DESCRIPTION

START
29-May-09 22-Jul-10 23-Jun-09 11-Nov-09

FINISH
26-Jul-11 13-Dec-10 04-Aug-10 12-Jan-11

2012 2009 2010 2011 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

CONSTRUCTION - SITE WORKS


06 - Sitework 96 - Plant Drain Pump Station 07 - Yard Piping 08 - Site Electrical, Substation, Switchyard 59 - Headworks 60 - Clarifier 63 - Aeration Basin 64 - Membrane 78 - Solids Handling 85 - Anaerobic Digestors 82 - Aerobic Digestors 91 - Odor Control (Bio Filter) 83 - Gas Storage/Incineration Facilities 95 - Cogeneration 97 - Maintenance Facility

CONSTRUCTION - PROCESS FACILITIES - LIQUID


21-Apr-10 15-Apr-10 08-Jul-09 26-Feb-10 09-Jun-11 11-Feb-11 21-Oct-10 19-Aug-11

CONSTRUCTION - PROCESS FACILITIES - SOLIDS


09-Mar-10 20-Jun-09 13-Jan-10 29-Mar-11 14-Jul-10 30-Jul-10

CONSTRUCTION - BIOFILTER, MAINTENANCE AND GAS SYSTEMS


28-Jul-10 09-Sep-10 02-Aug-10 09-Sep-10 11-Jan-11 24-Nov-10 30-Nov-10 15-Apr-11

CONSTRUCTION - OPERATIONS FACILITY


10 - Treatment Ops Facility 98 - Water Resource Center
30-Sep-09 30-Sep-09 09-Nov-10 24-Sep-10

SYSTEMS START-UP AND TESTING


Systems Start-up and Testing
25-Sep-10 14-Oct-11

PLANT START-UP AND TESTING


Plant Start-up and Testing
06-Oct-10 02-Mar-12

Actual Work Remaining Work Critical Remaining Work Milestones Summary

748 - Spokane WRF SUMMARY CONSTRUCTION SCHEDULE Data Date: 29-May-2009