement.

• Seasonal Variation (S) represents variation caused by season. Typically, this


shows variation in demand during peak and lean season. For example, demand for
snow tires will be at its peak during winter in USA.

• Cyclical Variation (C) represents the typical business cycles that occur
periodically in several years. For example, in stock market , you will witness cycle
of boom and cycle of recession that occur once in a while between many years.

• Random Variation (R) represents irregular variations that occur by chance having
no assignable cause. Random variation cannot be predicted.

Prepared by – Vinayanand Rele


Page 218 of 380 24/11/2008
Project Management

METHODS OF FORECASTING

Method - I ( FORECASTING BASED ON MOVING AVERAGES )

The moving averages method uses the average of the most recent n data values
in the time series as the forecast for the next period. Mathematically.

∑ ( Most resent n data Values )


Moving average = ------------------------------------------ …………. ( 1 )
N

The term moving indicates that, as a new observation becomes available for the time
series, it replaces the oldest observation in equation (1), and a new average is
computed. As a result, the average will change, or move, as new observations become
available.

To illustrate the moving averages method, consider the 12 weeks of data presented in
Table-1 These data show the number of gallons of gasoline sold by a gasoline
distributor over the past 12 weeks.

To use moving averages to forecast gasoline sales, we must first select the number of
data values to be included in the moving average. For example, let us compute
forecasts Using a 3 week moving average. The moving average calculation for the first
3 weeks of the gasoline sales time series is :

17 + 21 +19 57
Moving average (weeks 1 - 3) = ------------------ = ------ = 19
3 3

We then use this moving average value as the forecast for week 4. The actual value
observed in week 4 is 23, so the forecast error in week 4 is 23 - 19. In general, the error
associated with a forecast is the difference between the observed value of the time
series and the forecast.

The calculation for the second 3 week moving average is :


21 + 19 + 23
Moving average (weeks 2 -4) - -------------------- = 21
3

Prepared by – Vinayanand Rele


Page 219 of 380 24/11/2008
Project Management

Table 1

Week 1 2 3 4 5 5 7 8 9 10 11 12

Sales
17 21 19 23 18 16 20 18 22 20 15 22
(1000's of Gallons)

Hence, the forecast for week 5 is 21, and the error associated with this forecast is 18 -
21 -3. Thus, the forecast error may be positive or negative, depending on whether the
forecast is too low or too high. A complete summary of the 3 weeks moving average
calculations for the gasoline sales time series is shown in Table 2.

To forecast gasoline sales for week.13 using a 3 week moving average, we need to
compute the average of sales for weeks 10, 11 and 12. The calculation for this moving
average is :

20 + 15 + 22
Moving average (weeks 10 - 12) = ------------------- = 19
3

TABLE2

SUMMARY OF 3 WEEKS MOVING AVERAGE CALCULATION

Week Time Series Values Moving Average Forecast


1 17 -
2 21 -
3 19 -
4 23 19
5 18 21
6 16 20
7 20 19
8 18 18
9 22 18
10 20 20
11 15 20
12 22 19
13 - 19

Hence, the forecast for week 13 is 19, or 19,000 gallons of gasoline.

Prepared by – Vinayanand Rele


Page 220 of 380 24/11/2008
Project Management

Problem – 1.

You are given the following information about demand of an item :

Month 1 2 3 4 5 6 7 8 9 10 11
Demand 220 228 217 219 258 241 239 244 256 260 265

Calculate forecasted values using (i) three - monthly moving averages, (ii) five -
monthly moving averages.

Solution :

The required values are given in third and fourth columns of Table 1. The three
monthly values are obtained as (220 + 228 + 217) / 3 221.67, (228 + 217 +
219)/3 = 221.33 and so on. Similarly, five-monthly values are obtained by
considering five monthly data.

Table 1 Calculation of Forecasted Demand

5 - Monthly
3 - Monthly
Month Demand Y Moving
Average
Average
1 220 - -
2 228 - -
3 217 - -
4 219 221.67 -
5 258 221.33 -
6 241 231.33 228.40
7 239 239.33 232.60
8 244 246.00 234.80
9 256 241.33 240.20
10 260 246.33 247.60
11 265 253.33 248.00
12 - 260.33 252.80

Prepared by – Vinayanand Rele


Page 221 of 380 24/11/2008
Project Management

Problem – 2.

Obtain the profit forecasts using (i) four – yearly moving averages and (ii) five yearly
moving averages, from the following data relating to profits (in '000 Rs.)

Year 1986 1987 1988 1989 1990 1991 1992 1993


Profit 48 53 55 56 58 63 68 60
Year 1994 1995 1996 1997 1998 1999 2000 2001
Profit 61 68 58 63 70 76 83 88

Solution :

The given data and the required moving averages are shown in Table 2.

Table 2

4 - Yearly 5 - Yearly
Year Profit Moving Moving
Average Average
1986 48 - -
1987 53 - -
1988 55 - -
1989 56 - -
1990 58 53.00 -
1991 63 55.50 54.00
1992 68 58.00 57.00
1993 60 61.25 60.00
1994 61 62.25 61.00
1995 68 63.00 62.00
1996 58 64.25 64.00
1997 63 61.75 63.00
1998 70 62.50 62.00
1999 76 64.75 64.00
2000 83 66.75 67.00
2001 88 73.00 70.00
2002 - 79.25 76.00

Forecast Accuracy An important consideration in selecting a forecasting method is


the accuracy of the forecast.

Prepared by – Vinayanand Rele


Page 222 of 380 24/11/2008
Project Management

There are two methods to determine the accuracy of the forecast.

(i) Mean Absolute Deviation (MAD)


(ii) Mean Squared Error (MSE)

Of these two methods the MSE is often used measure of the accuracy of a forecasting
method.

As we indicated previously, to use the moving averages method, we must first select the
number of data values to be included in the moving average. Not surprisingly, for a
particular time series, different lengths of moving averages will affect the accuracy
of the forecast. One possible approach to choosing the number of values to be
included is to use trial and error to identify the length that minimizes the MSE, Then,
if we assume that the length that is best for the past will also be best for the future,
we would forecast the next value in the time series using the number of data values
that minimized the MSE for the historical time series.

To understand this concept let us take an illustration.

Continuing with the Gasoline example, let us find the 3-weekly moving averages and 5-
seekly moving averages and compute both MAD and MSE for these averages.

MAD and MSE computations for 3-weekly moving averages.

Moving
Forecast Absolute Squared
Week Profit Forecast
Error Forecast Forecast Error
Average

1 17 - - - -
2 21 - - - -
3 19 - - - -
4 23 19 4 4 16
5 18 21 -3 3 9
6 16 20 -4 4 16
7 20 19 1 1 1
8 18 18 0 0 0
9 22 18 4 4 16
10 20 20 0 0 0
11 15 20 -5 5 25
12 22 19 3 3 9
13 - 19 - - -
Total 24 92
24
Mean Absolute Deviation (MAD) = --------- = 2.67
9
Prepared by – Vinayanand Rele
Page 223 of 380 24/11/2008
Project Management

Where 9 is Observations.

92
Mean Absolute Deviation (MSE) = --------- = 10.22
9

MAD and MSE computations for 5-weekly moving averages.

Moving
Forecast Absolute Squared
Week Profit Forecast
Error Forecast Forecast Error
Average
1 17 - - - -
2 21 - - - -
3 19 - - - -
4 23 - - - -
5 18 - - - -
6 16 19.60 -4 3.6 12.96
7 20 19.40 1 0.6 0.36
8 18 19.20 -1 1.2 1.44
9 22 19.00 3 3 9
10 20 18.80 1 1.2 1.44
11 15 19.20 -4 4.2 17.64
12 22 19.00 3 3 9
13 - 19.40 - - -
Total 16.8 51.84

16.8
Mean Absolute Deviation (MAD) = ----------- = 2.4
7

51.84
Mean Absolute Deviation (MSE) = ------------ = 7.41
7

Based on MAD and MSE, 5-weekly moving averages are better. Therefore, forecast
for the 13th week is 19,400 gallons.

Sometimes MAD and MSE may give contradicting results. in that case we take decision
based on MSE.

Problem – 3.

Following data is available about, actual sales quantities for the past 14 years :

Prepared by – Vinayanand Rele


Page 224 of 380 24/11/2008
Project Management

Find the "forecast' for year 15 using Two Years' as well as Three Years' Moving
Average. Which of the two forecasts is more `reliable' on the basis of 'Mean Squared
Error' (MSE) criterion ?

Error
2 Years Error 3 Years
Actual ( Actual
Year Moving ( Actual Error Square Moving Error Square
Sales Forecasted
Average Forecasted ) Average
)
1 2,300 - - - - - -
2 2,200 - - - - - -
3 2,000 2250 -250 62,500 - - -
4 2,250 2100 150 22,500 2,167 83 6,889
5 2,600 2125 475 225,625 2,150 450 202,500
6 3,300 2425 875 765,625 2,283 1,017 1,034,289
7 3,500 2950 550 302,500 2,717 783 613,089
8 4,100 3400 700 490,000 3,133 967 935,089
9 3,800 3800 0 - 3,633 167 27,889
10 4,000 3950 50 2,500 3,800 200 40,000
11 4,300 3900 400 160,000 3,967 333 110,889
12 4,200 4150 50 2,500 4,033 167 27,889
13 4,800 4250 550 302,500 4,167 633 400,689
14 5,200 4500 700 490,000 4,433 767 588,289
15 5000 - 4,733 - -
Sum Square of Errors 2,826,250 3,987,501
Mean Square of Errors MSE 235,520.83 362,500.1

Answers:

1) Forecast based on 2 years moving average = 5,000


2) Forecast based on 3 years moving average = 4,733 3)
3) Mean Squared Error being less for the two year moving average, it is more reliable

( Note: 3-4 marks could be allotted if only the moving average forecasts are correctly
calculated without MSE )

Prepared by – Vinayanand Rele


Page 225 of 380 24/11/2008
Project Management

Problem – 4.

Following data is available about "actual sales quantities" for the 10 years

Year 1 2 3 4 5 6 7 8 9 10
Sales 230 220 200 240 230 260 300 240 280 320

Find the "forecast" for year 11 using "Two years" as well as "Three years "Moving
Averages. Which of the two forecasts is more reliable on the basis of "Mean Squared
Error" (MSE) criterion ?

Solution :

For Homework

Prepared by – Vinayanand Rele


Page 226 of 380 24/11/2008
Project Management

Problem – 5.

Compute the three year and five year moving average for the following set of data.
Compare the results. Comment.

Period Value Period Value Period Value


1 69 6 112 11 178
2 84 7 120 12 196
3 90 8 129 13 220
4 94 9 147 14 236
5 93 10 162 15 260

Solution :

For Homework

Prepared by – Vinayanand Rele


Page 227 of 380 24/11/2008
Project Management

Drawbacks of moving average forecast :

Moving average forecast is quick, easy and fairly inexpensive to implement. It provides
a reasonably good forecast for the immediate future (very short term). However,
practicing managers must remember the drawbacks given in the following paragraph.

• Moving averages do not react well to seasonal variations.


• All observations considered in a time horizon are given the same weights.
• A large amount of historical data should be gathered and maintained to update
forecast values.
• The choice of the period(n) is generally arbitrary.

Prepared by – Vinayanand Rele


Page 228 of 380 24/11/2008
Project Management

Method – II ( Exponential Smoothing )

Exponential smoothing is a forecasting method that is easy to use and is handled


efficiently by computers. Although it is a type of moving average technique, it involves
little record keeping of past data. The basic exponential smoothing formula can be
shown as follows :

New forecast = last period's forecast


+p (last period's actual demand - last period's forecast) ....................... (1)

Where p is a weight (or smoothing constant) that has a value between 0 and 1, inclusive.

Equation 1 can also be written mathematically as

F t = F t -1 + p (A t -1 – F t - 1 )

Where

Ft = new forecast (for time period t)


Ft-1 = previous forecast (for time period t – 1 )
p = smoothing constant (0 ≤ p ≤ 1 )
A t- 1 = previous period's actual demand

The concept here is not complex. The latest estimate of demand is equal to our old
estimate adjusted by a fraction of the error (last period's actual demand minus the old
estimate).

The smoothing constant, a, can be changed to give more weight to recent data when
the value is high, or more weight to past data when it is low. For example, when a =
0.5, it can be shown mathematically that the new forecast is based almost entirely
on demand in the past three periods. When a = 0.1, the forecast places little weight on
recent demand and takes many periods (about 19) of historic values into account.

Prepared by – Vinayanand Rele


Page 229 of 380 24/11/2008
Project Management

Example

In January, a demand for 142 of a certain car model for February was predicted by a
dealer. Actual February demand was 153 cars. Using a smoothing constant of a = 0.20,
we can forecast of March demand using the exponential smoothing model.

Substituting into the formula, we obtain.

New forecast (for March demand) = 142 + 0.2 (153 — 142) = 144.2

Thus, the demand forecast for the cars in March is 144.

Suppose that actual demand for the cars in March was 136. A forecast for the demand
in April, using the exponential smoothing model with a constant of a = 0.20, can be
made.

New forecast (for April demand) = 144.2 + 0.2 (136 — 144.2) = 142,6, or 143 cars.

Selecting the Smoothing Constant The exponential smoothing approach is easy to use
and has been applied successfully by banks, manufacturing companies, wholesalers,
and other organizations. The appropriate value of the smoothing constant, a, however,
can make the difference between an accurate forecast and an inaccurate forecast. In
picking a value for the smoothing constant, the objective is to obtain the most accurate
forecast.

Several values of the smoothing constant may be tried, and the one with the lowest
MAD (Mean Absolute Deviation) could be selected

Prepared by – Vinayanand Rele


Page 230 of 380 24/11/2008
Project Management

Example :

Let us apply this concept with a trial and error testing of two values of a in the following
example. The port of Baltimore has unloaded large quantities of grain from ships
during the past eight quarters. The port's operations manager wants to test the use of
exponential smoothing to see how well the technique works in predicting tonnage
unloaded. He assumes that the forecast of grain unloaded in the first quarter was
175 tons. Two values of a are examined : a = 0.10 and a = 0.50. Table shows the
detailed calculations for a = 0.10 only.

Table - 1

Actual Tonnage Rounded Forecast


Quarter Rounded Forecast With a = 0.10
Unloaded With a = 0.50*
1 180 175 175
2 168 176 = 175.00 + 0.10 (180 - 175) 178
3 159 175 = 175.50 + 0.10 (168 - 175.50) 173
4 175 173 = 174.75 + 0.10 (159 - 174.75) 166
5 190 173 = 173.18 + 0.10 (175 - 173.18) 170
6 205 175 = 173.36 + 0.10 (190 - 173.36) 180
7 180 178 = 175.02 + 0.10 (205 - 175.02) 193
8 182 178 = 178.02 + 0.10 (180 - 178.02) 186
9 ? 179 = 178.22 + 0.10 (182 - 178.22) 184

Note : * forecast rounded to the nearest one.

To evaluate the accuracy of each smoothing constant, we can compute the absolute
deviations and MADs (see table). Based on this analysis, a smoothing constant of a =
0.10 is preferred to a = 0.50 because it’s MAD is smaller.

Prepared by – Vinayanand Rele


Page 231 of 380 24/11/2008
Project Management

Table - 2

Quarter
Absolute
Actual Rounded Absolute Rounded
Deviations
Tonnage Forecast Deviations Forecast with
With p = 0.10 for p =
Unloaded for p = 0.10 p = 0.50
0.50
1 180 175 5 175 5
2 168 176 8 178 10
3 159 175 16 173 14
4 175 173 2 166 9
5 190 173 17 170 20
6 205 175 30 180 25
7 180 178 2 193 13
8 182 178 4 186 4
Sum of absolute deviations 84 100

∑ | deviations |
MAD = ---------------------- = 10.50 ( for p = 0.1 )
n
MAD = = 12.50 ( for p = 0.5 )

Prepared by – Vinayanand Rele


Page 232 of 380 24/11/2008
Project Management

Problem - 1

A company manufacturing Xerox machines experienced the following sales for theft Xerox
machines during their busiest time of the year.

Month Actual Demand


May 120
June 180
July 150

Forecasted demand for May was 80 units. Using exponential something with a =
0.20, forecast the demand for August.

Solution :

For Homework

Prepared by – Vinayanand Rele


Page 233 of 380 24/11/2008
Project Management

4th April, 2008.

Lecture – XII.

DECISION TREE
Introduction

A decision tree is a schematic diagram of a sequence of alternative decisions and the


results of those decisions.

A decision tree is beneficial for several reasons :

First, it provides a pictorial representation of the sequential decision


process which facilitates understanding of the process.

Second, it makes the expected value computation easier as they can be


performed directly on the tree diagram.

Third, the actions of more than one decision maker can be considered.

Drawing a decision tree (the basic rules)

Every decision tree starts from a decision point with the decision options that are
currently being considered.

(a) There should be a fine, or branch, for each option or alternative.


(b) It helps to identify the decision point, and any subsequent decision points in the
tree, with a symbol. Here, we shall use a square shape.

It is conventional to draw decision trees from left to right, and so a decision tree will
start as follows.

D1
C

Prepared by – Vinayanand Rele


Page 234 of 380 24/11/2008
Project Management

The square is the decision point, and A, B, C and D represent four alternatives from
which choice must be made.

If the outcome from any choice is certain, the branch of the decision tree for that
alternative is complete.

If on the other hand, the outcome of a particular choice is uncertain, the various possible
outcomes must be shown. We show this on a decision tree by inserting an outcome
point on the branch of the tree. Each possible outcome is then shown as a
subsidiary branch, coming out from the outcome point. The probability of each
outcome occurring should be written on to the branch of the tree which represents
that outcome.

To distinguish decision points from outcome points, a circle will be used as the
symbol for an outcome point.

D1
High Sales
0.6
B
1

Low Sales
0.4

In the example above, there are two choices facing the decision maker, A and B. The
outcome if A is chosen is known with certainty, but if 8 is chosen, there are two
possible outcomes, high sales (0.6 probability) or low sales ( 0.4 probability ). When
several outcomes are possible it is usually simpler to show two or more stages of
outcome points on the decision tree.

Prepared by – Vinayanand Rele


Page 235 of 380 24/11/2008
Project Management

Example:

A company can choose to launch a new product XYZ or not. If the product is
launched, expected sales and expected unit costs might be as follows :

Sales
Units Probability Unit cost Probability
10,000 0.8 Rs. 6 0.7
15,000 0.2 Rs. 8 0.3

a) The decision tree could be drawn as follows :

Cost Rs. 6
0.7
Sales 10,000
1
0.8
Cost Rs. 8
Launch
3 0.3
Cost Rs. 6
0.7
Sales 15,000
2
0.2
Cost Rs. 8
D1
0.3

Do Not Lauch

Prepared by – Vinayanand Rele


Page 236 of 380 24/11/2008
Project Management

b) The layout shown above will usually be easier to use than the alternative way
of drawing the tree which is shown below :

Sales 10,000, Cost Rs. 6


0.56
Sales 10,000, Cost Rs. 8
Launch 0.24
1
Sales 15,000, Cost Rs. 6
0.14
D1 Sales 15,000, Cost Rs. 8
0.06

Do Not Lauch

Sometimes, a decision taken now will lead to other decisions to be taken in the future.
When this situation arises, the decision tree can be drawn as a two-stage tree, as
follows :
Decision A

D2
0.7
Decision B
Decision X
1

Decision C

D3
0.3
Decision D
D1

Decision Y

Prepared by – Vinayanand Rele


Page 237 of 380 24/11/2008
Project Management

In this tree, either a choice between A and B or else a choice between C and D will be
made depending on the outcome which occurs after choosing X.

The decision tree should be in chronological order from left to right. When there are two-
stage, decision trees, the first decision in time should be drawn on the left.

Advantages

Decision trees are a useful management tool. They allow manages to consider the
options they are facing and the possible consequence of those options. Moreover,
provided that the parameters included in the decision tree have been estimated correctly,
managers, choose the best course of action and hopefully save money. Bear in mind,
however, that the calculation of probabilities is highly subjective and on occasions, only a
small error in the calculation of probabilities or expected values could lead to an incorrect
decision being taken.

Decision trees are useful in giving a simple diagrammatic representation of the various
options open to management, and the possible outcomes of each options. They also
draw attention to the immediate decisions to be made, and may help management to
avoid wasting unnecessary time deliberating later decisions.

A decision tree might also help management to eliminate decision options which are not
worth considering further, and to focus attention on the more viable options.

A decision tree is a simplified representation of reality, however, it may omit some


possible decision options, or it may simplify the possible outcomes. For example, in this
question, 'success' and 'failure' are two extreme outcomes, whereas a variety of
outcomes between success and failure may be possible. The decision tree is therefore
likely to be a simplification of reality.

If management choose to base their decisions on the expected value criterion, choosing
the option with the highest expected value of profit, then decision trees (along with other
methods of calculating and presenting expected value figures) are a useful guide to
decision making.

Expected values reflect the weighted average of probable outcomes. For one-off
decisions, a weighted average value may be an inappropriate basis for comparing
options. For example, if there is a 0.8 probability of earning Rs.100,000 and a 0.2
probability of losing Rs.50,000,000, the expected value of profit would be -Rs.99,20,000.
If the decision is non recurring, management may need to consider all possible outcomes,
and especially the worst possible outcomes. If the company cannot afford to lose
Rs.50,000,000, a 0.2 probability of such a loss might be unacceptable.

Decision trees, or expected value calculations, are most useful where decisions are of a
recurring nature, where the long-run average profit should be approximately the expected
value of the profit for a single decision. Examples of such situations would be :

Prepared by – Vinayanand Rele


Page 238 of 380 24/11/2008
Project Management

i) Decisions on test drilling for oil, where a company carries out many tests each year,
ii) Decisions on whether or not to launch a new product on the market, where a large
number of new products are considered each year,
iii) Decisions on whether or not to obtain market research information for particular
project, where market research is in common use through out the organization.

Prepared by – Vinayanand Rele


Page 239 of 380 24/11/2008
Project Management

Example.

A company has an investable surplus of Rs.100 Crores. Investing this amount in this
existing business can give a certain return of 8.0%. Alternatively, there is an opportunity
for diversification which, if successful, is estimated to bring a return of 17.0%. However if
diversification is not successful, expected return will be only 2.0%. What must be the
probabilities for two outcomes of diversification in order to make the diversification
worthwhile?

Let probability of success in diversification be lx'. Hence probability of failure be (1 - x).


Evaluation of diversification should be at least be 8% i.e. Rs.8.0 crores if not more.

Existing Business 8.0 Cr

D1 Success X % 17.0 Cr

Failure ( 1 – X ) % 2.0 Cr

Hence,

8 = 17 X + 2 ( 1 – X )

8 = 17 X + 2 – 2X

8 - 2 = 15X

6 = 15X

6
X = ------ = 0.4
15

Probability of success in diversification should be at least 0.4 or 40.0%

Prepared by – Vinayanand Rele


Page 240 of 380 24/11/2008
Project Management

Problem – 1.

A manufacturing company has to select one of the two products A or B for manufacturing.
Product A required investment of Rs.20,000 and product B, Rs.40,000. Market research
survey shows high medium and low demands with corresponding probabilities and return
from sales, in Rs. thousand, for the two products, in the following table.

Probability Return from Sales ( Rs in ‘000 )


Market
A B A B
High 0.4 0.3 50 80
Medium 0.3 0.5 30 60
Low 0.3 0.2 10 50

Construct an appropriate Decision Tree. What decision the company should take?

Solution :

High
Sale Rs 50,000/-
0.4
* Rs 32,000/- Medium
Product - A 1 Sale Rs 30,000/-
0.3
Investment Low
Rs 20,000 Sale Rs 10,000/-
D1 0.3
High
Product - B Sale Rs 80,000/-
0.3
Investment ** Rs 64,000/- Medium
2 Sale Rs 60,000/-
Rs 40,000 0.5

Low Sale Rs 50,000/-


0.2
Roll Back Technique to evaluate Decision Tree.

We need to calculate the EMV ( Earnest Monitory Value ) for each alternate.

EMV at 1

= 50,000 x 0.4 +
30,000 x 0.3 +
10,000 x 0.3

= 32,000 *

Prepared by – Vinayanand Rele


Page 241 of 380 24/11/2008
Project Management

EMV at 2

= 80,000 x 0.3 +
60,000 x 0.5 +
50,000 x 0.2

= 64,000 **

So, Net Profit from

Product – A Product – B

32,000 64,000
- 20,000 - 40,000
------------- --------------
12,000 24,000

∴ Optimum decision at D1 is Product “B”

Prepared by – Vinayanand Rele


Page 242 of 380 24/11/2008
Project Management

Problem – 2.

Alfa Industries has to decide whether to set up a large plant or a small plant for its new
range of refrigerators. A large plant will cost the company Rs.25 lakhs while a small plant
will cost Rs.12 lakhs. An extensive market survey and a cost profit volume analysis
carried out by the company reveal the following.

High demand Probability = 0.5


Moderate demand Probability = 0.3
Low demand Probability = 0.2

(a) A large plant with high demand will yield an annual profit of Rs.100 lakhs.
(b) A large plant with moderate demand will yield an annual profit of Rs.60 lakhs.
(c) A large plant with low demand will lose Rs.20 lakhs annually because of production
inefficiencies.
(d) A small plant with high demand would yield Rs.25 lakhs annually, taking into account
the cost of lost sales due to inability to meet demand.
(e) A small plant with moderate demand will yield Rs.35 lakhs, as the losses due to lost
sales will be lower.
(f) A small plant with low demand will yield Rs.45 lakhs annually, as the plant capacity
and demand will match.

Draw a Decision Tree and find optimum solution.

Prepared by – Vinayanand Rele


Page 243 of 380 24/11/2008
Project Management

Solution :

( All figures in Lakhs )


High
Sale Rs 100
0.5
* Rs 72 Medium
Large Plant 1 Sale Rs 60
0.3
Investment Rs 25 Low
Sale Rs 20
D1 0.2
High
Small Plant Sale Rs 25
0.5

Investment Rs 12 ** Rs 32 Medium
2 Sale Rs 35
0.3

Low Sale Rs 45
0.2
EMV at 1

= 100 x 0.5 +
60 x 0.3 +
20 x 0.2

= 72 *

EMV at 2

= 25 x 0.5 +
35 x 0.3 +
45 x 0.2

= 32 *

So, Net Profit from

Large Plant Small Plant

72 32
- 25 - 12
--------- ---------
47 20

∴ Optimum decision at D1 is build the Large Plant.


Prepared by – Vinayanand Rele
Page 244 of 380 24/11/2008
Project Management

Problem – 3.

A financial advisor has recommended two possible mutual funds for investment: Fund A
and Fund B. The return that will be achieved by each of these depends on whether
the economy is good, fair, or poor. A payoff table has been constructed to illustrate this
situation.

State of Nature
Investment
Good Economy Fair Economy Poor Economy
Fund A $10,000 $ 2,000 - $ 5,000
Fund B $ 6,000 $ 4,000 0
Probability 0.2 0.3 0.5

(a) Draw the decision tree to represent this situation.


(b) Perform the necessary calculations to determine which of the two mutual funds is
better. Which one should you choose to maximize the expected value?

Solution :

( All figures in $ )
Good
10,000
0.2
* 100 Fair
Fund A 1 2,000
0.3

Poor
( 5,000 )
D1 0.5
Good
Fund B 6,000
0.2
** 2400 Fair
2 4,000
0.3

Poor 0
0.5
EMV at 1

= 10,000 x 0.2 +
2,000 x 0.3 +
- 5,000 x 0.5

= 100 *

Prepared by – Vinayanand Rele


Page 245 of 380 24/11/2008
Project Management

EMV at 2

= 6,000 x 0.2 +
4,000 x 0.3

= 2400 **

∴ It is advisable to Invest in the Mutual Fund B.

Prepared by – Vinayanand Rele


Page 246 of 380 24/11/2008
Project Management

Problem – 4.

Grow fast Company is evaluating four alternative single-period investment opportunities


whose returns are based on the state of the economy. The possible states of the
economy and the associated probability distribution are as follows :

State Fair Good Grate


Probability 0.2 0.5 0.3

The returns for each investment opportunity and each state of the economy are as
follows :

Alternative Fair Good Great


W Rs.1,000 Rs.3,000 Rs.6,000
X Rs. 500 Rs.4,500 Rs.6,800
Y Rs.2,000 Rs.5,000 Rs.8,000
Z Rs.4,000 Rs.6.000 Rs.8,500

Using the decision tree approach, determine the expected return for each alternative.
Which alternative investment proposal would you recommend if the expected monetary
value criterion is to be employed ?

Prepared by – Vinayanand Rele


Page 247 of 380 24/11/2008
Project Management

Solution :
Fair
1,000
0.2
* 3,500 Good
1 3,000
0.5

Grate
6,000
Alternate W 0.3
Fair
500
0.2
** 4,390 Good
2 4,500
Alternate X 0.5

Grate 6,800
0.3
D1

Fair
Alternate Y 2,000
0.2
*** 5,300 Good
3 5,000
0.5

Grate
Alternate Z 8,000
0.3
Fair
4,000
0.2
**** 6,350 Good
4 6,000
0.5

Grate 8,500
0.3

1
EMV at

= 1,000 x 0.2 +
3,000 x 0.5 +
6,000 x 0.3

= 3,500 *

Prepared by – Vinayanand Rele


Page 248 of 380 24/11/2008
Project Management

2
EMV at

= 500 x 0.2 +
4,500 x 0.5 +
6,800 x 0.3

= 4,390 **

3
EMV at

= 2,000 x 0.2 +
5,000 x 0.5 +
8,000 x 0.3

= 5,300 ***

4
EMV at

= 4,000 x 0.2 +
6,000 x 0.5 +
8,500 x 0.3

= 6,350 ****

∴ Alternate Z is the Better Proporals.

Prepared by – Vinayanand Rele


Page 249 of 380 24/11/2008
Project Management

Problem – 5.

Company, X has to decide whether to manufacture and market product A or product B.


Profits will be the decision criterion. In case product A is manufactured and marketed,
there is :

i) A 40 percent chance or probability 0.4 that sales will be excellent and profit
realized will be Rs. One lakh.
ii) A 50 percent chance (or 0.5 probability ) of sales being merely fair, realizing a
profit of Rs.60,000 and,
iii) A 10 percent chance (or 0.1 probability ) of poor sales and loss of Rs.20,000.

Similarly for Product B,


a) A 70 percent chance or (0.7 probability ) of realizing a profit of Rs.1,50,000
and,
b) A 30 percent chance (or 0.3 probability) of making a loss of Rs.30,000.

Which product should be manufactured and marketed ?

Solution :

( All figures in Rs. )


Excellent
1,00,000
0.4
* Rs, 30,000 Fair
Product A 1 60,000
0.5

Poor
( 20,000 )
D1 0.1
Excellent
Product B 1.50,000
0.7
** 2400
2

Poor ( 30.000 )
0.3

Prepared by – Vinayanand Rele


Page 250 of 380 24/11/2008
Project Management

EMV at 1

= 1,00,000 x 0.4 +
60,000 x 0.5 +
- 20,000 x 0.2

= 30,000 *

EMV at 2

= 1,50,000 x 0.7 +
- 30,000 x 0.3

= 96,000 *

∴ Product B is Referred.

Prepared by – Vinayanand Rele


Page 251 of 380 24/11/2008
Project Management

Problem – 6.

The investment staff of TNC Bank is considering four investment proposals for a client
Shares, Bonds, Real Estate and Savings Certificates. These investments will be held for
one year. The past data regarding the four proposals are given below :

Share : There is a 25 percent chance that shares will decline by 10 percent, a 30


percent chance that they will remain stable and a 45 percent chance that they will
increase in value by 15 percent. Also the shares under consideration do not pay any
dividends.

Bonds : These bonds stand a 40 percent chance of increase in value by 5 percent and
60 percent chance of remaining stable and they yield 12 percent.

Real Estate : This proposal has a 20 percent chance of increasing 30 percent in value,
a 25 percent chance of increasing in 20 percent value, a 40 percent chance of
increasing in 10 percent value, a 10 percent chance of remaining stable and a 5 percent
chance of losing 5 percent of its value.

Saving Certificate : These certificates yield 8 1/2 percent with certainty.

Use a decision tree to structure the alternatives to the investment staff and using the
expected value criterion, choose the alternative with the highest expected value.

Prepared by – Vinayanand Rele


Page 252 of 380 24/11/2008
Project Management

Solution :

Assumption, Initial Investment is Rs. 100/- ( Figures in Rs. )

Decline
100 – 10 % = 90
0.25
* 51.75 Stable
1 100
0.30

Increase
100 + 15 % = 115
0.45
Shares
Increase 100 + 5 % = 105
0.40 + 12 = 117
** 114
2
Bonds
Stable
100 + 12 = 112
0.60

30 % Increase 100 + 15 % = 120


D1
0.20
20 % Increase
Real Estate 100 + 25 % = 125
0.25
*** 113.75 10 % Increase
3 100 + 10 % = 110
0.40

Stable
Saving Certificate 100
0.10
5 % Decrease
0.05 100 + 5 % = 90

**** 108 Increase 8.5 %


4 100 + 8.5 % = 108.50
1.0

1
EMV at

= 90 x 0.25 +
100 x 0.30 +
115 x 0.45

= 51.75 *

Prepared by – Vinayanand Rele


Page 253 of 380 24/11/2008
Project Management

2
EMV at

= 117 x 0.40 +
112 x 0.60

= 114 **

3
EMV at

= 120 x 0.20 +
125 x 0.25 +
110 x 0.40 +
100 x 0.10 +
90 x 0.05

= 113.75 ***

4
EMV at

= 108 x 1.00

= 108 ****

∴ Bond is Referred option

Prepared by – Vinayanand Rele


Page 254 of 380 24/11/2008
Project Management

Problem – 7.

Suppose you have Rs.5,00,000 (Rs. Five Lakh) to invest in share market. Your broker
has suggested to invest in either Company A or Company B.

Shares in Company A are risky but could yield a 40% return on investment during next
year if stock market conditions are favourable ("Bull" market). If stock market conditions
are not favourable ("Bear" market), the stock many loose 20% of its value.

Company B provides safe investment with 15% return in a "bull" market and only 5% in
a "bear" market. The chance of the market being "bull" is 55%.

Draw the decision tree and specify optimum course of action.

Solution :

Here important statement is “The chance of the market being "bull" is 55%.”
( All figures in Lakhs )
Bull Market
5 + 40 % = 7
0.55
* Rs 5.65
Company A 1

Investment Rs 5 L Bear Market


5 - 20 % = 4
D1 0.45
Bull Market 5 + 15 % = 5.75
Company B
0.55
** Rs 5.52
Investment Rs 5 L 2

Bear Market
5 + 5 % = 5.25
1 0.45
EMV at

= 7,00,000 x 0.55 +
4,00,000 x 0.45
= 5,65,000 *

EMV at 2

= 5,65,000 x 0.55 +
5,25,000 x 0.45
= 5,52,500 **

∴ Company – A is a preferred option.


Prepared by – Vinayanand Rele
Page 255 of 380 24/11/2008
Project Management

Problem – 8.

A road transport company renews its fleet of luxury buses every 4 years. By replacing
the entire fleet at one time favourable purchase prices are obtained. The size of the
present fleet is 10 buses. The proprietor of the company could vary the size of the fleet
depending on the economic climate. He estimates that if he buys 8 buses, he could earn
a profit of Rs.10,000/- per bus over the next 4 years if the economic climate is upbeat,
Rs.8000/- per bus if the climate is moderate and Rs.5000/- per bus if the economic
climate is depressing. If he buys 12 buses , he could earn a profit of respectively
Rs.13000/-, Rs.8000/- or Rs.1000/- per bus depending on the three types of economic
climates. If he keeps the fleet at its present strength , the profits per bus are respectively
Rs.12000/-, Rs.8000/- and Rs.3500/- over the next four years. He estimates that, the
chance that the economic climate will be upbeat is 0.4 and that it will be moderate is
0.3. Use decision tree to get proprietor's optimal decision.

Solution :

Upbeat
Rs 10,000
0.4
* Rs 63,200 Moderate
1 Rs 8,000
0.3
8 Buses Depressing
Rs 5,000
0.2
Upbeat
Rs 12,000
0.4
10 Buses ** Rs 82,500 Moderate
D1 2 Rs 8,000
0.3
Depressing
Rs 3,500
0.2
12 Buses
Upbeat
Rs 13,000
0.4
*** Rs 94,800 Moderate
3 Rs 8,000
0.3

Depressing
Rs 10,000
0.2

Prepared by – Vinayanand Rele


Page 256 of 380 24/11/2008
Project Management

EMV at 1

= 10,000 x 0.40 +
8,000 x 0.30 +
5,000 x 0.30

= 7,900

As this fleet has 8 buses, 8 x 7,900 = 63,200/- *

EMV at 2

= 12,000 x 0.40 +
8,000 x 0.30 +
3,500 x 0.30

= 8,250

As this fleet has 10 buses, 10 x 8,250 = 82,500/- **

EMV at 3

= 13,000 x 0.40 +
8,000 x 0.30 +
1,000 x 0.30

= 7,900

As this fleet has 12 buses, 12 x 7,900 = 94,800/- ***

∴ 12 Buses Fleet is Recomended.

Prepared by – Vinayanand Rele


Page 257 of 380 24/11/2008
Project Management

Problem – 9.

Suppose that you want to invest Rs.10,000 in the stock market by buying shares in one
of two companies A and B. Share in company A are risky but could yield a 50% return
on investment during the next year. If the stock market conditions are not favorable (i.e.
"bear" market), the stock may loose 20% of its value. Company B provides safe
investment with 15% return in a "bull" market and only 5% in a "bear" market. All the
publications you have consulted are predicting a 60% chance for a 'bull" market and
40% for "bear" market.

Draw the decision tree, and specify a course of action.

Prepared by – Vinayanand Rele


Page 258 of 380 24/11/2008
Project Management

Problem – 10.

'Thanda Cool' Company has developed a new cold drink. A total of Rs.25 lakh is spent
on the new product. One plan is to market it in small cans with other products of the
company . The plan will cost Rs.8 lakhs and it might result in high, moderate or low
market response with probabilities 0.3, 0.5 and 0.2 respectively, with revenues of Rs.55
lakhs, Rs.35 lakhs and Rs.15 lakhs for the corresponding market responses. The
second marketing plan is to fully concentrate on T. V. advertisements with a cost of
Rs.20 lakhs. The resulting market response can be either excellent or very good, with
probabilities 0.4 and 0.6 respectively. The revenues in these cases will be Rs.50 lakhs
and Rs.35 lakhs respectively. Draw a decision tree to determine the plan the company
should follow, to maximize the profit.

Prepared by – Vinayanand Rele


Page 259 of 380 24/11/2008
Project Management

Problem – 11.

A company has the opportunity of marketing a new package of computer games. It has
two possible courses of action : to test market on a limited scale or to give up the project
completely. A test market would cost Rs.1,60,000 and current evidence suggests that
consumer reaction is equally likely to be "Positive" or 'Negative". If the reaction to the
test marketing were to be "Positive", the company could either market the computer
games nationally or still give up the project completely.

Research suggests that a national launch might result in the following sales :

Contribution
Sales Probability
Rs. Million
High 1.2 0.25
Average 0.3 0.50
Low -0.24 0.25

If the test marketing were to yield "Negative" results, the company would give up the
project. Giving up the project at any point would result in a contribution of Rs,60,000
from the sale of copyright etc. to another manufacturer.

You are required to:

(a) Draw a decision tree to represent this situation including all relevant probabilities
and financial values.
(b) Recommend a course of action for the company on the basis of expected values.

Prepared by – Vinayanand Rele


Page 260 of 380 24/11/2008
Project Management

Solution :

Give Up Cost Rs. 60,000/-


2

D2 High
Rs 12,00,000
0.25
Positive
Market Average
0.5 1 Rs 3,00,000
3 0.50

Low
Limited Negative Rs (-2,40,000)
Scale Cost Rs. 60,000/- 0.25
0.5
Cost Rs. 1,60,000/-

D1

Give-up
4
Cost Rs. 60,000/-

EMV at 1

= 12,00,000 x 0.25 +
3,00,000 x 0.50 +
- 2,40,000 x 0.25

= 3,90,000 *

EMV at 2

= 3,90,000 x 0.5 +
60,000 x 0.5

= 2,45,000 **
( In – Complete Problem )
Prepared by – Vinayanand Rele
Page 261 of 380 24/11/2008
Project Management

Problem – 12.

Raman Industries Ltd. has a new product which they expect has a great potential. At
present they have two courses of action open to them. To test market (S1) and to drop
product (S2).

Test market will cost Rs.50,000 and the response could be positive or negative with
probabilities 0.70 and 0.30 respectively. If the result of the test marketing is positive they
could either market it with full scale or drop the product. If they market with full scale
then the result might be low, medium or high demand and the respective net pay offs
would be Rs.1,00,000, Rs.2,00,000 or Rs.5,00,000. The outcomes have probabilities of
0.25, 0.55 and 0.20 respectively. If the result of the test marketing is negative they have
decided to drop the product.

If at any point they drop the product there is a net gain of Rs.25,000/- from the sale of
the scrap. All financial values have been discounted to the present. Draw a decision tree
for the problem and indicate the most preferred decision.

Problem – 13.

A businessman has two independent investments A and B available to him but he lacks
of capital to undertake both simultaneously. He can choose to take A first and then stop
or if A s successful then take B or vice versa. The probability of success of A is 0.7 while
for B it is 0.4. Both investments require an initial capital outlay of Rs.2,00,000 and both
return nothing if unsuccessful. Successful completion of A will return Rs.30,000 over
cost and the successful of B will return Rs.15,000 over cost. Draw the decision tree and
determine the best strategy.

Prepared by – Vinayanand Rele


Page 262 of 380 24/11/2008
Project Management

Problem – 14.

An investment company is evaluating four alternative investment opportunities whose


returns are based on the state of the economy. The possible states of economy and
associated probabilities are as follows :

State of Economy Fair Good Very Good


Probability 0.2 0.5 0.3

The returns for each investment opportunity and each state of the economy are as
follows :

State of Economy
Investment
Fair Good Very Good
Shares 1000 3000 6000
Bonds 500 4500 6800
Real Estate 0 5000 8000
Savings Certificates - 4000 6000 8500

Using decision tree approach determine the expected return for each alternative. Which
investment proposal would you recommend ?

Problem – 15.

A company is currently working with a process which after paying for materials, labour
etc., brings a profit of Rs.10 crores. The following alternatives are made available to the
company.

(i) The company can conduct research (R1) which is expected to cost Rs.10 crores
having 90% chances of success. If it proves a success, the company gets a gross
income of Rs.25 crores.
(ii) The company can conduct research (R2) which is expected to cost Rs.5 crores
having a probability of 60% success. If successful, the gross income will be Rs.25
crores.
(iii) The company can pay Rs.6 crores as royalty of a new process which will bring a
gross income of Rs.20 crores.
(iv) The company can continue the current process.

Because of limited resources, it is assumed that only one of the two types of research
can be carried cut at a time.

Draw a decision tree and evaluate the optimum decision.

Prepared by – Vinayanand Rele


Page 263 of 380 24/11/2008
Project Management

Problem – 16.

An agricultural company wants to decide which commodity it should stock to get


maximum profit. It was supplied with the following information. The respective
probabilities of monsoon will be excess, normal and deficient are being 0.40, 0.30 and
0.30. The estimated profit or loss of three commodities in respect of these different
kinds of monsoon are :

Monsoon
Excess ( Rs. ) Normal ( Rs. ) Deficient ( Rs. )
Profit Per Ton
Rice + 10,000 - 4,000 +15,000
Wheat + 4,000 - 3,000 + 8,000
Rice + 4,000 + 1,000 + 1,000

Problem – 17.

“New – India Telecom” company has invented a new device which can be used for
internet telephoning. The following options are available :

(i) Manufacture the device.


(ii) Sell the rights to other company.
(iii) Be paid on royalty from other company.

The probabilities associated with the level of sales in the market are 0.15 for 'High sales ;
0.25 for `Medium Sales' and 0.6 for 'Low Sales'. The profit (in lakhs of Rs.) which can be
expected in each case is given in the following table. Draw the associated decision
tree and specify course of action. (Profit in laksh of Rs.)

Market Condition
Action
High Sales Medium Sales Low Sales
Manufacture 85 25 - 20
Sell the rights 20 20 - 20
Get royalty 40 20 -10

Prepared by – Vinayanand Rele


Page 264 of 380 24/11/2008
Project Management

Problem – 18.

A manufacturer of ultimate coffee products has come to realize that its top brand coffee
powder sale has started falling down. The board meets to discuss the alternative courses
of action drafted out by the research cell of the company. They recommended :-

Course (I) to step up the promotional efforts incurring an additional cost of Rs.3.5
lakhs.

Course (ii) to modify the container slightly and introduce it as new ultimate coffee.
Expenses for this change and promotion would be Rs.5 Lakhs.

Course (III) to maintain statusquo.

The estimated revenue in each of these courses of action is as follows :

Revenue (Rs.'000) 700 600 500 400 300 200


Course (I)
Probability: 0.15 0.25 0.25 0.20 0.10 0.05

Revenue( Rs.'000) 900 800 700 600 500 400


Course (II)
Probability: 0.05 0.15 0.30 0.20 0.15 0.15

Revenue( Rs.'000) 400 300 200 100


Course (III)
Probability: 0.25 0.30 0.25 0.20

Draw a decision tree to decide optimum course of action.

Prepared by – Vinayanand Rele


Page 265 of 380 24/11/2008
Project Management

Problem – 19.

A manufacturer of a popular brand of refrigerator intends to market its new fuel' economy
model. It has 3 options namely

(i) to go ahead and launch


(ii) to run a test market
(iii) to abandon the model.

If the product is launched the demand may be poor, good or excellent. Market research
conducted by a consulting firm indicates the probabilities of poor, good and excellent
demand as 20%, 40%, 40% respectively.

If a test market is used at a cost of Rs .2 Lakhs, it will give the indication of market being
either favourable or unfavourable, there being 50 : 50 chance for the same.

If the market response is favourable, the probabilities of poor, good and excellent
market are 10%, 20% and 70 % respectively and if the response is unfavourable and
the product is launched the corresponding probabilities are 80%, 10%, 10%. The pay–
offs are Rs.4,00,000, Rs.8,00,000 and Rs.14,00,000.

Draw a decision tree and select an optimum strategy.

Prepared by – Vinayanand Rele


Page 266 of 380 24/11/2008
Project Management

Problem – 20.

Doily Toys Private Limited is considering the addition of a new toy to its existing product
line. Three alternatives are available to the company.

(i) Work overtime to meet the demand of the new toy. Overtime expenses are
estimated at Rs.20,000 per month.
(ii) Install a new equipment for which fixed expenses per month are expected at
Rs.80,000.
(iii) Lease (rent) a machine at the rate of Rs.35,000 per month.

The expected demand for the toy are as given below :

10,000 pieces with a probability of 0.5


20,000 pieces with a probability of 0.3
50,000 pieces with a probability of 0.2

Monthly contribution from the sales of different units under different alternatives are
calculated as under :

Demand (Monthly Contribution) (in Rs.)


( in pieces)
10,000 20,000 50,000
Alternatives
Overtime working 60,000 1,20,000 3,00,000
New equipment 80,000 1,60,000 4,00,000
Leasing 70,000 1,40,000 3,50,000

Draw the Decision Tree and recommend the optimum course of action to the company.

Prepared by – Vinayanand Rele


Page 267 of 380 24/11/2008
Project Management

10th April, 2008.

Lecture – XIII.

CAPITAL BUDGETING

Introduction

Capital budgeting is a process of planning capital expenditure which is to be made to


maximize the long – term profitability of the organization. The term capital budgeting
refers to planning for capital assets. The capital budgeting decision means a decision as
to whether or not money should be invested in long term projects such as installing a
machinery or creating additional capacities to manufacture a part which is at present
purchased from outside.

Investment Appraisal Techniques

The techniques available for appraisal of investment proposals are classified as follows :

Traditional Techniques

(a) Payback period method


(b) Accounting rate of return method

Discounted Cash flow Techniques (DCF Techniques)

i) Net Present Value method


ii) Internal Rate of Return method
iii) Profitability Index Method

Prepared by – Vinayanand Rele


Page 268 of 380 24/11/2008
Project Management

Payback Period Method

The payback period is usually expressed in years, which it takes the cash inflows from a
capital investment project to equal the cash outflows. The method recognizes the
recovery of original capital invested in a project. At payback period the cash inflows from
a project will be equal to the project's cash outflows. This method specifies the recovery
time, by accumulation of the cash inflows (inclusive of depreciation) year by year until
the cash inflows equal to the amount of the original investment. When deciding between
two or more competing projects the usual decision is to accept the one which has the
shortest payback. In simple terms it can be defined as the number of years required to
recover the cost of the investment.

Merits

• It is simple to apply and easy to understand.


• This method is most suitable when the future is very uncertain. Shorter the
payback period, the less risky is the project. Therefore, it can be considered as
an indicator of risk.
• This method gives an indication to the prospective investors specifying when
their funds are likely to be repaid.
• It does riot involve assumptions about future interest rates.

Demerits

• It does not indicate whether an investment should be accepted or rejected,


unless the payback period is compared with an arbitrary managerial target.
• The method ignores cash generation beyond the payback period and this can be
seen more a measure of liquidity than of profitability.
• It fails to take into account the timing of returns and the cost of capital. It fails to
consider the whole life time of a project. It is based on a negative approach and
gives reduced importance to the going concern concept and stresses on the
return of capital invested rather than on the profits occurring from the venture.
• The traditional payback approach does not consider the salvage value of an
investment. It fails to determine the payback period required in order to recover
the initial outlay if things go wrong.
• This method makes no attempt to measure a percentage return on the capital
invested and is often used in conjunction with other methods.
• The projects with long payback periods are characteristically those involved in
long term planning and which determine an enterprise's future. However, they
may not yield their highest returns for a number of years and the result is that the
payback method is biased against the very investments that are most important
to long term.

Prepared by – Vinayanand Rele


Page 269 of 380 24/11/2008
Project Management

Examples :

1. When the Cash inflows are UNIFORM every year.

Here the initial cost of investment is divided by the constant annual cash inflow as
defined above to get the payback period.

For example, an investment of Rs.40,000 in a machine is expected to produce a cash


inflow of Rs.8,000 per annum then

40,000
Payback period = ---------------- = 5 years
8,000

2. When the projected cash inflows are NOT EQUAL every year.

In such a situation payback period is calculated by a process of cumulating cash inflows


till they equate the original investment outlay.

e.g. Suppose initial cost is Rs.50 000/-

Annual Inflows ( Rs ) Rs.


Year – I 10,000
Year – II 15,000
Year – III 20,000
Year – IV 25,000

Year Inflows ( Rs ) Cumulative Inflows Rs.


1 10,000 10,000
2 15,000 25,000
3 20,000 45,000
4 25,000 70,000

The initial cost of Rs.50,000 will be recovered between years 3 and 4. Therefore,
payback period will be 3 years plus a fraction of the 4th year. By the 3rd year, Rs.45,000
is recovered. The remaining Rs.5,000 would be recovered in the 4th year whose annual
inflow in Rs.25,000.

Therefore the fraction of the 4th Year needed to reach the cost would be :

 5,000  1
  =
 25,000  5

Prepared by – Vinayanand Rele


Page 270 of 380 24/11/2008
Project Management

1
∴ Payback Period = 3 -------- Years
5

An alternative way of expressing the payback period is the payback period Reciprocal
which is expressed as :

1
----------------------- x 100
Payback period

Higher the reciprocal more profitable will be the project.

3. Comparison between two projects.

Project X ( 1,00,000 ) Project Y ( 1,00,000 )


Initial
Cumulative Cumulative
Investment Cash Inflows Cash Inflows
Inflows Inflows
Year – I 20,000 20,000 25,000 25,000
Year – II 20,000 40,000 25,000 50,000
Year – III 30,000 70,000 50,000 1.00,000
Year – IV 30,000 1,00,000 20,000 1.20,000
Year – V 50,000 1,50,000 10,000 1,30,000

Analysis – In this example, Project Y would be selected as its payback period of 3


years is shorter than the 4 years payback period of Project X.

Prepared by – Vinayanand Rele


Page 271 of 380 24/11/2008
Project Management

Accounting Rate of Return Method

The accounting rate of return is also known as 'Return On Investment' or 'return on


capital employed method' It employs the normal accounting technique to measure the
increase in profit expected to result from an investment by expressing the net
accounting profit arising from the investment as a percentage of the capital investment.
In this method, most often the following formula is applied to arrive at the accounting
rate of return.

Average Annual Profit After Tax


Accounting Rate of Return = ------------------------------------------ X 100
Average Investment

Initial Investment + Salvage Value


Average Investment = ----------------------------------------------
2

Sometimes, initial investment is used in place of average investment. Of the various


accounting rates of return on different alternative proposals, the one having highest rate
of return is taken to be the best investment proposal. For example, in three alternative
proposals A, B and C with expected accounting rates of return of 10%, 20% and 18%
respectively, projects will be selected in order of B, C ad A. if he prevailing rates of
interest is taken to be 15% p.a. then only proposals B and C will qualify for
consideration and in that order.

Merits

• It is easy to calculate because it makes use of readily available accounting


information.
• It is not concerned with cash flows but rather based upon profits which are
reported in annual accounts and sent to shareholders.
• Unlike payback period method, this method does take into consideration all the
years involved in the life of a project.
• Where a number of capital investment proposals are being considered, a quick
decision can be taken by use of ranking the investment proposals.
• If high profits are required, this is certainly a way of achieving them.

Demerits

• It does not take into accounting time value of money.


• It fails to measure properly the rates of return on a project even if the cashflows
are even over the project life.
• It uses the straight line method of depreciation. Once a change in method of
depreciation takes place, the method will not be easy to use and will not work
practically.

Prepared by – Vinayanand Rele


Page 272 of 380 24/11/2008
Project Management

• This method fails to distinguish the size of investment required for individual
projects. Competing investment proposals with the same accounting rate of
return may require different amounts of investment.
• It is biased against short term projects in the same way that payback is biased
against long term ones.
• Several concepts of investment are used for working out accounting rates of
return. Thus there is no full agreement on the proper measure of the term
investment. Thus different managers have different meanings when they refer to
accounting rate of return.
• The accounting rates of return does not indicate whether an investment should
be accepted or rejected, unless the rates of return is compared with the arbitrary
management target. It measures the return in relation to the outlay and does not
evaluate the absolute worth of the returns. Problems can arise in defining yearly
profits, which will depend. to a certain extent , on the accounting policies adopted
by the term which respect to such items as stock valuation, treatment of
depreciation, research and development etc.

Example

The cost of the machine is Rs.80,000/-. It is expected to have a scrap value of


Rs.10,000/- at the end of the Five year period. It is estimated to generate a profit over its
life as follows :

Year Net Profit ( Rs. )


1 6,000
2 26,000
3 16,000
4 1,000
5 11,000
Total 60,000

Calculate the Accounting Rate of Return (ARR)

Average Annual Profit


ARR = ------------------------------- x 100
Average Investment

60,000
Average Annual Profit = ------------- = 12,000
5

Prepared by – Vinayanand Rele


Page 273 of 380 24/11/2008
Project Management

( Original Investment + Salvage Value )


Average Investment = ----------------------------------------------------------
2

( 80,000 + 10,000 ) 90,000


= -------------------------- = ---------- = 45,000
2 2

12,000
∴ ARR = ----------- x 100 = 26.76 %
45,000

Prepared by – Vinayanand Rele


Page 274 of 380 24/11/2008
Project Management

Net Present Value Method

The objective of the firm is to create wealth by using existing and future resources to
produce goods and services. To create wealth, inflows must exceed the present value
of all anticipated cash outflows. Net present value is obtained by discounting all cash
outflows and inflows attributable to a capital investment project by a chosen percentage.
The method discounts the net cash flows from the investment by the minimum required
rate of return, and deducts the initial investment to give the yield from the funds
invested. If yield is positive the project is acceptable. If it is negative the project in
unable to pay for itself and is thus unacceptable. The exercise involved in calculating
the present value is known as 'Discounting' and the factors by which we have multiplied
the cash flows are known as the 'Discount Factors'. The discount factor is given by the
following expression:

1
(1 + r) n
Where

r = Rate of interest per annum.


n = number of years over which we are discounting.

Merits

• It is based on the assumption that cash flows, and hence dividends, determine
share holders wealth.
• Cash flows are subjective than profits.
• It considers the time – value of money.
• It considers the total benefits arising out of proposals over its life-time.
• The future discount rate normally varies due to longer time span. This rate can be
applied in calculating the NPV by altering the denominator.
• This method is particularly useful for the selection of mutually exclusive projects.
( In mutually exclusive projects acceptance of one project tantamount to rejection
of the other project. )
• This method of project selection is instrumental in achieving the financial
objective. i.e., the maximization of the shareholders wealth.

Demerits

• It is difficult to calculate as well as understand as compared to accounting rate of


return method or payback period method.
• Calculation of the desired rates of return presents serious problems. Generally
cost of capital is the basis of determining the desired rate. The calculation of cost
of capital is itself complicated. Moreover, desired rates of return will vary from
year to year.

Prepared by – Vinayanand Rele


Page 275 of 380 24/11/2008
Project Management

• This method is an absolute measure. When two projects are being considered,
this method will favour the project which has higher NPV.
• This method may not give satisfactory results when two projects having different
effective lives are being compared. Normally, the project with shorter economic
life is preferred, if other things are equal.
• This method emphasizes the comparison of net present value and disregards the
initial investment involved. Thus, this method may not give dependable results.

Example - 1 :

A firm can invest Rs.10,000/- in a project with a life of Three years. The projected cash
inflow are : Year-1 Rs. 4,000/-, Year-2 Rs.5,000/- and Year-3 Rs. 4,000/-.

The cost of capital is 10 % p.a. Should the investment be made ?

Firstly the discount factors can be calculated based on Re.1 received in with `r' rate of
interest in 3 years.

1
(1 + r) n

1 1
Year – 1 = --------------------- = ---------- = 0.909
( 1 + 10 / 100 ) ( 1.10 )

1 1
Year – 2 = --------------------- = ---------- = 0.826
( 1 + 10 / 100 )2 ( 1.10 )2

1 1
Year – 3 = --------------------- = ---------- = 0.751
( 1 + 10 / 100 )3 ( 1.10 )3

Year Cash Flow ( Rs ) Discount Factor Present Value ( Rs )


0 (10,000) 1.000 (10,000)
1 4,000 0.909 3,636
2 5,000 0.826 4.130
3 4,000 0.751 3,004
NPV = 770

Analysis : Since the net present value is positive, investment in the project can be
made.

Prepared by – Vinayanand Rele


Page 276 of 380 24/11/2008
Project Management

Example - 2 :

National Electronics Ltd., an electronic goods manufacturing company manufactures


large range of electronic goods. It has under consideration two projects X and Y, each
costing Rs.120 Lakhs.

The projects are mutually exclusive and the company is considering the question of
selecting one of the two projects. Cash flows have been worked out for both the projects
and the details are given below.

Project X has a life of 8 years and Project Y has a life of 6 years. Both will have zero
salvage value at the end of their operational lives. The company is already making
profits and its tax rate is 50%. The cost of Capital of the Company is 15%.

Net Cash Inflow Present Value of


At the end of Year
Project X Project Y Rupee at 15 %
1 25 40 0.870
2 35 60 0.765
3 45 80 0.685
4 65 50 0.572
5 65 30 0.497
6 55 20 0.432
7 35 - 0.376
8 15 - 0.327

The company follows straight line method of depreciating assets. Advise the company
regarding the selection of the project.

Computation of Net Present Value of the Project X and Project Y.

Prepared by – Vinayanand Rele


Page 277 of 380 24/11/2008
Project Management

Project – X

Net C. F. =
End of Cash Depreciation PBT Tax PAT PAT + Discount P. V.
year flow Depreciation Factor
1 25 15 10 5 5 20 0.870 17.40
2 35 15 20 10 10 25 0.756 18.90
3 45 15 30 15 15 30 0.658 19.74
4 65 15 50 25 25 40 0.572 22.88
5 65 15 50 25 25 40 0.497 19.88
6 55 15 40 20 20 35 0.432 15.12
7 35 15 20 10 10 25 0.375 9.40
8 15 15 - - - 15 0.327 4.91
P V of cash inflows 128.23
Less: Initial Investment 120.00
Net Present Value 8.23

Project – Y

Net C. F. =
End of Cash Depreciation PBT Tax PAT PAT + Discount P. V.
year flow Depreciation Factor
1 40 20 20 10 10 30 0.870 26.10
2 60 20 40 20 20 40 0.756 30.24
3 80 20 60 30 30 50 0.658 32.90
4 50 20 30 15 15 35 0.572 20.02
5 30 20 10 5 5 25 0.497 12.43
6 20 20 - - - 20 0.432 8.64
P V of cash inflows 130.33
Less: Initial Investment 120.00
Net Present Value 10.33

Analysis: As Project Y has a higher net present value, it is advisable to take


up Project Y .

Prepared by – Vinayanand Rele


Page 278 of 380 24/11/2008
Project Management

Internal Rate of Return Method

Internal rate of return (IRR) is a percentage discount rate used in capital investment
appraisals which brings the cost of a project and its future cash inflows into equality. It is
the rate of return which equates the present value of anticipated net cash flows with the
initial outlay. The IRR is also defined as the rate at which the net present value is zero.
The rate for computing IRR depends as bank lending rate or opportunity cost of funds to
invest which is often called as personal discounting rate or accounting rate. The test of
profitability of a project is the relationship between the IRR (%) of the project and the
minimum acceptable rate of return (%). The IRR can be stated in form of a ratio as
shown below :

Cash Inflows
-------------------- = 1
Cash Outflows

Or P. V. of Cash inflows – P.V. of Cash Outflows = 0

The IRR is to be obtained by trial and error method to ascertain the discount rate at
which the present values of total cash inflows will be equal to the present values of total
cash out flows. If the cash inflow is not uniform, then IRR will have to be calculated by
trial and error method. In order to have an approximate idea about such discounting
rate, it will be better to find out the 'factor'. The factor reflects the same relationship of
investment and cash inflows as in case of payback calculations.

F = I/C
F = Factor to be located.
Where, I = Original Investment
C = Average Cash Inflow per year.

In appraising the investment proposals, IRR is compared with the desired rate of return
or weighted average cost of capital, to ascertain whether the project can be accepted or
not. IRR is also called as 'cut off rate' for accepting the investment proposals.

The trial and error method for computing IRR when cash inflows are not even is
summarized, step by step, as follows:

1. Compute NPV at the cost of capital, denoted here as r1-


2. See if NPV is positive or negative.
3. If NPV is positive, then pick another rate (r2) much higher than r1.
4. Compute NPV using r2. If NPV is positive then choose another value of r2 which
is higher than previous r2. If NPV is negative at new r2 then, the true IRR at
which NPV = 0 must be somewhere between these two rates r1 and r2
(new).
5. Use interpolation for the exact rate.
Prepared by – Vinayanand Rele
Page 279 of 380 24/11/2008
Project Management

Interest Rate NPV


( X1 ) r 1 NPV1 > 0 ( Y1 )
( X0 ) IRR NPV = 0 ( Y0 )
( X2 ) r 2 NPV2 < 0 ( Y2 )

Then,
( X2 – X1 ) ( Y1 – Y0 )
X0 = X1 + ---------------------------
( Y1 – Y2 )

Merits :

• It Considers the time value of Money


• It takes into account the total cash inflows and cash outflows.
• It is easy to understand for example if told that IRR of an investment is 20%
against the desired rate of an investment is Rs.15,396/-.

Demerits

• It does not use the concept of desired rate of return whereas it provides the
rate of return which is indicative of the profitability of investment proposal.
• It involves tedious calculations, based on trial and error method.
• It produces multiple rates which can be confusing.
• Projects selected based on higher IRR may not be profitable.
• Unless the life of the project can be accurately estimated, assessment of
cash flows cannot be correctly made.
• Single discount rate ignores the varying future interest rates.

Prepared by – Vinayanand Rele


Page 280 of 380 24/11/2008
Project Management

Example:

A company has to select one of the following two projects :

Particular Project A Project B


Cost 11,000 10,000
Cash In Flows :
Year – 1 6,000 1,000
Year – 2 2,000 1,000
Year – 3 1,000 2,000
Year – 4 5,000 10,000

Using the Internal rate of return method suggest which project is preferable.

Factor in case of Project A = 11,000 / 3,500 = 3.14


Factor in case of Project B = 10,000 / 3,500 = 2.86

The factor thus calculated will be located in table given at the end of the handout on the
line representing number of years corresponding to estimated useful life of the asset.
This would give the expected rate of return to be applied for discounting the cash
inflows the internal rate of return.

In case of Project A, the rate comes to 10% while in case of Project B it comes to 15%.

Project – A

Cash Inflows Discounting Present


Year
( Rs. ) Factor at 10 % Value ( Rs. )
1 6,000 0.909 5,454
2 2,000 0.826 1,652
3 1,000 0.751 751
4 5,000 0.683 3,415
Total Present Value 11,272

The present value at 10% comes to Rs.11,272. The initial investment is Rs.11,000.
Internal rate of return may be taken approximately at 10%.

Prepared by – Vinayanand Rele


Page 281 of 380 24/11/2008
Project Management

In case more exactness is required another trial rate which is slightly higher than 10%
(since at this rate the present value is more than initial investment ) may be taken.
Taking a rate of 12%, the following results would emerge:

Cash Inflows Discounting Present


Year
( Rs. ) Factor at 12 % Value ( Rs. )
1 6,000 0.893 5,358
2 2,000 0.797 1,594
3 1,000 0.712 712
4 5,000 0.636 3,180
Total Present Value 10,844

The internal rate of return is thus more than 10% but less than 12%. The exact rate
may be calculated as follows :

P. V. Required 11,000
P. V. at 10 % 11,272 (+) 272
P. V. at 12 % 10,844 (-) 156

272
Actual IRR = 10 + ---------------------- x 2 = 11.27%
272 – (-156)

Project – B

Cash Inflows Discounting Present


Year
( Rs. ) Factor at 15 % Value ( Rs. )
1 1,000 0.870 870
2 1,000 0.756 756
3 2,000 0.658 1,316
4 10,000 0.572 5,720
Total Present Value 8,662

Since present value at 15% comes only to Rs.8,662, a lower rate of discount should
be taken. Taking a rate of 10% the following will be the result.

Cash Inflows Discounting Present


Year
( Rs. ) Factor at 10 % Value ( Rs. )
1 1,000 0.909 909
2 1,000 0.826 826
3 2,000 0.751 1,502
4 15,000 0.683 6,830
Total Present Value 10,067

Prepared by – Vinayanand Rele


Page 282 of 380 24/11/2008
Project Management

The present value at 10% comes to Rs.10,067 which is more or less equal to the
initial investment Hence the internal rate of return may be taken as 10%.

In order to have more exactness to Internal rate of return can be interpolated as


done in case of Project 'A'.

P. V. Required 10,000
P. V. at 10% 10,067 (+) 67
P. V. at 15% 8,662 (-) 1,338

67
Actual IRR = 10 + ---------------------- x 5 = 10.24%
67 – (-1,338)

Analysis : Thus, internal rate of return in case of Project A is higher as compared to


Project B. Hence, Project A is preferable.

Prepared by – Vinayanand Rele


Page 283 of 380 24/11/2008
Project Management

Relative Ranking of Projects : IRR vs. NPV

The relative ranking of projects, using the different DCF methods will be considered
initially in simple accept / reject situations. This will be extended later to a detailed
assessment of situations where a choice has to be made between two or more
alternatives. In simple accept / reject situations a firm is able to implement all projects
showing a return at or above the firms cost of capital. Both NPV and IRR would appear
to be equally valid in the sense that they will both lead to accept or reject the same
projects. Using NPV, all projects with a positive net present value, when discounted at
the firm's cost of capital, will be accepted. Using IRR all projects which yield an internal
rate of return in excess of the firms cost of capital will be chosen. Although IRR and
NPV lead to the same conclusion regarding project acceptability, the ranking of a set of
projects, obtained from IRR does not necessarily agree with that produced using NPV.
Since, in the latter case, the ranking may vary according to particular discount rate
used. The IRR measures only the quality of the investment while NPV takes into
account both the quality and the scale. This is because the IRR provides a relative
measure of value (% IRR) while the NPV provides an absolute measure (Rs. surplus).
The IRR would rank, for example, a 100% return on an investment of Re.l.considerably
higher than a 20% return on an investment of Rs.10 Lakhs, whereas the reverse would
be true using NPV (as long as the cost of capital is below 20%).

While one project may have a higher rate of profit per unit of capital invested than
another, if it has fewer units of capital invested in it, it may make a smaller contribution
to the wealth of the firm. Thus, if the objective is to maximize the firms wealth, then the
ranking of project NPVs provides the correct measure. If the objective is to maximize,
the rate of profitability per unit of capital invested, then RR would provide the correct
ranking of projects, but this objective could be achieved by rejecting all but the most
highly profitable projects. This is clearly unrealistic and therefore, one would conclude
that NPV ranking is correct and !RR unsatisfactory as a measure of relative project
value. When two investment proposals are mutually exclusive, both methods will give
contradictory results. When two mutually exclusive projects are not expected to have
the same life, NPV and IRR methods will give conflicting ranking.

Prepared by – Vinayanand Rele


Page 284 of 380 24/11/2008
Project Management

Example

A company is considering which of the two mutually exclusive projects it should


undertake. The Finance Director thinks that the project with the higher NPV should be
chosen whereas the Managing Director thinks that the one with the higher iRR should
be undertaken especially as both projects have the same initial outlay and length of fife.
The company anticipates a cost of capital of 10% and the net after – tax cash flows of
the projects are as follows :

Year 0 1 2 3 4 5
Cash Flows
Project X ( 200 ) 35 80 90 75 20
Project Y ( 200 ) 218 10 10 4 3

Required :

(a) Calculate the NPV and IRR of each project.


(b) State, with reasons, which project you would recommend.
(c) Explain the inconsistency in the ranking of the two projects.

The discount factors are as follows :

Year 0 1 2 3 4 5
( 10 % ) 1 0.91 0.83 0.75 0.68 0.62
Discount Factors
( 20 % ) 1 0.83 0.69 0.58 0.48 0.41

(a) Calculation of the NPV and !RR of each Project.

NPV of Project X

Discount Discount
Discounted Discounted
Year Cash Flow Factors Factors @
Values Values
@ 10 % 20 %
0 (200) 1.00 (200) 1.00 (200)
1 35 0.91 31.85 0.83 29.05
2 80 0.83 66.40 0.69 55.20
3 90 0.75 67.50 0.58 52.20
4 75 0.68 51.00 0.48 36.00
5 20 0.62 12.40 0.41 8.20
NPV +29.15 -19.35

Prepared by – Vinayanand Rele


Page 285 of 380 24/11/2008
Project Management

IRR of Project X

At 20% NPV is - 19.35

At 10% NPV is + 29.15

29.15
IRR = 10 + -------------------- x 10 = 16.01 %
29.15 + 19.35

NPV of Project Y

Discount Discount
Discounted Discounted
Year Cash Flow Factors Factors @
Values Values
@ 10 % 20 %
0 (200) 1.00 (200) 1.00 (200)
1 218 0.91 198.38 0.83 180.94
2 10 0.83 8.30 0.69 6.90
3 10 0.75 7.50 0.58 5.80
4 4 0.68 2.72 0.48 1.92
5 3 0.62 1.86 0.41 1.23
NPV +18.76 -3.21

IRR of Project Y

At 20% NPV is - 3.21

At 10% NPV is + 18.76

18.76
IRR = 10 +
-------------------- x 10 = 18.54 %
18.76 + 3.21
(b) Both the projects are acceptable because they generate the positive NPV at
the company's cost of capital at 10%. However , the company will have to
select Project X because it has a higher NPV. If the company follows IRR
method, then Project Y should be selected because of higher internal rate of
return (IRR). But when NPV and IRR give contradictory results , a project with
higher NPV is generally preferred because of higher return in absolute terms.
Hence, Project X should be selected.

(c) The inconsistency in the ranking of the projects arises because of the
difference in the pattern of cash flows. Project X's major cash flows occur
mainly in the middle three years, whereas Y generates the major cash flows
in the first year itself.

Prepared by – Vinayanand Rele


Page 286 of 380 24/11/2008
Project Management

Profitability Index Method

The profitability index (PI) is the present value of an anticipated future cash inflows
divided by the initial outlay. The only difference between the net present value method
and profitability index method is that when using the NPV technique the initial outlay is
deducted from the present value of anticipated cash inflows , whereas with the
profitability index approach the initial outlay is used as a divisor. in general terms, a
project is acceptable if its profitability index value is greater than 1. Clearly, a project
offering a profitability index greater than 1 must also offer a net present value which is
positive. When more than one project proposals are evaluated, for selection of one
among them, the project with higher profitability index will be selected. Mathematically.
PI (profitability index) can be expressed as follows : -

Present Value of Cash Inflows

Profitability Index (PI) = ----------------------------------------

Present Value of Cash Outflow

This method is also called 'cost – benefit ratio' or 'desirability ratio' method.

Example

The following mutually exclusively projects can be considered :

Particulars Project A Project B


P V of Cash Inflows (i) 20,000 8,000
Initial Cash Outlay (ii) 15,000 5,000
Net Present Value 5,000 3,000
Profitability Index (i)/(ii) 33 1.60

Analysis : According to the NPV method, Project A would be preferred, whereas


according to Profitability Index, Project B would be preferred. Although P1 method is
based on NPV, it is a better evaluation technique than NPV in a situation of capital
rationing. For example two projects may have the same NPV of Rs.10,000 but Project A
requires initial outlay of Rs.1.00,000 whereas B only Rs.50,000. Then Project B would
be preferred as per the yard stick of PI method.

Limitations

• Profitability Index can not be used in capital rationing problems where projects
are indivisible. Once a single large project with high NPV is selected, the
possibility of accepting several small projects which together may have higher
NPV than the single project , is excluded.
• Some times the project with lower profitability index may have to be selected if it
generates cashflows in the earlier years, which can be used for setting up of
another project to increase the overall NPV.

Prepared by – Vinayanand Rele


Page 287 of 380 24/11/2008
Project Management

Assumptions in Use of DCF Techniques

In use of discounted cash flow techniques the following assumptions should be


given consideration:

• The discount rate is constant over the life of the investment.

• All cash flows can be predicted with certainty so that a risk premium need not
be added to the discount rate in order to compensate for risk.

• In project appraisal, managers work with uncertain future events and


estimated cash flows expected to occur in future years. This involves a
substantial amount of estimation which in practical terms, means that
spurious accuracy is something which needs to be avoided

• The discount figures used can be calculated with great accuracy but when
they are applied to these future estimated cash flows, the resultant
calculation is only as accurate as the cash flows estimates.

• In many companies there is a tendency to produce discounted cash flow


computation with several decimal places on each of the present values. This
creates a totally fallacious appearance of accuracy in the evaluation process.

• To enable convenient calculation s to be performed , it is normal practice in


capital project evaluations to assume that all cash flows take place at the end
of the year. The initial cash outflows or investment in a project is assumed to
take place now. The cash flows which go out now are taken to be at Year 0.
The concept of Year C does not mean a year in general terms, but a point in
time, i.e. today. Year 1 cash flows are assumed to take place at the end of
the first year. The second year cash flows occurring at the end of the Year 2
and similarly for subsequent years.

• In appraising long projects. it is normal to use an arbitrary horizon period f 10


to 15 years. Firms do not consider cash flows beyond the horizon even if they
expect the project to last longer.

Prepared by – Vinayanand Rele


Page 288 of 380 24/11/2008
Project Management

Capital Rationing

Capital rationing is a situation where a constraint of budget ceiling is placed on the


total size of capital expenditures during a particular period. Often firms draw up their
capital budget under the assumption that the availability of financial resources is
limited. Capital rationing refers to the selection of the investment proposals in a
situation of constraint on availability of capital funds, to maximize the wealth of the
company by selecting those projects which will maximize overall NPV of the
concern. In capital rationing situation a company may have to forego some of the
projects whose IRR is above the overall cost of the firm due to ceiling on budget
allocation for the projects which are eligible for capital investment. Capital rationing
refers to a situation where a company cannot undertake all positive NPV projects it
has identified because of shortage of capital. Under this situation a decision maker
is compelled to reject some of the viable projects having positive net present value
because of shortage of funds. It is known as a situation involving capital rationing. In
terms of financing investment projects, the following important questions are to be
answered.

• What would be the requirement of funds for capital investment decisions in


the forthcoming planning period?

• How much quantum of funds available for capital investment?

• How to assign the available funds to the acceptable proposals which require
more funds than are available?

The answer to the first and second questions are given with reference to the capital
investment appraisal decisions made by the top management. The third question is
answered with specific reference to the appraisal of investment decisions from the
angle of capital rationing.

Situations of Capital Rationing

Capital rationing decisions can be studied under the following situations :

Situation I – Projects are Divisible and Constraint is a Single Period One

The following are the steps to be adopted for solving the problem under this
situation:

(a) Calculate the profitability index of each project.

(b) Rank the projects on the basis of the profitability index calculated in (a)
above.

(c) Choose the optimal combination of the projects.

Prepared by – Vinayanand Rele


Page 289 of 380 24/11/2008
Project Management

Example

NPV
Required Initial
Project The appropriate
Capital
Cost of Capital
A 1,00,000 20,000
B 3,00,000 35,000
C 50,000 16,000
D 2,00,000 25,000
E 1,00,000 30,000

Total fund available is Rs.3,00,000. Determine the optimal combination of projects


assuming that the projects are divisible

Required initial Profitability


NPV at the appropriate
Project outlay index Rank
cost of capital (Rs.)
(Rs.) [ (3) / (2) ]
(1) (2) (3) (4) (5)
A 1,00.000 20,000 0.2 3
B 3,00,000 35,000 0.117 5
C 50.000 16,000 0.32 1
D 2,00,000 25,000 0.125 4
E 1,00,000 30,000 0.3 2

Rank of Investment Project Required Initial (Rs.)


1 C 50,000
2 E 1,00,000
3 A 1,00,000
4 1 / 4th of D 50,000 *
Total 3,00,000

* (Rs.2,00,000 x 1 / 4)

Therefore, the optimal combination of projects is C, E, A and 114t11 portion of D.

Prepared by – Vinayanand Rele


Page 290 of 380 24/11/2008
Project Management

Situation II — Projects are Indivisible and Constraint is a Single Period one

The following steps to be followed for solving the problem under this situation.

(a) Construct a table showing the feasible combinations of the project (whose
aggregate of initial outlay does not exceed the fund available for investment).

(b) Choose the combination whose aggregate NPV is maximum and consider it
as the optimal project mix.

Example

Using the same data as used in the previous illustration, determine the optimal
project mix on the basis of the assumption that the projects are indivisible.

Feasible Combinations Aggregate of NPVs


A, C 36,000
A, D 45,000
A, E 50,000
C, D 41,000
C, E 46,000
D, E 55,000
A, C, E 66,000

By a careful inspection of the feasible combinations constructed in the above table,


we can conclude that the optimal project mix is A, C and E because the aggregate
of their NPVs is maximum.

Prepared by – Vinayanand Rele


Page 291 of 380 24/11/2008
Project Management

Problem – 1.

The initial investment for a project is Rs.15,000/- The annual cash flow due to the
project are as given below :

Year 1 2 3 4 5 6 7
Cash flow (in Rs.) 4000 2000 4000 3000 2000 1000 2000

If the cost of capital is 10% p.a., what is the net present value of the project ?

Solution :

Cash Flow PV Factor PV of Cash


Year
( Rs ) @ 10 % Flow
0 (15,000) 1.000 (15,000)
1 4,000 0.909 3,636
2 2,000 0.826 1,652
3 4,000 0.751 3,004
4 3,000 0.683 2,049
5 2,000 0.621 1,242
6 1,000 0.564 564
7 2,000 0.513 1,026
NPV = -1,827

Prepared by – Vinayanand Rele


Page 292 of 380 24/11/2008
Project Management

Problem – 2.

The management of the Play Toy Factory, a manufacturer of toys in New Delhi, is
considering the introduction of a new type of a toy-remote control motorbike. In the
past, the management has been quite conservative in making investments in new
product and consider this project quite a risky one. The management feels that the
normally used required rate of return of 10% is not proper in this case and instead,
a return of 16% is expected on this project.

The project, requiring an outlay of Rs.1,50,000 has the following expected returns
over its estimated life of 6 years.

Year 1 2 3 4 5 6
Cash Flow (‘000 Rs.) 30 30 50 60 40 25

Should the project be undertaken ?

Solution :

Cash Flow PV Factor


Year PV of Cash Flow
( Rs ) @ 16 %
0 (1,50,000) 1.000 (1,50,000)
1 30,000 0.862 25,860
2 30,000 0.743 22,290
3 50,000 0.641 32,050
4 60,000 0.552 33,120
5 40,000 0.476 19,040
6 25,000 0.410 10,250
NPV = -7,390

Since NPV is Negative Do Not take this Project.

Prepared by – Vinayanand Rele


Page 293 of 380 24/11/2008
Project Management

Problem – 3.

A management wants to judge whether a project X is worth taking up or not The


data with regarding the project (having life of 8 years' ) is given below :

Net Cash Net Cash


Year Year
Flow Flow
1 6,000 5 9,700
2 8,500 6 7,600
3 10,000 7 5,700
4 11,800 8 4,000

The initial outlay of the project is Rs.45,000/- with a salvage value of Rs.10,000/-. If
the cost of capital is 10%, find the Net Present Value (NPV) of the project and
hence determine whether it is worth taking up the project or not.

Solution :

Salvage value means re-sale value

Now since in the 8th year i.e. last year of the project, there will be sale of capital
asset which will generate Rs. 10,000/- at extra flow of cash.

So net cash flow for 8th year will be 4,000 + 10,000/- = 14,000/-

Cash Flow PV Factor PV of Cash


Year
( Rs ) @ 10 % Flow
0 (45,000) 1.000 (45,000)
1 6,000 0.909 5,454
2 8,500 0.826 7,021
3 10,000 0.751 7,510
4 11,800 0.683 8,059
5 9,700 0.621 6,024
6 7,600 0.564 4,286
7 5,700 0.513 2,924
8 14,000 0.467 6,538
NPV = 2816.60

Prepared by – Vinayanand Rele


Page 294 of 380 24/11/2008
Project Management

Problem – 4.

Consider two projects A and B with the following cash flow streams.

Year 0 1 2 3 4
Project A 1,00,000 28,000 35,000 41,000 45,000
Project B 1,80,000 65,000 65,000 65,000 65,000

Assuming discount rate as 10% per annum, and both projects are equally risky, which
projects would you accept if you have to choose only one project between the two ?
Justify your answer.

Solution :

Project - A Project - B
PV Factor
Year Cash Flow PV of Cash Cash Flow PV of Cash
@ 10 %
( Rs ) Flow ( Rs ) Flow
0 1.000 -100,000 -100,000 -180,000 -180,000
1 0.909 28,000 25,452 65,000 59,085
2 0.826 35,000 28,910 65,000 53,690
3 0.751 41,000 30,791 65,000 48,815
4 0.683 45,000 30,735 65,000 44,395
NPV 15,888 NPV 25,985

Since NPV of Project B is > Project – A, Project B is Better.

Justification
Project A Project B

PV 1,15,888 2,06,050
Investment 1,00,000 1,80,000

PV 1,15,888 2,06,050
Profitability = ---- = ------------ ------------
Index ( PI ) I 1,00,000 1,80,000

PI = 1.16 1.14

Now PI of Project – A is > than Project – B, Hence Project A is Better.

Prepared by – Vinayanand Rele


Page 295 of 380 24/11/2008
Project Management

Problem – 5.

A company is deciding to choose between two mutually exclusive projects A and B.


Project A requires an initial investment of Rs.3,00,000 and is expected to generate cash
flow of Rs.1,50,000 per annum for the 3 years of its life. Project B, on the other hand,
requires Rs.3,40,000, and has a life of 6 years and would generate Rs.1,00,000 every
year. Which proposal should be accepted ? Assume a 10% rate of interest.

Solution :

Project - A Project - B
PV Factor
Year Cash Flow PV of Cash Cash Flow PV of Cash
@ 10 %
( Rs ) Flow ( Rs ) Flow
0 1.000 -300,000 -300,000 -340,000 -340,000
1 0.909 150,000 136,350 100,000 90,900
2 0.826 150,000 123,900 100,000 82,600
3 0.751 150,000 112,650 100,000 75,100
4 0.683 100,000 68,300
5 0.621 100,000 62,100
6 0.564 100,000 56,400
NPV 72,900 NPV 95,400

Since NPV of Project B is > Project – A, Project B is Better.

Prepared by – Vinayanand Rele


Page 296 of 380 24/11/2008
Project Management

Problem – 6.

A company has to decide which of the four projects W, X, Y, Z is a better investment.


The initial investments along with each year's cash flows of these projects are given
below :

Life Initial Investment Annual Cash flow


Project
(in Years) (In Rs.) (in Rs.)
W 8 16,000 4,000
X 3 6,000 3,500
Y 5 12,000 4,000
Z 6 8,000 3,000

Rank these projects on the basis of NPV, if the cost of capital s 15% per annum.

Solution :

PV of
Initial Annual PV Factor

RANK

RANK
Life in Cash NPV = PI =
Projects Investme Cash 15 %
Years Flow ( PV - I ) ( PV / I )
nt ( I ) Flow ( Cumulative )
( PV )
W 8 16,000 4,000 4.487 17,948 1,948 3 1.12 3
X 3 6,000 3,500 2.283 7,991 1,991 2 1.33 2
Y 5 12,000 4,000 3.352 13,408 1,408 4 1.12 4
Z 6 8,000 3,000 3.784 11,352 3,352 1 1.42 1

Prepared by – Vinayanand Rele


Page 297 of 380 24/11/2008
Project Management

Problem – 7.

One of the two machines A and B is to be purchase. From the following information,
find out which of the two will be more profitable ?

Machine A Machine B
( Rs. ) ( Rs. )
Cost of Machine Life Rs. 50,000 Rs. 80,000
Earning before Tax 4 Years 6 Years
1 10,000 8,000
2 15,000 14,000
3 20,000 25,000
4 15,000 30,000
5 - 18,000
6 - 13,000

Answer
ARR
A 1.875 %
B 2.33 % ( Machine B is Profitable )

Payback

A 3 years and 9 months


B 5 years and 2 months ( Machine A is Profitable )

Solution :

Since PV factor is not given take it as 8%.

Project - A Project - B
PV
PV of
Year Factor @ Cash Flow Cash Flow PV of
Cash
8% ( Rs ) ( Rs ) Cash Flow
Flow
0 1.000 -50,000 -50,000 -80,000 -80,000
1 0.926 10,000 9,260 8,000 7,408
2 0.857 15,000 12,855 14,000 11,998
3 0.794 20,000 15,880 25,000 19,850
4 0.735 15,000 11,025 30,000 22,050
5 0.681 18,000 12,258
6 0.630 13,000 8,190
NPV -980 NPV 1,754

Prepared by – Vinayanand Rele


Page 298 of 380 24/11/2008
Project Management

Since NPV of Project – B > NPV of Project – A, ∴ Project – B is profitable.

Project A Project B

PV 49,020 81,754
Investment 50,000 80,000

PV 49,020 81,754
Profitability = ---- = ------------ ------------
Index ( PI ) I 50,000 80,000

PI = 0.98 1.02

By PI index method Project – B is better.

Prepared by – Vinayanand Rele


Page 299 of 380 24/11/2008
Project Management

Problem – 8.

A company whose cost of capital is 12% is considering two projects A and B. The
following data are available.

Project Project
A B
Rs. Rs.
Investments 1,40,000 1,40,000
Cash Flows :
Year 1 20,000 1,00,000
2 40,000 80,000
3 60,000 40,000
4 1,00,000 20,000
5 1,10,000 20,000

Select the most profitable project by using the following methods:

(a) Payback period


(b) NPV
(c) profitability Index

P. V. or Re.1 at 12% are :

Year 1 2 3 4 5
P. V. .9 .8 .7 .6 .55

Answer

a) Payback :

1
A 3 ------ years
5

1
B 1 ------ years
2

Project B is Profitable.

Prepared by – Vinayanand Rele


Page 300 of 380 24/11/2008
Project Management

Solution :

a) By Payback Period Method

Project A ( 1,40,000 ) Project B ( 1,40,000 )


Initial
Cumulative Cumulative
Investment Cash Inflows Cash Inflows
Inflows Inflows
Year – 1 20,000 20,000 1,00,000 1,00,000
Year – 2 40,000 60,000 80,000 1,80,000
Year – 3 60,000 1,20,000 40,000 2.20,000
Year – 4 1,00,000 2,20,000 20,000 2.40,000
Year – 5 1,10,000 3,30,000 20,000 2,60,000

For Project :.
20,000 1 1
A ------------- = ------ that is 3 ------
1,00,000 5 5

40,000 1 1
B ------------- = ------ that is 1 ------
80,000 2 2

Hence by Payback Period Method Project B is Profitable.

b) By NPV Method

Project - A Project - B
PV
PV of
Year Factor @ Cash Flow Cash Flow PV of
Cash
12 % ( Rs ) ( Rs ) Cash Flow
Flow
0 1.000 -140,000 -140,000 -140,000 -140,000
1 0.900 20,000 18,000 100,000 90,000
2 0.800 40,000 32,000 80,000 64,000
3 0.700 60,000 42,000 40,000 28,000
4 0.600 100,000 60,000 20,000 12,000
5 0.550 110,000 60,500 20,000 11,000
NPV 72,500 NPV 65,000

Since NPV of Project – A > NPV of Project – B, ∴ Project – A is profitable.

Prepared by – Vinayanand Rele


Page 301 of 380 24/11/2008
Project Management

c) By PI Method

Project A Project B

PV 2,12,500 2,05,000
Investment 1,40,000 1,40,000

PV 2,12,500 2,05,000
Profitability = ---- = --------------- ---------------
Index ( PI ) I 1,40,000 1,40,000

PI = 1.517 1.464

By PI index method Project – A is better.

Prepared by – Vinayanand Rele


Page 302 of 380 24/11/2008
Project Management

Problem – 9.

A Company has an investment opportunity costing Rs. 40,000 with the following
expected net cash flow after tax but before depreciation.

Year Net Cash Flow


( Rs )
1 7,000
2 7,000
3 7,000
4 7,000
5 7,000
6 8,000
7 10,000
8 15,000
9 10,000
10 4,000

Using 10% as the cost of capital, determine the following :

(a) Payback period


(b) NPV at 10% discount factor
(c) Profitability Index at 10% discount factor
(d) IRR within 10% and 15% discount factor

Answers :

a) 5 years and 7.5 months


b) Rs.8961
c) At 10% = 1.224
At 15% = .9855
d) 14,696%

Prepared by – Vinayanand Rele


Page 303 of 380 24/11/2008
Project Management

Solution :

(a) Payback Method.

Investment ( Rs. 40,000 )


Cash Cumulative
Year Inflows Inflows
1 7,000 7,000
2 7,000 14,000
3 7,000 21,000
4 7,000 28,000
5 7,000 35,000
6 8,000 43,000
7 10,000 53,000
8 15,000 68,000
9 10,000 78,000
10 4,000 82,000

5,000
------------- = 0.625
8,000 So multiply this by 12,

0.625 x 12 = 7.5. So 5 years and 7.5 months.

b) NPV Method.

Cash Flow PV @ 10 % PV @ 15 %
PV Factor of Cash PV Factor of Cash
Year ( Rs ) @ 10 % Flow @ 15 % Flow
0 -40,000 1.000 -40,000 1.000 -40,000
1 7,000 0.909 6,363 0.870 6,090
2 7,000 0.826 5,782 0.756 5,292
3 7,000 0.751 5,257 0.658 4,606
4 7,000 0.683 4,781 0.572 4,004
5 7,000 0.621 4,347 0.497 3,479
6 8,000 0.564 4,512 0.432 3,456
7 10,000 0.513 5,130 0.376 3,760
8 15,000 0.467 7,005 0.324 4,860
9 10,000 0.424 4,240 0.284 2,840
10 4,000 0.386 1,544 0.247 988
NPV 8,961 NPV -625

Prepared by – Vinayanand Rele


Page 304 of 380 24/11/2008
Project Management

c) By PI Method
@ 10 % @ 15 %

PV 48,961 39,375
Investment 40,000 40,000

PV 48,961 39,375
Profitability = ---- = --------------- ---------
Index ( PI ) I 40,000 40,000

PI = 1.224 0.984

d) IRR Method

At 15% NPV is - 625

At 10% NPV is + 8961

8961
IRR = 10 + ------------------ x 5 = 14.67 %
8961 + 625

Prepared by – Vinayanand Rele


Page 305 of 380 24/11/2008
Project Management

Problem – 10.

Consider an investment which has the following cash flows :

Year 0 1 2 3 4 5
Cash Flows $ ( 31,000 ) 10,000 20,000 10,000 10,000 5,000

Compute the following :

(a) Payback period


(b) Net present value (NPV) at 14 percent cost of capital
(c) Internal rate of return (IRR)

Problem – 11.

A company is considering two mutually exclusive projects. Both require an initial cash
out-lay of Rs.10,000 each, and have a life of five years. The company's required rate of
return is 10 percent and pays tax at a 50 percent rate. The projects will be depreciated
on a straight line basis. The before taxes cash flows expected to be generated by the
projects are as follows :

Before tax Cash Flow (Rs.)


Year
1 2 3 4 5
Project A 4,000 4,000 4,000 4,000 4,000
Project B 6,000 3,000 2,000 5,000 5,000

Calculate for each project :

(1) the payback.


(2) the average rate of return,
(3) the net present value and profitability index, and
(4) the internal rate of return. Which project should be accepted and why?

Problem – 12.

A company with a 10% cost of funds & limited investment of Rs.160 lakhs is evaluating
the desirability of several investment proposals.

Initial Investment Annual


Project Life
( Rs in Lakhs ) Cash Flow
A 120 5 30
B 80 3 32
C 80 4 25
D 40 7 8
E 120 9 15
Prepared by – Vinayanand Rele
Page 306 of 380 24/11/2008
Project Management

(i) Rank the projects according to PI & NPV


(ii) Determine optimal investment package.

Prepared by – Vinayanand Rele


Page 307 of 380 24/11/2008
Project Management

Problem – 13.

A company with 12% cost of funds and limited investment fund of Rs.4,00,000 is
evaluating the desirability of several investment proposals.

( Cash flow in Rs. / Project life in years )


Total Project Life Annual Cash
Project
Investment Years Inflow
A 3,00,000 2 1,87,600
B 2,00,000 5 66,000
C 2,00,000 3 1,00,000
D 1,00,000 9 20,000
E 3,00,000 10 66,000

(i) Rank the projects according to the profitability index and NPV method.
(ii) Determine optimal investment package.
(iii) Which projects should be chosen if investment limit is raised to Rs.5,00,000?

Note : - The following is an extract from table for the 'Present Value Factor' for an
annuity.

Years 1 2 3 4 5 6 7 8 9 10
12% 0.893 1.690 2.402 3.037 3.605 4.111 4.564 4.968 5.328 5.650

Solution :

PV of
Initial Annual PV Factor
RANK

RANK
Life in Cash NPV = PI =
Projects Investment ( Cash 12 %
Years Flow ( PV - I ) ( PV / I )
I) Flow ( Cumulative )
( PV )
A 2 300,000 187,600 1.690 317,044 17,044 4 1.06 5
B 5 200,000 66,000 3.605 237,930 37,930 3 1.19 3
C 3 200,000 100,000 2.402 240,200 40,200 2 1.20 2
D 9 100,000 20,000 5.328 106,560 6,560 5 1.07 4
E 10 300,000 66,000 5.650 372,900 72,900 1 1.24 1

Note : Always take PI Method for Ranking.

Take project C & E, i.e. 2,00,000 + 3,00,000 = 5,00,000.

If 4,00,000 would have been available then, we would have taken E & D projects

Prepared by – Vinayanand Rele


Page 308 of 380 24/11/2008
Project Management

16th April, 2008.

Lecture – XIV.

Cash Flow Evaluation


In this the cash flow is not given hence cash flow needs to be generated.

Before you start :-

1. Use Pencil for this exercise


2. Workout depreciation Schedule
3. Start Writing values

Remember :

1. You must Remember the Rows & columns of the table.

2. Mentioned below are to be written with Negative Signs.

a. Fixed Assets.
b. Net working Capital
c. Costs
d. Depreciation
e. Tax
g. Initial Outlay
h. Net Cash flow ( For First Year )

Prepared by – Vinayanand Rele


Page 309 of 380 24/11/2008
Project Management

Problem – 14.

“Futura Limited” is considering a capital project about which the following information is
available,

(i) The investment outlay on the project will be Rs.200 million. This consists of
Rs.150 million on the plant and machinery and Rs.50 million on net working
capital. The entire outlay will be incurred in the beginning.
(ii) The life of the project is expected to be 5 years. At the end of 5 years, fixed
assets will fetch a net salvage of Rs.48 million whereas the net working capital
will be liquidated at its book value.
(iii) The project is expected to generate the revenue of the firm by Rs.250 million per
year. The increase in costs on account of the project is expected to be Rs.100
million per year. (This includes all items on cost other than depreciation, interest
and tax). The tax rate is 30%.
(iv) Plant and machinery will be depreciated at the rate of 25% per year as per the
written down method.

Estimate the post-tax cash flows of the project, assuming cost of capital 12%.

Solution :

Working of Depreciation ( WDV Method ) – Figures in millions

Year Depreciation Book Value

1 25 % of 150 = 37.5 150 – 37.5 = 112.50


2 25 % of 112.5 = 28.12 112.5 – 28.12 = 84.37
3 25 % of 84.37 = 21.90 84.37 – 21.09 = 63.28
4 25 % of 63.28 = 15.82 63.28 – 15.82 = 47.46
5 25 % of 47.46 = 11.86

All computation with 2 decimal round-off.

Prepared by – Vinayanand Rele


Page 310 of 380 24/11/2008
Project Management

All Figure in Millions


Sr
Particulars 0 1 2 3 4 5
No
1 Fixed Assets -150.00
2 Net working Captial -50.00
3 Revenues 250.00 250.00 250.00 250.00 250.00
Cost
4 ( Other than Deprication & Tax ) -100.00 -100.00 -100.00 -100.00 -100.00
5 Depriciation -37.50 -28.12 -21.09 -15.82 -11.86
6 PBT (3) - (4) - (5) 112.50 121.88 128.91 134.18 138.14
7 Tax -33.75 -36.56 -38.67 -40.25 -41.44
8 PAT (6) - (7) 78.75 85.32 90.24 93.93 96.70
Net Salvage
9 Value of FA 48.00
10 Recovery of Net working Capital 50.00
11 Initial Outlay -200.00
Operating (8) + (5)
12 Cash Flows 116.25 113.44 111.33 109.75 108.56
Terminal
13 Cash Flows (9) + (10) 98.00
Net Cash Flows
14 (11) + (12) + (13) -200.00 116.25 113.44 111.33 109.75 206.56
15 PV Factor 1.000 0.893 0.797 0.712 0.636 0.567
PV of Cash Flow
16 (15) * (16) -200.00 103.81 90.41 79.26 69.80 117.12
NPV
17 (14) - (17) 12.44 23.03 32.06 39.95 89.44
196.92

Prepared by – Vinayanand Rele


Page 311 of 380 24/11/2008
Project Management

Problem – 15.

A company is considering a capital project about which the following information is


available :

(a) The investment outlay on the project will be Rs.400 lakhs. This consists of
Rs.300 lakhs on the plant and machinery and Rs.100 lakhs on net working
capital. The entire outlay will be incurred at the beginning of the project.
(b) The life of the project is expected to be 5 years, fixed assets will fetch a net
salvage value of Rs.96 lakhs where as net working capital will be liquidated at its
book value.
(c) The project is expected to increase the revenue of the firm by Rs.440 lakhs per
year. The increase in costs on account of the project is expected to be Rs.250
lakhs per year (This includes all items of cost other than depreciation , interest
and tax). The tax rate is 30%.
(d) Plant and machinery will be depreciated at the rate of 20% per year as per the
written down value method
(e) Cost of capital 10%

Using Net Present Value (NPV) method, determine whether the company should
undertake the above proposal or not:

Year 1 2 3 4 5 6 7
Present value at 10% 0.909 0.826 0.751 0.683 0.621 0.564 0.513

Prepared by – Vinayanand Rele


Page 312 of 380 24/11/2008
Project Management

Solution :

Working of Depreciation ( WDV Method ) – Figures in Lakhs

Year Depreciation Book Value

1 20 % of 300 = 60 300 – 60 = 240


2 20 % of 240 = 48 240 – 48 = 192
3 20 % of 192 = 38.4 192 – 38.4 = 153.6
4 20 % of 153.6 = 30.72 153.6 – 30.72 = 122.88
5 20 % of 122.88 = 24.58

All computation with 2 decimal round-off.

All Figure in Lakhs


Sr
Particulars 0 1 2 3 4 5
No
1 Fixed Assets -300.00
2 Net working Captial -100.00
3 Revenues 440.00 440.00 440.00 440.00 440.00
Cost
4 ( Other than Deprication & Tax ) -250.00 -250.00 -250.00 -250.00 -250.00
5 Depriciation -60.00 -48.00 -38.40 -30.72 -24.58
6 PBT (3) - (4) - (5) 130.00 142.00 151.60 159.28 165.42
7 Tax -39.00 -42.60 -45.48 -47.78 -49.63
8 PAT (6) - (7) 91.00 99.40 106.12 111.50 115.79
Net Salvage
9 Value of FA 96.00
10 Recovery of Net working Capital 100.00
11 Initial Outlay -400.00
Operating (8) + (5)
12 Cash Flows 151.00 147.40 144.52 142.22 140.37
Terminal
13 Cash Flows (9) + (10) 196.00
Net Cash Flows
14 (11) + (12) + (13) -400.00 151.00 147.40 144.52 142.22 336.37
15 PV Factor 1.000 0.909 0.826 0.751 0.683 0.621
PV of Cash Flow
16 (15) * (16) -400.00 137.26 121.75 108.53 97.13 208.89
NPV
17 (14) - (17) 13.74 25.65 35.99 45.08 127.49
247.94

Prepared by – Vinayanand Rele


Page 313 of 380 24/11/2008
Project Management

Problem – 16.

A company is considering a capital project about which the following information is


available.

(i) The initial outlay of the project would be Rs.50 Lakhs with a salvage value of
Rs.5 Lakhs.
(ii) The cost of capital is 12%.
(iii) The working capital required would be Rs.4 Lakhs which will be liquidated at the
book value when the project is terminated.
(iv) The life of the project is 6 years
(v) The yearly cost is Rs.12 Lakhs which exclude depreciation and tax.
(vi) The revenue generated in the first year is Rs.24 Lakhs which will increase by
Rs.4 Lakhs every year.
(vii) The depreciation will be charged as per the written down value method and the
rate is 25%.
(viii) The income tax rate is 40%.

Solution :

Working of Depreciation ( WDV Method ) – Figures in Lakhs

Year Depreciation Book Value

1 25 % of 50 = 12.50 50 – 12.50 = 37.50


2 25 % of 37.5 = 9.37 37.5 – 9.37 = 28.12
3 25 % of 28.12 = 7.03 28.12 – 7.03 = 21.09
4 25 % of 21.09 = 5.27 21.09 – 5.27 = 15.82
5 25 % of 15.82 = 3.95 15.82 – 3.95 = 11.86
6 25 % of 11.86 = 2.97

All computation with 2 decimal round-off.

Prepared by – Vinayanand Rele


Page 314 of 380 24/11/2008
Project Management

All Figure in Lakhs


Sr
Particulars 0 1 2 3 4 5 6
No
1 Fixed Assets -50.00
2 Net working Captial -4.00
3 Revenues 24.00 28.00 32.00 36.00 40.00 44.00
Cost
4 ( Other than Deprication & Tax ) -12.00 -12.00 -12.00 -12.00 -12.00 -12.00
5 Depriciation -12.50 -9.38 -7.03 -5.27 -3.96 -2.97
6 PBT (3) - (4) - (5) -0.50 6.62 12.97 18.73 24.04 29.03
7 Tax -2.45 -5.19 -7.49 -9.62 -11.61
8 PAT (6) - (7) -0.50 4.17 7.78 11.24 14.42 17.42
9 Net Salvage Value of FA 5.00
10 Recovery of Net working Capital 4.00
11 Initial Outlay -54.00
Operating (8) + (5)
12 Cash Flows 12.00 13.55 14.81 16.51 18.38 20.39
Terminal
13 Cash Flows (9) + (10) 9.00
Net Cash Flows
14 (11) + (12) + (13) -54.00 12.00 13.55 14.81 16.51 18.38 29.39
15 PV Factor 1.000 0.893 0.797 0.712 0.636 0.567 0.507
PV of Cash Flow
16 (15) * (16) -54.00 10.72 10.80 10.55 10.50 10.42 14.90
NPV
17 (14) - (17) 1.28 2.75 4.27 6.01 7.96 14.49
35.47

Note :

1. Since there is a Loss in the First Year No Tax will be Paid.


2. In the Next year such loss of the last year will be adjusted before paying tax,
So in the 2nd year tax will be ( 6.62 – 0.5 ) x 40 % = 2.45

Prepared by – Vinayanand Rele


Page 315 of 380 24/11/2008
Project Management

Problem – 17.

XYZ ENTER PRISE is contemplating a new investment project for which they are
considering the following information.

(a) Total cash outflow of the project will be Rs.10 crores, which consists of Rs.6
crores on plant and machinery and Rs.4 crores on gross working capital. The
entire outflow will be incurred at the beginning of the project.

(b) Project has a life of 5 years at the end of 5 years, plant and equipment would
fetch a salvage value of Rs.2 crores. Working capital will be liquidated at end of 5
years which will be equal to its book value (Rs.4 crores)

(c) The project will entail incremental revenues for the firm to the tune of Rs.8 crores
per annum, the incremental expenses on account of the project will be Rs.4
crores per annum, which includes all items of expenses excluding depreciation
and taxes.

(d) The effective tax rate is 50%.

(e) Cost of capital 14%.

(f) Depreciation is charged at 33.33% on the basis of Written Down Value Method.

(g) Help the enterprise, whether it should undertake the project or not on the basis of
NPV criterion.

Solution :

Working of Depreciation ( WDV Method ) – Figures in Lakhs

Year Depreciation Book Value

1 33.33 % of 600 = 199.98 600 – 199.98 = 400.02


2 33.33 % of 400.02 = 133.32 400.02 – 133.32 = 266.66
3 33.33 % of 266.69 = 88.88 266.69 – 88.88 = 177.80
4 33.33 % of 177.80 = 59.26 177.80 – 59.26 = 118.54
5 33.33 % of 118.54 = 39.51

Prepared by – Vinayanand Rele


Page 316 of 380 24/11/2008
Project Management

Solution :

All Figure in Lakhs


Sr
Particulars 0 1 2 3 4 5
No
1 Fixed Assets -600.00
2 Net working Captial -400.00
3 Revenues 800.00 800.00 800.00 800.00 800.00
Cost
4 ( Other than Deprication & Tax ) -400.00 -400.00 -400.00 -400.00 -400.00
5 Depriciation -199.98 -133.32 -88.88 -59.26 -39.51
6 PBT (3) - (4) - (5) 200.02 266.68 311.12 340.74 360.49
7 Tax -100.01 -133.34 -155.56 -170.37 -180.25
8 PAT (6) - (7) 100.01 133.34 155.56 170.37 180.25
9 Net Salvage Value of FA 200.00
10 Recovery of Net working Capital 400.00
11 Initial Outlay -1000.00
Operating (8) + (5)
12 Cash Flows 299.99 266.66 244.44 229.63 219.76
Terminal
13 Cash Flows (9) + (10) 600.00
Net Cash Flows
14 (11) + (12) + (13) -1000.00 299.99 266.66 244.44 229.63 819.76
15 PV Factor 1.000 0.877 0.769 0.675 0.592 0.519
PV of Cash Flow
16 (15) * (16) -1000.00 263.09 205.06 165.00 135.94 425.45
NPV
17 (14) - (17) 36.90 61.60 79.44 93.69 394.30
665.93

Prepared by – Vinayanand Rele


Page 317 of 380 24/11/2008
Project Management

Problem – 18.

Naveen Enterprises is considering a capital project about which he following information


is available:

(i) The investment outlay of the project will be Rs.100 million. This consists of Rs.80
million on plant and machinery and Rs.20 million on net working capital. The
entire outlay will be incurred at the beginning of the project
(ii) The project will be financed with Rs.45 million of equity capital, Rs.5 million of
preference capital and Rs.50 million of debt capital. Preference capital will carry a
dividend rate of 15%, debt capital will carry an interest 15%.
(iii) The life of the project is expected to be 5 years. At the end of 5 years, fixed
assets will fetch a net salvage value of Rs.30 million whereas net working capital
will be liquidated at its book value.
(iv) The project is expected to increase the revenue of the firm by Rs.120 million per
year. The increase in cost on account of the project is expected to be Rs.80
million per year (This includes all items of cost other than depreciation, interest
and tax). The effective tax rate will be 30%.
(v) Plant and machinery will be depreciated at the rate of 25% per year as per the
written down value method. Hence the depreciation charges will be:

First Year : Rs.20 million


Second Year : Rs.15 million
Third Year : Rs.11.25 million
Fourth Year : Rs.8.44 million
Fifth Year : Rs.6.33 million

Given the above details develop the project cash flows.

Prepared by – Vinayanand Rele


Page 318 of 380 24/11/2008
Project Management

Problem – 19.

The following is available for a project.

(i) Initial project outlay is Rs.200 lakhs. The finance structure is Working Capital
Loan Rs.20 lakhs, Term Loan Rs.100 lakhs and equity Rs.8 lakhs. The assets
structure is land Rs.5 lakhs, building Rs.55 lakhs and machinery Rs.120 lakhs
and current liabilities Rs.20 lakhs.
(ii) Term loan is repaid in 20 equal quarterly instalments as principal repayment.
Interest will be 20% p.a. The first instalment is due after 2 years.
(iii) The three products P,S and K manufactured have a capacity of 30,000 units
each per year. The selling prices are Rs.250, Rs.190 and Rs.130 respectively.
(iv) Working Capital remains unchanged for all 3 years and carries rate of interest of
12% p.a.
(v) Operating cost is 55% of sales revenue. The capacity utilization is 80% first year,
90% second year and 100% third year.
(vi) Depreciation is charged on fixed assets 20% p.a. on Written Down Value
method.

Evaluate project cash flows for first three years.

Solution :

Notes :

1. All fixed assets to be added, that is 5 + 55 +120 = 180


2. Evaluation is to be done for only 3 years as asked in the problem
3. Since Tax in not given 30 % is assumed
4. Since Salvage value is not given it is assumed to be Zeros
5. Recover of working capital is Zero
6. Interest to be ignored.

Prepared by – Vinayanand Rele


Page 319 of 380 24/11/2008
Project Management

Working of Depreciation ( WDV Method ) – Figures in Lakhs

Year Depreciation Book Value

1 20 % of 180 = 36 180 – 36 = 144.00


2 20 % of 144 = 28.80 144 – 28.80 = 115.20
3 20 % of 115.20 = 23.04

Calculation of Revenues

Year – 1

Product Max Qty Produced Net Qty Sale Rate Revenue


P 30000 80% 24000 250 6,000,000
S 30000 80% 24000 190 4,560,000
K 30000 80% 24000 130 3,120,000
13,680,000

Year – 2

Product Max Qty Produced Net Qty Sale Rate Revenue


P 30000 90% 27000 250 6,750,000
S 30000 90% 27000 190 5,130,000
K 30000 90% 27000 130 3,510,000
15,390,000

Year – 3

Product Max Qty Produced Net Qty Sale Rate Revenue


P 30000 100% 30000 250 7,500,000
S 30000 100% 30000 190 5,700,000
K 30000 100% 30000 130 3,900,000
17,100,000

Prepared by – Vinayanand Rele


Page 320 of 380 24/11/2008
Project Management

Sr No Particulars 0 1 2 3
1 Fixed Assets -180.00
2 Net working Captial -20.00
3 Revenues 136.80 153.90 171.00
Cost
4 ( Other than Deprication & Tax ) -75.24 -84.65 -94.05
5 Depriciation -36.00 -28.80 -23.04
6 PBT (3) - (4) - (5) 25.56 40.45 53.91
7 Tax -7.67 -12.14 -16.17
8 PAT (6) - (7) 17.89 28.32 37.74
Net Salvage
9 Value of FA 0.00
10 Recovery of Net working Capital 0.00
11 Initial Outlay -200.00
Operating (8) + (5)
12 Cash Flows 53.89 57.12 60.78
Terminal
13 Cash Flows (9) + (10) 0.00
Net Cash Flows
14 (11) + (12) + (13) -200.00 53.89 57.12 60.78
15 PV Factor 1.000 0.909 0.826 0.621
PV of Cash Flow
16 (15) * (16) -200.00 48.99 47.18 37.74
NPV
17 (14) - (17) 4.90 9.94 23.03

Prepared by – Vinayanand Rele


Page 321 of 380 24/11/2008
Project Management

Problem – 20.

The details of a capital investment project are given below:

Initial investment for plant and machinery : Rs. 100 Lakhs


Additional investment in working capital : Rs. 40 Lakhs
Sales (units) per years for years 1 to 5 : Rs. 1 Lakhs
Selling price per unit : Rs. 120/-
Variable cost per unit : Rs. 60/-
Fixed overheads (excluding depreciation)
per year for years 1 to 5 : Rs. 15 Lakhs
Rate of depreciation on plant and machinery : 25 % by WDV Method
Salvage value of plant and machinery (years) : Rs. 10 Lakhs
Applicable tax rate : 40 %
Time Horizon : 5 years
Post-tax cut off rate : 12 %

Calculate NPV of the project.

Discount Years
Factor 0 1 2 3 4 5 6 7
12% 1.000 0.8929 0.7972 0.7118 0.6355 0.5674 0.5066 0.4523
25% 1.000 0.8000 0.6400 0.5120 0.4096 0.3277 0.2621 0.2097
40% 1.000 0.7143 0.5102 0.3644 0.2603 0.1859 0.1328 0.0949

Solution :

Notes :

1. Variable cost to be added in Cost, also it is there for 0th year.


2. Since Time Horizon is 5 year Depreciation will be for 5 year.
3. Salvage & Recovery of working capital is not considered as the information about
it is not given.
4. Since Post Tax cut off rate is given it is considered for PV Factor.

Prepared by – Vinayanand Rele


Page 322 of 380 24/11/2008
Project Management

Working of Depreciation ( WDV Method ) – Figures in Lakhs

Year Depreciation Book Value

1 25 % of 100 = 25 100 – 25 = 75
2 25 % of 75 = 18.75 75 – 18.75 = 56.25
3 25 % of 56.25 = 14.06 56.25 – 14.06 = 42.18
4 25 % of 42.18 = 10.55 42.18 – 10.55 = 31.63
5 25 % of 31.63 = 7.91

Sr
Particulars 0 1 2 3 4 5
No
1 Fixed Assets -100.00
2 Net working Captial -40.00
3 Revenues 120.00 120.00 120.00 120.00 120.00
Cost
4 ( Other than Deprication & Tax ) -60.00 -75.00 -75.00 -75.00 -75.00 -75.00
5 Depriciation -25.00 -18.75 -14.06 -10.55 -7.91
6 PBT (3) - (4) - (5) 20.00 26.25 30.94 34.45 37.09
7 Tax -8.00 -10.50 -12.38 -13.78 -14.84
8 PAT (6) - (7) 12.00 15.75 18.56 20.67 22.25
Net Salvage
9 Value of FA
10 Recovery of Net working Capital
11 Initial Outlay -140.00
Operating (8) + (5)
12 Cash Flows 37.00 34.50 32.62 31.22 30.16
Terminal
13 Cash Flows (9) + (10) 0.00 0.00
Net Cash Flows
14 (11) + (12) + (13) -140.00 37.00 34.50 32.62 31.22 30.16
15 PV Factor 1.0000 0.8929 0.7972 0.7118 0.6355 0.5674
PV of Cash Flow
16 (15) * (16) -140.00 33.04 27.50 23.22 19.84 17.12
NPV
17 (14) - (17) 3.96 7.00 9.40 11.38 13.05

Prepared by – Vinayanand Rele


Page 323 of 380 24/11/2008
Project Management

25th April, 2008.

Lecture – XV. ( Last Lecture )

Network Technique

There are two techniques AOA ( Activity on Arrow ) by which activity can be shown
as below :
A
1 2
5

There is another Method AON ( Activity on Node ) where the activity can be shown
as below :

A/5

Where A is the Activity and 5 is the duration. This method is also known as
“Precedence Diagram”.

Below activity of AOA

A B
1 2 3
5 6

Can be shown in AON as

A/5 B/6

Suppose B & C starts after A then with AON it can be shown as

Prepared by – Vinayanand Rele


Page 324 of 380 24/11/2008
Project Management

Suppose Z starts after X & Y

Example -1 :

A B C D E F G H
- A A A B C D E,F,G

3
B E

A C F H
1 2 4 7
6
D
G

B E

A C F H

D G

Prepared by – Vinayanand Rele


Page 325 of 380 24/11/2008
Project Management

Example - 2

A B C D E F G H
- - A A B D.E C F,G

4
C
G

2
A D
F H
5 6 7
1 E
B

C G

A D F H End

Start

B E

Prepared by – Vinayanand Rele


Page 326 of 380 24/11/2008
Project Management

Example - 3

A B C D E F
- A A B C D

( Dangler )

D
3 5
B

A F
1 2
C

E
4 6

B D C

Start A End

E
C

Prepared by – Vinayanand Rele


Page 327 of 380 24/11/2008
Project Management

Example - 4

A B C D E F
- A B B C D,E

3 5 4 8 7 6 12

12

0 8 8
4
0 3 8 C

A 4 19 25
B E 7
1 2 3
3 5 19
D 25

4 E
5 6
6

EST EFT
Activity

Duration

0
LST
LFT

8 12 12 19

C/4 E/7
8 0 12 12 0 19
3 8
0 3

A/3 B/5 19 25

0 0 3 0 8
F/6
3
19 25
5 13

D/8
11 3 19

Prepared by – Vinayanand Rele


Page 328 of 380 24/11/2008
Project Management

Example – 5.

A B C D E F G
- - B B B E A,D,C

4 5 6 3 8 11 4

( Dummy )
11
0

20
0

A 4
1
4
24
C G
B D1
5 6 4 24

D 6
5 2 3
3
5
E 8 20 F
8
11

5 13 13

0 4

A/4
16 20

5 11
0 0
C/6 11 15
Start
14 20 G/4
0 0
0 5 5 8 20 24

D/3 26 24
B/5
END
0 17 20
5
5 13 24 24
13 24
F/11
E/8
5 13 13 24
Prepared by – Vinayanand Rele
Page 329 of 380 24/11/2008
Project Management

Two Approaches to Network Drawing

The two approaches used to develop project networks are known as activity on node
(AON) and activity on arrow (AOA). Both methods use two building blocks the arrow and
the node. Their names derive from the fact that the former uses a node to depict an
activity, while the second uses an arrow to depict an activity.

Basic Rule to Follow in Developing Project Networks

The following eight rules apply in general when developing a project network:

1. Networks flow typically from left to right.


2. An activity cannot begin until all preceding connected activities have been
completed.
3. Arrows on networks indicate precedence and flow. Arrows can cross over each
other.
4. Each activity should have a unique identification number.
5. An activity identification number must be larger than that of any activities that
precede it.
6. Looping is not allowed (in other words, recycling through a set of activities cannot
take place).
7. Conditional statements are not allowed that is this type of statement should not
appear. If successful, do something, if not, do nothing.
8. Experience suggests that when there are Qlultiple starts, a common start node
can be used to indicate a clear project beginning on the network. Similarly a
single project end node can be used to indicate a clear ending.

Activity- on- Node (AON) Fundamentals

The wide availability of personal computes and graphics programs has served as an
impetus for use of the activity on node (AON) method (sometimes called the
precedence diagram method). Figure 1 shows a few typical uses of building blocks for
the AON network construction. An activity is represented by a node (box). The node can
take many forms, but in recent years the node represented as a rectangle (box) has
dominated. The dependencies among activities are depicted by arrows between the
rectangles (boxes) on the AON network. The arrows indicate how the activities are
related and the sequence in which things must be accomplished. The length and slope
of the arrow are arbitrary and set for convenience of drawing the network. The letters in
the boxes server here to identify the activities while you learn the fundamentals of
network construction and analysis. In practice, activities have identification numbers and
descriptions.

Prepared by – Vinayanand Rele


Page 330 of 380 24/11/2008
Project Management

There are three basic relationships that must be established for activities included in a
project network. The relationships can be found by answering the following three
questions for each activity.

1. Which activities must be completed immediately before this activity? These


activities are called predecessor activities.
2. Which activities must immediately follow this activity? These activities are called
successor activities.
3. Which activities can occur while this activity is taking place? This is known as a
concurrent or parallel relationship.

Activity - on - Node Network Fundamentals

(i)
A is preceded by nothing
B is preceded by A
C is preceded by B

(ii)

Y and Z are preceded by X


Y and Z can begin at the same time, if
you wish

(iii)

J, K & L can all begin at the same time,


if you wish (they need not occur
simultaneously)

but

All (J, K, L) must be completed before M


can begin

(iv)

Z is preceded by X and Y
AA is preceded by X ad Y

Prepared by – Vinayanand Rele


Page 331 of 380 24/11/2008
Project Management

Above (i) is analogous to a list of things to do where you complete the task at the top of
the list first and then move to the second task, etc. This figure tells the projects manager
that activity A must be completed before activity B can begin, and activity B must be
completed before activity C can begin.

Above (ii) tells us that activities Y and Z cannot begin until activity X is completed. This
figure also indicates that activities Y and Z can occur concurrently or simultaneously if
the project manager wishes: however, it is not a necessary condition. For example,
pouring concrete driveway (activity Y) can take place while landscape planting
(activityZ) is being accomplished, but land clearing (activity X) must be completed
before activities Y and Z can start. Activities Y and Z are considered parallel activities.
Parallel paths allow concurrent effort, which may shorten time to do a series of activities.
Activity X is sometimes referred to as a burst activity because more than one arrow
bursts from the node. The number of arrows indicates how many activities immediately
follow activity X.

Above (iii) shows us activities, J, K and L can occur simultaneously if desired and
activity M cannot begin until activities J, K and L are completed. Activities J, K and L are
parallel activities. Activity M is called a merge activity because more than one activity
must be completed before M can begin. Activity M could also be called a milestone.

And in (iv), activities X and Yare parallel activities that can take place at the same time,
activities Z and AA are also parallel activities. But activities Z and AA can not begin until
activities X and Yare both completed.

Given these fundamentals of AON, we can practice developing a simple network.

Remember, the arrows can cross over each other (e.g. (iv above)), be bent, or be of any
length or slope. Neatness is not a criterion for a valid, useful network - only accurate
inclusion of all projects activities, their dependencies, and time estimates. Information
for a simplified project network is given in Table 1. This project represents a new
business center that is to be developed and the work and services the county
engineering design department must provide as it coordinates with other groups '- such
as the business center owners and contractors.

Prepared by – Vinayanand Rele


Page 332 of 380 24/11/2008
Project Management

Table – 1 Network Information

Activity Description Preceding


A Application approval None
B Construction plans A
C Traffic study A
D Service availability check A
E Staff report B,C
F Commission approval B,C,D
G Wait for construction F
H Occupancy E,G

Koll Business Center - Complete Network

Prepared by – Vinayanand Rele


Page 333 of 380 24/11/2008
Project Management

AON Method

Advantages :

1. No dummy activities are used.


2. Events are not used.
3. AON is easy to draw if dependencies are not intense.
4. Activity emphasis is easily understood by first-level managers.
5. The CPM approach uses deterministic times to construct networks.

Disadvantages :

1. Path tracing by activity number is difficult. If the network is not available,


computer outputs must list the predecessor and successor activities for each
activity.
2. Network drawing and understanding are more difficult when dependencies are
numerous.

AOA Method

Advantages :

1. Path tracing is simplified by activity event numbering scheme.


2. AOA is easier to draw if dependencies are intense.
3. Key events or milestones can easily be flagged.

Disadvantages :

1. Use of dummy activities increases data requirements.


2. Emphasis on events can detract from activities. Activity delays cause events and
projects to be late.

Prepared by – Vinayanand Rele


Page 334 of 380 24/11/2008
Project Management

Choice of method - AON or AOA

In AOA networks, dummy activities meet two needs. First, when two parallel activities
have the same start and end nodes, a dummy must be inserted to give each activity a
unique identification number. Next, dummy activities can be used to clarify dependency
relationships. Dummy activities are very useful when activity dependencies are far apart
on the network. The major advantage of the AOA method is the avoidance of having to
list all the predecessor and successor activities for each activity in the network so
activity sequence and dependency can be traced when a network is not available or
shows incomplete information. Computer output is reduced many fold.

LAD AND LAG

The method of showing relationships among activities discussed earlier is called the
Finish -to Start relationship because it assumes all immediate preceding connected
activities must be completed before the next activity can begin. In an effort to come
closer to the realities of projects, some useful extensions have been added. Te use of
laddering was the first obvious extension practitioners found very useful.

Laddering

The assumption that all immediate preceding activities must be 100 percent complete is
too restrictive for some situations found in practice. This restriction occurs most
frequently when one activity overlaps the start of another and has a long duration.
Under the standard Finish - to- Start relationship, when an activity has a long duration
and will delay the start of an activity immediately following it, the activity can be broken
into segments and the network drawn using a Laddering approach so that the following
activity can begin sooner and not delay the work.

Prepared by – Vinayanand Rele


Page 335 of 380 24/11/2008
Project Management

e.g. LAYING OF PIPE

The trench must be dug, pipe laid and the trench refilled. If the pipeline is one mile long,
it is not necessary to dig one mile of trench before the laying of pipe can begin or to lay
one mile of pipe before refill can begin.

Figure below shows how these overlapping might appear in an AON network using the
standard Finish - to - Start approach

Prepared by – Vinayanand Rele


Page 336 of 380 24/11/2008
Project Management

Use of Lags :

The use of lags has been developed to offer greater flexibility in network construction. A
lag is the minimum amount of time a dependent activity must be delayed to begin or to
end. The use of lags in project networks occurs for two primary reasons.

(1) When activities of long duration delay the start or finish of successor activities,
the network designer normally breaks the activity into smaller activities to avoid
the long delay of the successor activity. Use of lags can avoid such delays and
reduce network detail.
(2) Lags can be used to constrain the start and finish of an activity.

Examples:

A lag is positive and indicates the number of time periods that must pass before the
succeeding activity can start. E.g. a lag of +5 placed on a finish - to - start link means
that activity B can start five time units after activity A has ended.

A lag is positive and indicates the number of time periods that must pass before the
succeeding activity can start. E.g. a lag of +5 placed on a finish - to - start link means
that activity B can start five time units after activity A has ended.

The most commonly used relationship extensions are Start - to - Start, Finish - to -
Finish and the combination of these two.

Prepared by – Vinayanand Rele


Page 337 of 380 24/11/2008
Project Management

Finish - to - Start Relationship

The arrowhead on the line indicates the direction of flow and thus the precedence.
Activity B is A's successor. The logical link shown here is called a "Finish - to - Start link,
as it connects the finish of activity A to the start of activity B. This means that activity B
can not start unless activity A has ended.

There are situations in which the next activity in a sequence must be delayed even
when the preceding activity is complete.

Lag - 2

Activity Y starts say 2 days after activity X is completed.

Finish - to - start lags are frequently used when ordering materials. For example, it may
take 1 day to place orders but take 19 days to receive the goods. The use of finish - to -
start allows the activity duration to be 1 day and the lag 19 days. This approach ensures
the activity cost is tied to placing the order only rather than charging the activity for 20
days of work.

Prepared by – Vinayanand Rele


Page 338 of 380 24/11/2008
Project Management

Start - to - Start Relationship

Typical Start - to - Start relationships are shows in figure below. Figure - A shows the
start - to start relation with zero lag, while figure - B shows the same relationship with a
lag of 4 time units.

It is important to note that the relationship may be used with or without lag. If time is
assigned, it is usually shown on the dependency arrow of an AON network.

Figure A below shows that activities M and N can start at the same time.

In figure B, activity Q cannot begin until five units after activity P begins. This type of
relationship typically depicts a situation in which you can perform a portion of one
activity and begin a following activity before completing the first. This relationship can be
used on the pipe-laying project. Figure C shows the project using an AON network. The
Start - to - Start relationship reduces network detail and project delays by using lag
relationship.

Prepared by – Vinayanand Rele


Page 339 of 380 24/11/2008
Project Management

It is possible to change finish to start relations to start to start relationships.

e.g. in place of a finish - to start activity "design house, then build foundation", a start -
to - start relationship could be used in which the foundation can be started, say, five
days (lag) after design has started - the design of the foundation is the first part of the
total design activity.

Prepared by – Vinayanand Rele


Page 340 of 380 24/11/2008
Project Management

EXAMPLE

Draw the network using AON method.

Activity Immediate Duration


Description Predecessor (weeks)
Start - 0
A Start 16
B Start 20
C Start 30
D B 15
E B 10
G 0 3
H D 16
J A 15
K J, G, E 12
Finish K, H,C 0

Calculating the critical path duration

The network described in the activity sequencing table above and shown as the network
diagram will be used to illustrate the network calculations. The network calculations will
result in a number of values being determined for each activity. All the values need to be

Prepared by – Vinayanand Rele


Page 341 of 380 24/11/2008
Project Management

recorded on the diagram or in a table. If recorded in the network diagram, the values are
attached to the activity as follows :

EST EFT
Activity

Duration

0
Float
LST
LFT

Where,

EST = Earliest Start Time


EFT = Earliest Finish Time
LST = Latest Start Time
LFT = Latest Finish Time

The early start time ( EST ) for an activity is the earliest time that an activity can start
given that all its predecessor activities have been completed. The EST for an activity
having no predecessor is always set to 0. The early finish time ( EFT ) of an activity is
the earliest time that an activity can be completed. It is equal to the EST Plus its
estimated duration.

The EST time of an activity that have one predecessor is the EFT of the predecessor.
The EST of an activity that has two or more predecessor is the greatest of the EFT of all
its predecessors. To calculate these ties, work forward through the network –
performing a forward pass.

The late start (LST) time and late Finish time ( LFT ) of an activity are the latest times at
which an activity can start (LST) or be completed (LFT) without affecting the project
duration. The LST of an activity is equal to its LFT minus its estimated duration. The
LFT of an activity that has only one successor is the LST of the successor. The LFT of
an activity having two or more successor is the least of the LS of all successor. To
calculate these times, work backwards through the network performing a backward
pass.

Prepared by – Vinayanand Rele


Page 342 of 380 24/11/2008
Project Management

The Forward Pass

A forward pass is performed as follows :

1. Set the EST of the first activity in the network to 0 and its EFT equal to the
activity duration.
2. Then for each other activity in the network calculate its EST as the greatest of
the EFT of all its predecessor activities. Calculate each activity’s EFT as its EST
plus duration.

After performing the forward pass, the network now looks as shown below :

Prepared by – Vinayanand Rele


Page 343 of 380 24/11/2008
Project Management

The Backward Pass

A Backward pass is performed as follows :

1. First set the LFT of the last activity in the network to EFT of that activity.
Calculate its LST as its LFT minus the activity duration.
2. Then for each other activity in the network calculate its LFT as the least of the
LST of all the activities for which it is the predecessor. Calculate each activity’s
LST as its LFT minus duration.

After performing the Backword pass, the network now looks as shown below :

The resulting network diagram indicates the various paths through the project network
logic, the relationship between the various activities and paths through the network and
provides information on time duration – all of which are necessary to determine the
critical path.

Prepared by – Vinayanand Rele


Page 344 of 380 24/11/2008
Project Management

Exercise – 1.

Draw a project network from the following information.

Activity Predecessor
A None
B None
C A,B
D A,B
E A,B
F C,D
G E
H F
I F,G

Exercise – 2.

Draw a project network from the following information.

Activity Predecessor
A None
B None
C None
D A,B
E B,C
F D,E
G F
H F
I G
J H,I

Exercise – 3.

Draw a project network from the following information.

Activity Predecessor
A None
B A
C A
D A
E B
F B
G C
H D
I F,G
J E,I,H
Prepared by – Vinayanand Rele
Page 345 of 380 24/11/2008
Project Management

Theory ( Project Management )


Definition of A Project :

A project is a “Temporary Endeavour undertaken to create a unique product or Service”.

The amended definition is :

A project is a “Temporary Endeavour undertaken to Crate a unique outcome or results”.

Project Characteristics

• Project are Unique.


• Projects are Temporary in Nature and have definite beginning and ending
dates.
• Projects are completed when the project goals are achieved ore it’s
determined that the project is no more viable.
• A successful project is one that meats or exceeds the expectations of the
stakeholders.
• It is focused on the customer and customer expectations.
• It is made of collection of activities, that are linked together to achieve certain
results.
• It is complex and involved different departments.
• It has to be flexible to accommodate the changes.
• It has many unknown factors & external influences.
• It has cost constraints.
• Involves risks.
• Comprises many sub-projects.
• Requires expertise in many fields.
• Challenges Traditional line of authority
• Provides opportunity for learning.
• Builds team spirit.
• It consumes large resources.
• It requires special controls
• It is tasks & performance oriented.
• It Requires a task & performance oriented leader.

Stakeholders

Stakeholder are those individuals ( or Organisations ) with a vested interest in your


project. They are the people who are actively involved with the work of the project or
have something to either gain or loose as a result of the project.

Prepared by – Vinayanand Rele


Page 346 of 380 24/11/2008
Project Management

Stages or Phases of a Project.

Due to their uniqueness, projects involves a high degree of uncertainty. Organisations


performing projects usually divide a project into phases to better provide management
planning and control and identify appropriate links to the organisations ongoing
operations. Collectively, the project phases are known as the Project Life Cycle.

The various of Phases of Project are :

1. Project Conception Phase :

i) Project Scouting and Establishment of Need


ii) Identification of Project and Preliminary Screening
iii) Feasibility Testing

2. Project Definition Phase :

i) Visualization of the Project Features.


ii) Preparation of Detailed Project Report.

3. Project Planning and Organization Phase.

i) Appraisal of Project – Examination of Technical, Organisational,


Marketing, Financial, Economic and Social Aspects of the Project.
ii) Final Selection and Investment Decision.

4. Implementation Phase.

i) Implementation of Project – Establishment of Project organisation for ,


Planning and Mangement.
ii) Project follow-up : Monitoring and Control

5. Project Clearing Phase.

i) Project Fruitarion : Production / Service, Distribution and Consumer


Services.
ii) Ex-Post Evaluation.

Prepared by – Vinayanand Rele


Page 347 of 380 24/11/2008
Project Management

Project Management

Project Management is defined as :

“The application of knowledge, skills, tools and techniques to project activities in order to
meet or exceed stakeholders needs and expectations from a Project”. Meeting or
exceeding stakeholders needs and expectations involves balancing competing
demands among :

• Scope, time, cost and quality


• Stakeholders with differing needs and expectations
• Identified requirements ( needs ) and unidentified requirements ( Expectations )

Project Management Knowledge Areas :

Modern project management recognises nine knowledge areas as described below :

1. Project Integration Management : relates to the process require to ensure that


the various elements of the project co-ordinated. It includes plan development,
execution and overall change control

2. Project Scope Management : means ensuring that the project includes all the
work required and only the work required, to complete the project successfully. It
covers scope initiation, planning, definition, verification and change control.

3. Project Time Management : includes the decision and required to ensure timely
completion of the project, such as activity definition, sequencing, duration
estimating, schedule development and control.

4. Project Cost management : refers to the process required to ensure that the
project is completed within the approved budget – resource planning, cost
estimating, cost budgeting and control

5. Project Quality requirement : means the processes required to ensure that the
project that the project will satisfy the needs for which it was undertaken. It
covers quality planning, assurance and control.

6. Project Human Resource management : is making the most effective use of the
people involved with the project. It includes organizational planning, staff
acquisition and team development.

7. Project Communication Management : refers to the processes required to


ensure timely and appropriate generation, collection, dissemination, storage and
ultimate disposition of project information. It entails communications planning,
information distribution, performance reporting and administrative closure.

Prepared by – Vinayanand Rele


Page 348 of 380 24/11/2008
Project Management

8. Project Risk management means identifying, analyzing and responding to project


risk. It includes risk identification, risk quantification, risk response development
and risk response control.

9. Project Procurement management covers the processes required to acquire


goods and services from outside the performing organization - procurement
planning, solicitation planning, solicitation, source selection, contract
administration and contract close-out.

SCOPE OF PROJECT MANAGEMENT

The project management covers:

(i) Idea generation, analysis & finalization of one or more ideas for implementation,
(ii) Preparation of feasibility reports for various projects ( ideas), working out facilities
& finance requirements, benefits & long-term viability as well as profitability.
(iii) Identification of partners needed.
(iv) Technology requirements.
(v) Organisational requirements.
(vi) Probable sites & building requirements.
(vii) Commercial aspects.
(viii) Environmental effects & action required.
(ix) Govt. concessions available etc.

After finally getting the Feasibility report approved by the concerned authorities- as the
case may be, further actions required will be: -

PREPARATION OF DETAILED PROJECT REPORT (DPR)

This will deal with all the aspects of the project in details namely.

• Man power: How many managerial, supervisory & workmen ?


• Machines: Types, quantity & suppliers.
• Materials: Detailed specifications of various materials & their procurement
• pattern- make or by decisions.
• Layout & space requirements.
• Funds requirements & budget.
• Pay back period / cost benefit analysis.
• Process & technology
• Planning & progress control. etc

Prepared by – Vinayanand Rele


Page 349 of 380 24/11/2008
Project Management

APPROVAL OF DPR.

A Thorough study & scrutiny will be made of the DPR by the TOP management &
finance experts. If it requires clearance by specific Govt. Agencies, then a copy will be
sent to them for obtaining c1earance- Such as, from factory inspector, environment
dept., fire fighting dept., industries dept., municipality etc.

If the project is limited to a particular industry -such as introducing a new product,


increasing production, replacement of old plant & machinery & like, approval of board of
directors is necessary.

Detailed Project Report (DPR)

A Detailed Project Report (DPR) is a document containing detailed description of


important aspects of a Project. This is prepared after initial hurdles in the process of
getting the Project cleared, have been crossed and the need for Project has been
established.

A detailed Project Report generally contains the following details:

1. Background of the Project : The background of the project is described in


terms of its basis. This generally include the type of project, the sector of
economy it belongs to, its location, gestation period, brief description, technical
details such as scope, process, scale, maps and designs, target beneficiaries,
etc.

2. Objectives of the Projects : The objectives are specified in terms of general


objectives, specific objectives, physical targets to be achieved etc.

3. Justification for the Project : The justification for the Project is based on
technical organizational, marketing, financial, economic and environmental
appraisal of the project.

4. Cost of Project and Sources of Funding : The cost of Project is determined by


considering and including all the items of capital outlay. The arrangement made
for meeting the requirement of funds for the project is specified in terms of capital
structure, sources of funds and amount proposed to be raised from each source.

5. Salient Features of the Project : The salient features descried included, foreign
exchange requirement and contribution, estimated sales revenue, estimated
production cost, expected return on investment, social cost and benefits, extent
of public participation, role of government, participation of non-governmental
organizations, etc.

Prepared by – Vinayanand Rele


Page 350 of 380 24/11/2008
Project Management

6. Project Organization : Regarding the project organization and its personnel, the
details regarding organization chart, line of control, authority-responsibility
structure, extent of delegation, mechanism for monitoring and follow up, project
control mechanism, etc. are given.

7. Implementation Details : The implementation details for a project are given in


terms of sequence of tasks and activities, resource requirement, precautions,
safety requirement, etc. The programme of activities is also given under it. This
includes details regarding the activities covered, such as implementation
requirement, time schedule, activities and events, critical activities, activity-wise
resource requirement management control system, budgeting and budgetary
control system, management information system, etc.

Project Results :

The project results are given in terms of quantitative as well as non-quantitative


information both, such as year-wise targets to be achieved, area to be covered, persons
benefiting etc.

Prepared by – Vinayanand Rele


Page 351 of 380 24/11/2008
Project Management

APPOINTMENT & ROLE OF CONSULTANT IN PROJECT.

Introduction

Most of the project owners use the services of a consultant - An individual consultant or
a consulting firm or a captive consulting organization throughout the project duration.
Even when the owner has a competent project team, a consultant may be appointed for
the following reasons.

a) The functional experts of various departments who are also the members of the
project team will have many other parallel responsibilities which are bound to
divert their attention from the project.
b) A multi-disciplinary consultant's deep knowledge, rich experience and
concentrated attention to all important aspects of a project will, no doubt, boost
its efficiency, justifying the consultancy cost.
c) An independent consultant will view all matters in an unbiased manner.

General Issues Concerning Appointment

Determination of consultant's role in the project.

(a) Types of consultant


(b) The Role of Domestic consultant
(c) Selection & appointment
(d) Terms of reference
(e) Actual use of consultant
(f) Co-ordination procedure
(g) Professional - liability

Consultant's Role

A consultant can be used either in an "Advisory Role” or in a “Participatory Role". In the


advisory role, after accomplishing the task of the study phase, he might continue as an
advisor, without involving himself in the implementation.

His assignments in this role will be : -

• Pre-Investment investigation
• Preparation of feasibility report
• Preparation of detailed project report
• Preparation of project specifications & tender documents
• Giving advice on problems.

Prepared by – Vinayanand Rele


Page 352 of 380 24/11/2008
Project Management

He shall play the roles of a planner, an organizer, and effective co-ordinator, an advisor
in decision making, a counselor in overcoming the usual resistance to change and a
multidisciplinary management guide, committed to the client's success and profitability.

His role can further be increased to macro and micro- level planning of various activities
such as defining project scope, organizing project team, assisting in procurement of
critical equipments, scheduling & process chasing. Supply of technology or design is
optional.

Types of Consultants

(i) Technical specialists.


(ii) Functional experts.
(iii) Multi-Disciplinary generalists

The last one are the most sought- after

Domestic Consultant :

Whenever a foreign consultant is appointed, he has to work with a domestic consultant,


as per central govt. guidelines

Selection and Appointment :

Following selection process is followed :

a) Determination of consultant's role (term of reference)


b) Determination of pre-qualification criteria.

i) Cost
ii) Short - Listing
iii) Final selection
iv) Negotiations on terms & conditions
v) Appointment ( Decide type)

Other points are self explanatory

The selection criteria should also include:

i) General & technical qualifications of personnel proposed to be employed on the


project.
ii) Suitability of their experience to the specific requirements of the tasks.
iii) Local language ability, knowledge of the cultural background of project area.
iv) Probable impact on the project of the consultancy assignment.

Prepared by – Vinayanand Rele


Page 353 of 380 24/11/2008
Project Management

ECONOMIC APPRAISAL OF A PROJECT

Introduction

In case of commercial projects, the real justification for the project comes from the
economic viability. Accordingly, a project should be capable of producing an adequate
return on the investment and the rate of return should be higher than the cost of funds
or the required rate of return. A project is doomed to fail without economic viability.

The object of economic appraisal of a project is to analyse the aspects of cost of funds
and ROI over the life of the project and to determine whether the project shall be able to
give adequate ROI or not.

Scope

(a) Initial Investment outlay.

This specifies the requirement of funds for the project to begin with. It includes
the expenditure on design, survey, consultancy, land, plant & machinery, building
etc. & Minimum working capital, contingency etc.

b) Subsequent Investment outlays.

Some times the project is taken in phases. In such cases, subsequent investment
has to be provided for

c) Economic life of project:

This is determined by the stage upto which the project is expected to produce
positive cash flows and income flows. In other words, the project should produce
adequate ROI to justify its continuance on economic consideration.

(d) Salvage value:

At the end of economic life, different assets, belonging to the project, when
scrapped & disposed off, are expected to realize some value for the project.

(e) Operating cash flows:

These are generated from the sales revenue after deducting production cost and
overheads.

Prepared by – Vinayanand Rele


Page 354 of 380 24/11/2008
Project Management

(f) Depreciation :

Depreciation is charged with the object of distributing the cost of fixed assets
over their entire useful life. However, since it does not involve cash out flow, it is
added to the earning after interest and tax to determine the net cash inflow/ out
flow.

g) Rate of Tax :

Tax is charged by the state on profit and also on other earnings of the business
enterprise. This affects the surplus available for payment as dividend and also
results in outflow of cash.

h) Cost of Funds :

Funds required for a project are generally loans from bank or other sources,
which have got a cost. Cost of funds forms the basis for determining the present
value of inflows and the net present value of the project.

i) Opportunity cost :

The Opportunity cost of funds invested in a project is the expected return from
the alternative investment or the opportunity of investment foregone by the
investors while making investment in the project. The expected ROI, should be
higher than opportunity cost.

Prepared by – Vinayanand Rele


Page 355 of 380 24/11/2008
Project Management

PROJECT RISK

What is Risk ?

A risk is any uncertain event, if it occurs, could prevent the project realizing the
expectations of the stakeholders as stated in the agreed business case, project brief or
agreed definition. A risk that becomes reality is trended as an "Issue".

A Risk always has a cause and, if it occurs, a consequence, Risk can have negative or
positive consequences, success is dependent on maintaining a high commitment to risk
management procedures throughout the project. Two fundamental type of risks are
always present. :-

a) Project Risk –

Associated with the technical aspects of the work to achieve the required
outcomes and

b) Process Risk: -

Associated with the project process, procedures, tools & technique employed,
controls, communication, stakeholders and team performance,

Risk V/s Uncertainty

"Risk" can be defined as the variability of return from an investment & the possibilities of
the effect are known., but in uncertainty, the outcome cannot be predicated.

Kinds of Risks

1. Project Completion Risk :

Completing a project in time and within the estimated cost itself is a major
achievement. A project that is delayed will result in time over run which will
consequently result in cost overrun. If the promoters are not able to fund the cost-
over-run, project gets delayed. There can be technology failures or consultants
non availability may cause delay.

2. Resource Risk :

Manpower, raw materials, power, fuel, P & M etc. form resources. Delay in
receipt of raw materials or P & M etc. will cause delay in project completion.

Prepared by – Vinayanand Rele


Page 356 of 380 24/11/2008
Project Management

3. Price Risk :

Price fluctuations of both inputs and outputs will affect the project.

4. Competitor’s Risk :

The competitors may try to disturb the project by increasing or decreasing prices
which will force us to review the project for calculation of ROI.

5. Technology Risk :

The collaborator may supply us old technology or during the project time, new
technology may have been developed, which may effect the profitability. We
have to have a good consultant to guard against old technology supply.

6. Political Risk :

Suddenly the govt. may impose some new tax or withdraw some facility earlier
extended , such as lesser excise or octroi or no sales tax for 2 yrs or cheaper
power etc. Also import duly changes may affect project.

7. Interest Rate Risk :

Fluctuations in interest rate year after year may bring in adverse effect. Say
project is funded by way of long -term borrowings at a particular rate of interest
and if the interest rate falis down subsequently, there will be bad effect on
project. If the interest rate increases in future, the working capital will be available
at higher cost & will lower the profit.

8. Exchange Rate Risk :

There are currency fluctuations & international currency rate may vary, resulting
into more project cost.

9. Open Policy Risk or Risk from Global Competitors :

The new risk emerged with the 'open door' policy of GOI, has thrown out number
of industries as they cannot sustain the price-war. The project envisaged today
may face such risks in coming days and the project will suffer

10 Risk Due to Trading Activities :

Number of entrepreneurs are finding it easy to "assemble" products in producing


in India rather than producing components & making the products ( e.g ..
computers, DVDS etc. ) such risks in The project runs future times.

Prepared by – Vinayanand Rele


Page 357 of 380 24/11/2008
Project Management

11 Risk of Elimination of Product

Due to fast changing technology & varying customer demand, some of the
products ( now envisaged for project) may not be required., resulting into
termination of the project. (example- TV screen for computer monitor, or plasma
monitor in place of tube - technology)

Techniques of Risk Analysis

Though there are many mathematical techniques available for risk analysis, the
following are the simple tools that come handy for analyzing small & medium sized
projects:

(1) Break - Even analysis


(2) Sensitivity analysis
(3) Decision - Tree analysis
(4) Monte - carlo technique etc.

(1) Break-Even Technique

The costs are divided into fixed & variable costs as below :

Fixed Assets Variable Assets

Rent Raw Materials


Insurance Consumables
Depriciation Power, Fuel
Administrative Exp Tools Etc.

Fixed Cost
BEP ( Qty ) = ----------------------------------------------------
Selling Price Unit – Variable Cost / Unit

Contribution = Sales realization – Variable Cost

Also, can be represented as

Fixed Cost x Selling Price / Unit


BEP (Rs) = ----------------------------------------------------
Contribution / Unit

Prepared by – Vinayanand Rele


Page 358 of 380 24/11/2008
Project Management

(2) Sensitivity Analysis.

It is a technique that measures the change in the profitability of a project caused by


changes in the factors that affect the cash inflows of a project. If a small change in one
factor leads to a major change in the profitability of tile proposed investment, the project
is considered more sensitive to that factor, in other words, the project is more risky.
Other things being equal, a project that is less sensitive is preferable to projects that are
more sensitive.

Example

Hind bulbs proposes to start a new venture for the manufacture of fluorescent bulbs.
The estimates of the new venture are as under :-

Output of bulbs per annum : 3 L Numbers


Expected Sales revenue / annum : Rs. 1.50 cr
Fixed Cost : Rs. 35 L
Variable Costs : Rs. 65 L

i) If the selling price comes down to Rs 40 per unit, find out its effect on BEP.
ii) If the fixed costs increase to Rs 40 L find out its effect on BEP.
iii) If the variable costs increase by 1 %, find out its effect on BEP.

Solution

Fixed cost Rs : 35,00,000


Sales Revenue Rs : 1,50,00,000
Selling price per unit = ( 150L / 3 L ) = Rs 50
Variable cost per unit = ( Rs. 66 L / 3 L ) Rs 22

Fixed Cost
BEP = ----------------------------------------------
Selling Price / Unit – V.C Per Unit

35,00,000 35,00,000
= -------------- = ------------- = 1.25,000 Units.
50 – 22 28

Selling Price / Unit comes down to Rs 40 L

35,00,000 35,00,000
BEP = -------------- = ------------- = 1.94,999 Units.
40 – 22 18

Prepared by – Vinayanand Rele


Page 359 of 380 24/11/2008
Project Management

b) Fixed Cost increase to Rs 40 L

40,00,000 40,00,000
BEP = -------------- = ------------- = 1.42,875 Units.
50 – 22 28

c) Variable Cost increase by 10%

Revised V.C. = / unit = ( 1.1 x 22 ) = Rs 24.20

35,00,000 40,00,000
BEP = -------------- = ------------- = 1.35,569 Units.
50 – 24.20 25.80

Results

1. Reduction in selling price by 20 % , increases BEP by 56 %


2. Increase in F.C. by 14.21 % , Increases BEP by 9 %
3. Increase in V.C. by 10 % , Increases BEP by 9 %. Hence BEP is more sensitive
to selling price.

Prepared by – Vinayanand Rele


Page 360 of 380 24/11/2008
Project Management

Project Cost Estimation


Cost of The Project

Correct estimation of the capital cost of a project is the foundation over which the edifice
of financial appraisal stands. Resources for the project are tied up after the project cost
is estimated. Any under-estimation will put the project in problem.

Components of Capital Cost of A Project.

Following are the components that constitute the capital cost of any project :

(i) Land & land development


(ii) Buildings
(iii) Plant and machinery
(iv) Electricals
(v) Transport and erection charges
(vi) Know - how & consultancy fees
(vii) Miscellaneous assets.
(viii) Preliminary & pre- operative expenses
(ix) Provision of contingencies
(x) Margin money for working capital

(i) Land & Land Development

Before deciding upon the extent of land required for the project, re-assure that
investment on land is absolutely essential, after considering the aspect of lease
or hire etc. The proposed land has to be leveled in order to construct. The land
may uneven - high low or bushy or hilly etc. Approach roads are also to be made
simultaneously. Detailed estimates of cost for these work is required.

(ii) Buildings

Provision for different type of buildings such as : main office (admn.), factory
sheds, stores, canteen, creche, dispensary, security, rest room, time office,
toilets, facilities like dg set / ac. / compressor rooms etc. A detailed estimate of
cost of each building with its drawings is required to take decision at appropriate
time, for differing, if required.

(iii) Plant and machinery

At DPR stage, cost of each of the items of plant & machinery is required. Also
inclusion of materials handling equipments, inspection & testing equipments etc.
should be there. While, arriving at the cost estimates customs only, octroi,
insurance charges in addition to Sales Tax etc. to be considered.

Prepared by – Vinayanand Rele


Page 361 of 380 24/11/2008
Project Management

(iv) Electricals

These must include fees to electricity board, transformer, panel, cabling, voltage
stabilizers, uninterrupted power supply etc.

(v) Transport and erection charges

Transport charges fill the P & M reach the factory site, including loading & un-
loading charges are to be accounted for.

(vi) Know - how & consultancy fees

Know how fees to technical consultant or the consulting firm and the fees for
transported technology to the firm inclusive of training is to be provided. While
working out fees, the extent of participation of consultant is also to be specified.

(vii) Miscellaneous assets.

These include provision for office equipments, furniture, fire- fighting equipments,
water coolers, air conditioners etc. Also included in this are deposits with
electricity board, advance for lease etc.

(viii) Preliminary & pre- operative expenses

These expenses include investigation fees, service charges of banks/ financing


institutions etc. interest amount payable to the term loan landing institution during
the period of implementation of the project is to be worked out ( Included project
cost)

(ix) Provision of contingencies

While actually implementing the project, there may be some deviations like
changes in the price for plant & machinery, changes in interest rate or parity rate
of currency etc. Some un-planned equipments & items may be required. A
provision of about 5 to 15% is therefore provided in the project cost estimates.

(x) Margin money for working capital

Normally bank & financial institutions extend loan to the extent of 75 % to 80 %


on capital cost or for working capital. The balance amount is to be contributed by
the promoter. This provision is essential.

Prepared by – Vinayanand Rele


Page 362 of 380 24/11/2008
Project Management

MONITORING AND CONTROL OF PROJECT

Definition

Monitoring is collecting, recording, and reporting information concerning any and all
aspects of project performance that, the project manager or others in the organisation
wish to know. It is important to remember that monitoring, as an activity, is distinct from
"Controlling as well as from evaluation.

Control is the act of reducing the difference between 'plan' & 'reality'. It involves the
regular comparison of performance against targets, a search for the causes of deviation
and a commitment to check adverse variances .. Project control

Project Control

No sooner is the project launched, control becomes the dominant concern of the project
manager, indeed, once the launch phase is over, planning & control become closely
intertwined in an integrated managerial process.

Project control involves a regular comparison of performance against targets, a search


for the causes of deviation, and a commitment to check adverse variances. It serves two
major functions:

(a) It ensures regular monitoring of performance &


(b) Motivates project personnel to strive for achieving project objectives.

Prepared by – Vinayanand Rele


Page 363 of 380 24/11/2008
Project Management

A few things that can cause a project to require the control of performance cost or time
are as follows: -

A) Performance

i) Un-expected technical problems.


ii) Insufficient resources when needed.
iii) Quality & Reliability problems.
iv) Client requires changes.
v) Inter-functional complications.

B) Cost

i) Tech. Difficulties require more resources.


ii) Scope of work increases.
iii) Initial bids/ estimates were low.
iv) Budgeting was inadequate.
v) Input price changes.
vi) Corrective control was not exercised in time .

C) Time:

i) Long time to solve technical difficulties


ii) Initial time estimates too optimistic
iii) Task sequencing was incorrect.
iv) Inputs delay
v) Preceding talks delayed.
vi) Customer requirements changed.
Vii) Govt. Regulations were altered.

Prepared by – Vinayanand Rele


Page 364 of 380 24/11/2008
Project Management

PROJECT FINANCING
Introduction

Project financing may be defined as the raising of funds required to finance an


economically separable capital investment proposal in which the lenders mainly rely on
the estimated cash flow from the project to service their loans. Project financing differs
from conventional financing in the following aspects. :

A) In conventional financing, cash flow from different assets and business are co-
mingled. A creditor makes an assessment of repayment of his loan by looking at
all the cash flows and resources of the borrower. In project financing, cash flows
from the project related assets alone are considered for assessing the re-paying
capacity.
b) In conventional financing, end use of the borrowed funds is not strictly monitored
by the lenders. In project financing, the creditors ensure proper utilization of
funds & creation of assets. As envisaged in the project proposal. Funds are also
released in stages as & when assets are created.
C) In conventional financing, the creditors are not interested in monitoring the
performance of the enterprise and they are interested only in their money getting
repaid in one way or the other. Project financiers are keen to watch the
performance of the enterprise and suggest / take remedial measures as & when
required to ensure that the project repays the debt out of its cash generations.
They, at times, appoint their nominee in the board of directors, of their clients, in
order to monitor the performance.

Sources of Finance

After the project cost is ascertained, the sources of finances available for meeting the
project cost are to be analysed and a proper combination of different sources shall be
chosen that is most suitable for the project. The various sources of finance can be
broadly divided into 2 categories viz.

1) Equity capital &


2) Debt / Borrowed capital

The combination of the above two should be judiciously chosen. Debt capital enforces
upon the organisation an obligation for repayment of principal & payment of interest.
Equity capital does not impose any such obligation. Equity capital serves as cushion at
times when the business conditions are unfavourable leading to operational difficulties.
Interest paid on the debt (term loan, debenture etc.) is a deductible item of expenditure
from the profit earned by the organisation for the purpose of arriving at the tax payable
by the organisation on its earnings).

Prepared by – Vinayanand Rele


Page 365 of 380 24/11/2008
Project Management

The contributors of equity capital anticipate a return on their investment by way of


dividend.

The following are the main sources of project finance.

(i) Ordinary shares


(ii) Preference shares
(iii) Debentures
(iv) Bonds
(v) Term loans
(vi) Deferred credits
(vii) Capital investment subsidy
(viii) lease financing
(ix) unsecured loans
(x) lnternal accruals
(xi) Bridge loans
(xii) Public deposits

(i) Ordinary shares

Ordinary shares ( or common shares or equity shares) are the source of


permanent capital. The holders of ordinary shares are the legal owners of the
company. For the capital contributed by the shareholders towards purchase of
ordinary shares, they are entitled for dividends. Equity shareholders being the
owners of the company, bear the risk of ownership. They are entitled to dividends
on their capital invested, only after interest obligations and dividends to
preference shareholders are paid. Since equity shareholders bear such risks
associated with ownership of the company, they anticipate handsome return on
their investment, by way of attractive dividends and price appreciation of their
shares.

(ii) Preference shares

Preference shares bear a predetermined rate of dividend. They have priority of


claim over equity shares in the matter of payment of dividend. They also have
priority over equity shares on the assets of the company in the event of
liquidation of the company.

Though dividend on preference shares is payable out of profits. If the company


incurs loss in a particular year, the dividend not paid during that year. is to be
carried forward and is to be paid in subsequent year/years when the company
earns profit.

Dividends on non-cumulative preference shares do not add up for future


payment. When the company earns profit, it has to pay arrears of dividends to
preference shareholders before declaring any dividend on equity share. The

Prepared by – Vinayanand Rele


Page 366 of 380 24/11/2008
Project Management

dividend rate is fixed in the case of preference shares and the dividends pain on
preference shares are not tax deductible.

Preferences shares are of two types, viz, redeemable preference shares and
irredeemable preference shares. While redeemable preference shares are
redeemed after the stipulated period., Irredeemable preference shares do not
have any maturity date.

(iii) Debentures

Debentures are instruments for raising long term debt capital. The debenture
holders are the creditors of the company.

The company that has borrowed money by way of debentures has the obligation
to repay interest and debt on specified dates.

(iv) Bonds

A bond is more or less similar to a debenture and these tow terms of frequently
used interchangeably. In India, there is a tendency to reserve the term 'bond' to
public debt securities issued by the Government and public sector undertakings.

(v) Term loans

The term 'term loan' denotes long term loans offered for project financing. The
period of principal repayment of such long term loans vary from 5 to 10 years
depending upon the nature of the project (It will be more for infrastructure
projects, say in order of 20 to 25 years) Initial moratorium (Holiday period) for the
repayment of principal of one of two years is normally provided. The length of the
repayment period depends upon the period of implementation of the project.

(vi) Deferred Credits

Some machinery suppliers provide the facility of deferred credit, provided the
credit-taker offers a Bank guarantee. A project promoter when wants to avail the
deferred credit facilities offered by a machinery supplier should approach a bank
for offering guarantee for the repayment of deferred installments to the machinery
supplier. Banks examine the viability of the project proposal before giving their
guarantee. Normally, banks obtain mortgage of additional securities from the
credit-takers to ensure that the bank does not stand to loose in the event of the
guarantee being invoked by the machinery supplier due to non repayment of
deferred installments.

Prepared by – Vinayanand Rele


Page 367 of 380 24/11/2008
Project Management

(vii) Capital investment subsidy

Government provides subsidy for the setting up of industries. The subsidy offered
is two types. Viz.

a) Area subsidy
b) Product subsidy

a) Area subsidy :

Area subsidy is available for projects (both new and expansion projects)
set up in notified backward areas. Government notifies backward areas
from time to time based on the industrial activity prevailing in different
parts of the country. The objective of notifying certain areas as
backward/most backward is to promote industrial development in those
area.

b) Product subsidy :

Project subsidy is available for projects that manufacture specified


products. These products that are eligible for subsidy are identified by the
government by keeping in view the potential for the economic
development of the country in such sectors of industries and notified by
the Government. Projects that are set up for the manufacture of products
that find place in the list of eligible products. can avail product subsidy,
irrespective of the location of the project i.e. the project can avail su bsidy
irrespective of whether the unit is set up in a notified backward area or not.
The quantum of product subsidy is also fixed at a certain percentage on
the investment on fixed assets ( in the range of 10 % to 20 % for different
types of notified products)

(viii) lease financing

lease is a contract whereby the lessor (owner of an asset) give to the lessee ( the
user of the asset) the right to use the asset, usually for an agreed period of time,
in return for the consideration of periodical payments by the lessee to the lessor
called, lease rentals.

Lease, as a source of project finance is mainly suitable for expansion projects


This is because of the reason that repayment of lease rental starts immediately.

(ix) unsecured loans

If there is some shortfall in the means of finance, the promoters/ directors can
mobilize funds form their friends, relatives and well wishers in the form of loan to
make good the shortfall. Such loans are always unsecured i.e. the lenders can
not have any charge over the assets of the company. Unsecured loans can
Prepared by – Vinayanand Rele
Page 368 of 380 24/11/2008
Project Management

mobilized only based on the rapport that the project promoters have with their
friends and relatives.

Banks and financial institutions view unsecured loans with an eye of caution.
They normally stipulate the following conditions if unsecured loan is to form part
of the means - of finance.

- The promoters shall not repay the unsecured loan till the term loan
persists.
- Interest, if any payable on unsecured loan shall be paid only after meeting
the term loan repayment commitments (both repayment of principal and
interest)
- The rate of interest payable on unsecured loan shall not be higher that the
rate of interest applicable for term loan.

Banks/ Financial institutions also stipulate the maximum limit for unsecured loan.
Normally unsecured loan component is expected not to exceed 50 % of the
equity capital.

(x) lnternal accruals

Internal accruals from part of the means of finance in respect of expansion


projects. An existing company that goes for an expansion (or diversification or
modernization) project may opt to finance a portion of the capital investment out
of internal cash accruals. Depreciation which is not a cash expenditure and
profits retained after payment of dividends are the main sources of internally
generated funds. Apart from the internal funds that have already been generated.
The likely internal generation during the course of project implementation can
also be used as a source for funding expansion projects.

(xi) Bridge loans

This is a temporary loan meant for tieing up the capital cost of a project. Bridge
loans are sanctioned by banks and financial institutions in order to help speedy
implementation of the project. In the absence of bridge loan, the project
implementation may get delayed for want of sufficient funds. The necessity for
bridge finance arises in situations where finance from a particular source is
getting delayed. However, the availability of finance from that source is certain.

In such situations, if the project is funded with bridge-loan to the extent needed,
the implementation of the project will go on stream without getting held up for
want of funds. The following example will explain the concept well.

The project cost of a new project is estimated at Rs. 100.00 lakhs. The promoters
are able to bring in a capital of Rs. 30.0 Lakhs. The project is eligible for an
investment subsidy of Rs. 10.00 lakhs. The Financial institution that has

Prepared by – Vinayanand Rele


Page 369 of 380 24/11/2008
Project Management

appraised the project is ready to sanction a term loan of Rs. 60.00 lakhs. Thus,
the means of finance for the project cost gets tied up as under:

Promoter's contribution Rs. 30.00 Lakhs


Investment subsidy Rs. 10.001akhs
Term loan Rs. 60.001akhs
----------------------
Total 100.00 Lakhs
----------------------
(xii) Public deposits

Public deposits are mobilized from the public in general and also from the share
holders. Public deposits can be taken for a minimum period of six months and a
maximum period of 36 months. Section 58 A of the Companies act regulates
public deposits. The interest rate on Public deposits depends on the period of
deposit. Government issues directions on the interest rate payable on public
deposits from time to time. Raising of public deposit is a more simple and
convenient form of mobilizing money as compared to raising loans from
organized financial institutions.

Prepared by – Vinayanand Rele


Page 370 of 380 24/11/2008
Project Management

Question :

Discuss Human Aspects of Project Management in relation to Authority,


Personnel Orientation, Motivation and Team Building.

Although the use of proper planning and budgetary control techniques help in
successful project management, their use and effectiveness depends on the people
who are involved and are responsible for various project activities at various levels. It is
therefore very important to understand human nature and to achieve satisfactory human
relations in project setting. Project manager has to handle problems and challenges
relating to following issues.

1. Authority :

Project manager very often does not have a direct authority over the project team. He
has to co-ordinates efforts of various functional groups, experts, consultants external
agencies etc. Team leadership and influencing professionals assumes importance than
exercising authority. Project manager's authority therefore emanates from his ability to
develop rapport with the team members, skillful resolution of conflicts, skill of
communication and persuasion and ability to act as a buffer between technical
engineering, financial and commercial personnel.

2. Personnel Orientation :

Overemphasis on planning and control techniques that are mathematics and accounts
oriented tends to adopt a structured and mechanical approach to project management.
However, project being subject to many uncertainties, a more creative and adaptive
approach is necessary to solve un-programmed and un-structured problems as the
project progresses. Such orientation is required for all the project team.

3. Motivation :

Project being a short team endeavour carried out by lossely bound professional team, it
is very difficult to keep it motivated throughout the project term. The team members
sometimes tend to get confused due to split authority and dual subordination structure
of the organization. To keep a high level of motivation , the project manager has to
ensure that the project goals are clearly defined and are visible to all involved. He has to
encourage participative management with proper delegation of authority and
responsibility that creates a sense of belonging to the project and to make individuals
job sufficiently challenging to have greater personal commitment.

4. Team Building :

Most of the project activities are inter-related and interdependent and most 'of the
problems need inter-disciplinary solutions.

Prepared by – Vinayanand Rele


Page 371 of 380 24/11/2008
Project Management

Question

When do you judge a project to be a failure? What are the possible causes of
project failures?

A project is considered to be a failure if it fails to complete in scheduled time or it


exceeds the budgeted cost or is not able to fully accomplish the project objectives.
While time overruns and cost overruns are the common causes of project failure,
inability to meet the key performance indicators is also observed occasionally. Although
the project is may not be a total failure as it is finally implemented and starts functioning,
it tends to be uneconomical to run, does not create sufficient surplus for investing into
future growth of the organization and eventually becomes a drain on organizations'
funds.

Common causes that result in time / cost overruns or failure to meet specifications are:

Inadequate project formulation : Superficial field investigations, ill-defined project


scope, wrong assessment of input requirements, inaccurate methods for estimation in of
costs & benefits, deliberate underestimation of costs and overestimation of benefits etc.

Unsuitable Project Organization : Incompetent project leader, inadequate authority to


the project leader, confusing or improperly understood roles of project team members.

Improper Implementation Planning : Insufficient breakdown of project activities,


undue reliance on intuition and judgment rather than available information and data,
improper definition of interlinkages between activities.

Failure to take advance action : As project is subjected to a lot of risks during its
course of implementation, it is necessary to be proactive at the signs of impending
problems rather than react only when the problems are fully blown up.

Non-ability of funds in time : Proper cash flow management is the key to success of
the project. Non-availability of funds in time delays the project implementation as well as
increases the project costs.

Injudicious equipment tendering, procurement and contracts management : It is


generally observed that equipment and materials form 65 - 70% of the project cost and
procurement of the same covers almost 70% of the project implementation time.
Similarly-, Proper selection of contractors ensures timely completion within budgeted
costs.

Ineffective project monitoring : As the projects are implemented under a dynamic,


ever changing environment, effective monitoring and timely modifications in
implementation strategy are required for the success of the project.

Prepared by – Vinayanand Rele


Page 372 of 380 24/11/2008
Project Management

Question

What is a Gantt Chart ?

One of the oldest methods of presenting time schedule information is the Gantt chart,
developed around 1917 by Henery Gantt. A Gantt chart is one of the most convenient,
most commonly used, easy-to-grasp presentations of project activities.

It is a two-dimensional graphical representation of the activities that make up the


project. The vertical axis lists the project activities, one per tline, while the horizontal
axis indicates time. Once the scheduled start and completion dates for every activity
have been determined, the Gantt chart can be constructed. Figure shows a typical Gantt
chart as planned and shows the same chart progressed.

An added value of the Gantt chart is that the activities are time-scaled, which provides a
perspective not possible with other project charts such as network diagrams. A time
scaled network diagram can be developed which allows progress to be indicated similar
to a Gantt chart. Networks are described in the next section. 'Critical path analysis'.

The Gantt chart is a particularly effective and easy-to-read method of indicating the
actual current status of activities compared to the planned progress. As a result, the
Gantt chart can be helpful in expediting, sequencing and reallocating resources to
activities, as well as keeping track of progress. In addition, the charts can contain a
number of specialized symbols to designate or highlight items of special concern to the
situation being charted.

Advantages and disadvantages of the Gantt Chart

The Gantt has the following general advantages over other planning tools such as
network diagrams:

• Although they contain a great deal of information, they are easily understood.
• While they require frequent updating (as does any scheduling / control tool), they
• are easy to maintain.
• They provide a clear, simple picture of the state of the project.
• They are easy to construct and are not based on any mathematical model.
• The Gantt maybe constructed without a critical path analysis (CPA) being
needed.
• They can, however, also graphically represent the output of a CPA.

A close relationship exists between Gantt charts and CPA networks (PERT or CPM).
Generally Gantt charts are derived from CPA networks by plotting the activity from its
calculated earliest time for the length of its duration. If an activity has float, then this can
be shown as differently patterned bar at the back of the plotted activity bar.
Prepared by – Vinayanand Rele
Page 373 of 380 24/11/2008
Project Management

The major disadvantage of the Gantt chart is that the relationships or dependencies
between activities are not a explicit as in CPA networks. Unless connecting lines are
drawn on the Gantt chart, it is not possible to determine the links between activities.
Modern computer packages, however, can now show these connecting lines if required.
The Gantt chart has survived for more than 80 years. Considering that in 1917 Henry
Gantt could not have visualized the proliferation of sophisticated project management
tools and techniques, the Gantt chart continues to prove its usefulness beyond any
doubt.

Prepared by – Vinayanand Rele


Page 374 of 380 24/11/2008
Project Management

Table : Area Under the Standard Normal Curve From 0 to z


Z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09

.0 0.0000 0.0040 0.0080 0.1200 0.0160 0.0199 0.0239 0.0279 0.3190 0.0359
.1 0.0398 0.0438 0.0478 0.0517 0.0557 0.0596 0.0636 0.0675 0.0714 0.0753
.2 0.0793 0.0832 0.0871 0.0910 0.0948 0.0987 0.1026 0.1064 0.1103 0.1141
.3 0.1179 0.1217 0.1255 0.1293 0.1331 0.1368 0.1406 0.1443 0.1480 0.1517
.4 0.1554 0.1591 0.1628 0.1664 0.1700 0.7360 0.1772 0.1808 0.1844 0.1879
.5 0.1915 0.1950 0.1985 0.2019 0.2054 0.2088 0.2123 0.2157 0.2190 0.2224
.6 0.2257 0.2291 0.2324 0.2357 0.2389 0.2422 0.2454 0.2486 0.2518 0.2549
.7 0.2580 0.2612 0.2642 0.2673 0.2705 0.2734 0.2764 0.2794 0.2823 0.2852
.8 0.2881 0.2910 0.2939 0.2967 0.2995 0.3023 0.3051 0.3078 0.3106 0.3133
.9 0.3159 0.3186 0.3212 0.3238 0.3264 0.3289 0.3315 0.3340 0.3365 0.3389
1.0 0.3413 0.3438 0.3461 0.3485 0.3508 0.3531 0.3554 0.3577 0.3599 0.3621
1.1 0.3643 0.3665 0.3686 0.3708 0.3729 0.3749 0.3770 0.3790 0.3810 0.3830
1.2 0.3849 0.3869 0.3888 0.3907 0.3925 0.3944 0.3962 0.3980 0.3997 0.4015
1.3 0.4032 0.4049 0.4066 0.4082 0.4099 0.4115 0.4131 0.4147 0.4162 0.4177
1.4 0.4192 0.4207 0.4222 0.4236 0.4251 0.4265 0.4279 0.4292 0.4306 0.4319
1.5 0.4332 0.4345 0.4357 0.4370 0.4382 0.4394 0.4406 0.4418 0.4429 0.4441
1.6 0.4452 0.4463 0.4474 0.4484 0.4495 0.4505 0.4515 0.4525 0.4535 0.4545
1.7 0.4554 0.4564 0.4573 0.4582 0.4591 0.4599 0.4608 0.4616 0.4625 0.4633
1.8 0.4641 0.4649 0.4656 0.4664 0.4671 0.4678 0.4686 0.4693 0.4699 0.4706
1.9 0.4713 0.4719 0.4726 0.4732 0.4738 0.4744 0.4750 0.4756 0.4761 0.4767
2.0 0.4772 0.4778 0.4783 0.4788 0.4793 0.4798 0.4803 0.4808 0.4812 0.4817
2.1 0.4821 0.4826 0.4830 0.4838 0.4838 0.4842 0.4846 0.4850 0.4854 0.4857
2.2 0.4861 0.4864 0.4868 0.4871 0.4875 0.4878 0.4881 0.4884 0.4887 0.4890
2.3 0.4893 0.4896 0.4898 0.4901 0.4904 0.4906 0.4909 0.4911 0.4913 0.4916
2.4 0.4918 0.4920 0.4922 0.4925 0.4927 0.4931 0.4931 0.4932 0.4934 0.4936
2.5 0.4938 0.4940 0.4941 0.4943 0.4945 0.4946 0.4948 0.4949 0.4951 0.4952
2.6 0.4953 0.4955 0.5956 0.4958 0.4959 0.4960 0.4961 0.4962 0.4963 0.4964
2.7 0.4965 0.4966 0.4967 0.4968 0.4969 0.4970 0.4971 0.4972 0.4973 0.4974
2.8 0.4974 0.4975 0.4976 0.4977 0.4977 0.4978 0.4979 0.4979 0.4980 0.4981
2.9 0.4981 0.4982 0.4982 0.4983 0.4984 0.4984 0.4985 0.4985 0.4986 0.4986
3.0 0.49865 0.4987 0.4987 0.4988 0.4988 0.4989 0.4989 0.4989 0.4990 0.4990
4.0 0.4999684

Illustration for Z = 1.96, shaded area is 0.4750 out of total area of 1.

Prepared by – Vinayanand Rele


Page 375 of 380 24/11/2008
Project Management

Tables

Present Value Factor (PVF) Table rate of interest r %


Periods
1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13%
(n)
0 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000
1 0.990 0.980 0.971 0.962 0.952 0.943 0.935 0.926 0.917 0.909 0.901 0.893 0.885
2 0.980 0.961 0.943 0.925 0.907 0.890 0.873 0.857 0.842 0.826 0.812 0.797 0.783
3 0.971 0.942 0.915 0.889 0.864 0.840 0.816 0.794 0.772 0.751 0.731 0.712 0.693
4 0.961 0.924 0.889 0.855 0.823 0.792 0.763 0.735 0.708 0.683 0.659 0.636 0.613
5 0.951 0.906 0.863 0.822 0.784 0.747 0.713 0.681 0.650 0.621 0.593 0.567 0.543
6 0.942 0.888 0.838 0.790 0.746 0.705 0.666 0.630 0.596 0.564 0.535 0.507 0.480
7 0.933 0.871 0.813 0.760 0.711 0.665 0.623 0.583 0.547 0.513 0.482 0.452 0.425
8 0.923 0.853 0.789 0.731 0.677 0.627 0.582 0.540 0.502 0.467 0.434 0.404 0.376
9 0.917 0.837 0.766 0.703 0.645 0.592 0.544 0.500 0.460 0.424 0.391 0.361 0.333
10 0.905 0.820 0.744 0.676 0.614 0.558 0.508 0.463 0.422 0.386 0.352 0.322 0.295
11 0.895 0.804 0.722 0.650 0.585 0.527 0.475 0.429 0.388 0.350 0.317 0.287 0.261
12 0.887 0.788 0.701 0.625 0.557 0.497 0.444 0.397 0.356 0.319 0.286 0.257 0.231
13 0.879 0.773 0.681 0.601 0.530 0.469 0.415 0.368 0.326 0.290 0.258 0.229 0.204
14 0.870 0.758 0.661 0.577 0.505 0.442 0.388 0.340 0.299 0.263 0.232 0.205 0.181
15 0.861 0.743 0.642 0.555 0.481 0.417 0.362 0.315 0.275 0.239 0.209 0.183 0.160
16 0.853 0.728 0.623 0.534 0.458 0.394 0.339 0.292 0.252 0.218 0.188 0.163 0.141
17 0.844 0.714 0.605 0.513 0.436 0.371 0.317 0.270 0.231 0.198 0.170 0.146 0.125
18 0.836 0.700 0.587 0.494 0.416 0.350 0.296 0.250 0.212 0.180 0.153 0.130 0.111
19 0.828 0.686 0.570 0.475 0.396 0.331 0.276 0.232 0.494 0.164 0.138 0.116 0.098
20 0.820 0.673 0.554 0.456 0.377 0.312 0.258 0.215 0.178 0.149 0.124 0.104 0.087
25 0.780 0.610 0.478 0.375 0.295 0.233 0.184 0.146 0.116 0.092 0.074 0.059 0.047
30 0.742 0,552 0.412 0.308 0.231 0.174 0.131 0.099 0.075 0.057 0.044 0.033 0.026

Prepared by – Vinayanand Rele


Page 376 of 380 24/11/2008
Project Management

Tables

Present Value Factor (PVF) Table rate of interest r %


Periods
14% 15% 16% 17% 18% 19% 20% 24% 28% 32% 36% 40%
(n)
0 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000
1 0.877 0.870 0.862 0.855 0.847 0.840 0.833 0.806 0.781 0.758 0.735 0.714
2 0.769 0.756 0.743 0.731 0.718 0.706 0.694 0.650 0.610 0.574 0.541 0.510
3 0.675 0.658 0.641 0.624 0.609 0.593 0.579 0.524 0.477 0.435 0.398 0.364
4 0.592 0.572 0.552 0.534 0.516 0.499 0.482 0.423 0.373 0.329 0.292 0.260
5 0.519 0.497 0.476 0.456 0.437 0.419 0.402 0.341 0.291 0.250 0.215 0.186
6 0.456 0.432 0.410 0.390 0.370 0.352 0.335 0.275 0.277 0.189 0.158 0.133
7 0.400 0.376 0.354 0.333 0.314 0.296 0.279 0.222 0.178 0.143 0.116 0.095
8 0.351 0.324 0.305 0.285 0.266 0.249 0.233 0.179 0.139 0.108 0.085 0.068
9 0.308 0.284 0.263 0.243 0.226 0.209 0.194 0.144 0.108 0.082 0.063 0.048
10 0.270 0.247 0.227 0.206 0.191 0.176 0.162 0 116 0.085 0.062 0.046 0.035
11 0.237 0.215 0.195 0.178 0.162 0.148 0.135 0.094 0.066 0.047 0.034 0.025
12 0.208 0.187 0.168 0.152 0.137 0.124 0.112 0.076 0.052 0.036 0.025 0.018
13 0.182 0.163 0.145 0.130 0.116 0.104 0.093 0.061 0.040 0.027 0.018 0.013
14 0.160 0.141 0.125 0.111 0.099 0.088 0.078 0.049 0.032 0.021 0.014 0.009
15 0.140 0.123 0.108 0.095 0.084 0.074 0.065 0.040 0.025 0.016 0.010 0.006
16 0.123 0.107 0.093 0.081 0.071 0.062 0.054 0.032 0.019 0.012 0.007 0.005
17 0.108 0.093 0.080 0.069 0.060 0.052 0.045 0.026 0.015 0.009 0.005 0.003
18 0.095 0.081 0.069 0.059 0.051 0.044 0.038 0.021 0.012 0.007 0.004 0.002
19 0.083 0.070 0.060 0.051 0.043 0.037 0.031 0.017 0.009 0.005 0.003 0.002
20 0.073 0.061 0.051 0.043 0.037 0.031 0.026 0.014 0.007 0.004 0.002 0.001
25 0.038 0.030 0.024 0.020 0.016 0.013 0.010 0.005 0.002 0.001 0.000 0.000
30 0.020 0.015 0.012 0.009 0.007 0.005 0.004 0.002 0.001 0.000 0.000 0.000

Prepared by – Vinayanand Rele


Page 377 of 380 24/11/2008
Project Management

Tables

Present Value Factor for an Annuity Factor for Annuity ( PVFA ) Table
( Cumulative )

Rate of Interest r %

Periods
1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13%
(n)

0 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000
1 0.990 0.980 0.971 0.962 0.952 0.943 0.935 0.926 0,917 0.909 0.901 0.893 0.885
2 1.970 1.942 1.913 1.886 1.859 1.833 1.181 1.783 1.759 1.735 1.713 1.690 1.668
3 2.941 2.884 2.829 2.775 2.723 2.673 2.624 2.577 2.531 2.487 2.444 2.402 2.361
4 3.902 3.808 3.717 3.630 3.546 3.465 3.387 3.312 3.240 3.170 3.102 3.037 2.974
5 4.853 4.713 4.580 4.452 4.329 4.212 4.100 3.993 3.890 3.791 3.696 3.605 3.517
6 5.795 5.601 5.417 5.242 5.076 4.917 4.767 4.623 4.486 4.355 4.231 4.111 3.998
7 6.728 6.472 6.230 6.002 5.786 5.582 5.389 5.206 5.033 4.868 4.712 4.564 4.423
8 7.652 7.325 7.020 6.733 6.463 6.210 5.971 5.747 5.535 5.335 5.146 4.968 4.799
9 8.566 8.162 7.786 7.435 7.108 6.802 6.515 6.247 5.995 5.759 5.537 5.328 5.132
10 9.471 8.983 9.530 8.111 7.722 7.360 7.024 6.710 5.418 6.145 5.889 5.650 5.426
11 10.368 9.787 9.253 8.760 8.306 7.887 7.499 7.139 5.805 6.495 6.207 5.938 5.687
12 11.255 10.575 9.954 9.385 8.863 8.384 7.943 7.536 7.161 6.814 6.492 6.194 5.918
13 12.134 11.348 10.635 9.986 9.394 8.853 8.358 7.904 7.487 7.103 6.750 6.424 6.122
14 13.004 12.106 11.296 10.563 9.899 9.295 8.745 8.244 7.786 7.367 6.982 6.628 6.302
15 13.865 12.849 11.938 11.118 10.380 9.712 9.108 8.559 8.061 7.606 7.191 6.811 6.462
16 14.718 13.578 12.561 11.652 10.838 10.106 9.447 8.851 8.313 7.824 7.379 6.974 6.604
17 15.562 14.292 13.166 12.166 11.274 10.477 9.763 9.122 8.544 8.022 7.549 7.120 6.729
18 16.398 14.992 13.754 12.659 11.690 10.828 10.059 9.372 8.756 8.201 7.702 7.250 6.840
19 17.226 15.678 14.324 13.134 12.085 11.158 10.336 9.604 8.950 8.365 7.839 7.366 6.938
20 18.046 16.351 14.877 13.590 12.462 11.470 10.594 9.818 8.129 8.514 7.963 7.469 7.025
25 22.023 19.523 17.413 15.622 14.094 12.783 11.654 10.675 8.823 9.077 8.422 7.843 7.330
30 25.808 22.396 19.600 17.292 15.372 13.765 12.409 11.258 10.274 9.427 8.694 8.055 7.496

Prepared by – Vinayanand Rele


Page 378 of 380 24/11/2008
Project Management

Tables

Present Value Factor for an Annuity Factor for Annuity ( PVFA ) Table
( Cumulative )

Rate of Interest r %

Prepared by – Vinayanand Rele


Page 379 of 380 24/11/2008
Project Management

How to Study for Examination ?

Problems are asked on :

1. AOA & AON Methods.


2. Crashing ( 20 Marks )
3. PERT
4. Gannt Chart
5. Project Control
6. Decision Tree
7. Forecasting
8. Capital Budgeting ( 20 Marks + 10 – 20 Marks Theory )

Paper Pattern

Solve any 5 out of 8 ( 60 to 70 Marks ) problem & ( 40 to 30 Marks ) Theory

Tips :

First attempt problem about Capital Budgeting, Decision Tree, Gannt Chart etc.
Attempt Crashing at Last.

Prepared by – Vinayanand Rele


Page 380 of 380 24/11/2008

Das könnte Ihnen auch gefallen