Sie sind auf Seite 1von 4

CHECK LIST Date:

BOILER UNIT# 1

S No. Description Total tonnage completed Balance

1 Boiler 7421.212 4941.411 2479.801

2 Pressure parts 2401.105 2204.041 197.064

3 Welding joints

4 Pass-1 6174 6153 21

5 Pass-2 886 886 0

6 pass-3 6447 5771 676

common 627 0 0

7 Equilent joints

Pass-1 8731 8519 212

Pass-2 524 524 0

pass-3 5776 5188 588

Common 3549 0 0

8 SR Test 1612 385 1227

9 RT Test 1583 785 798

10 Fins balace in %

Pass-1 100% 50% 50%

Pass-2 100% Nill Nill

pass-3 100% 50% 50%

11 Coal bunker 607.126 488.124 119.002

12 APH 685.982 617.475 68.507

12 Refractory 750 58.165 691.835

13 Ducts 324.643 Nill Nill

14 Fuel feeding system 161.243 7.586 153.657

15 Rotary equipments 239.94 51.76 188.18


16 ESP 791.105 751.737 39.368
CHECK LIST Date:
BOILER UNIT #2

S No. Description Total tonnage completed Balance

1 Boiler 7421.212 4328.731 3092.481

2 Pressure parts 2401.105 1781.928 619.177

3 Welding joints

4 Pass-1 6174 714 5460

5 Pass-2 886 226 660

6 pass-3 6447 3042 3405

Common 627 213 414

7 Equilent joints

Pass-1 8731 1590 7141

Pass-2 524 138 386

pass-3 5776 2813 2963

Common 3549 1656 1893

8 SR Test 1612 0 0

9 RT Test 1583 0 0

10 Fins balace in %

Pass-1 100% 20% 80%

Pass-2 100% 30% 70%

pass-3 100% 20% 80%

11 Coal bunker 607.126 367.261 239.865

12 APH 685.982 618.103 67.879

12 Refractory 750 Nill Nill

13 Ducts 324.643 Nill Nill

14 Fuel feeding system 161.243 Nill Nill

15 Rotary equipments 239.94 51.76 188.18


16 ESP 791.105 674.011 117.094

Das könnte Ihnen auch gefallen