Beruflich Dokumente
Kultur Dokumente
BILL OF MATERIALS
Unit Cost Cost
Item Description Qty Unit
PhP PhP
1 CHB #4 3000 PC 5.5 16,500.00
2 CEMENT 630 BAG 174 109,620.00
3 WHITE SAND 40 M3 550 22,000.00
4 GRAVEL ¾ 45 M3 650 29,250.00
5 DEFORMED BAR 10mmø x 6M 800 PC 135 108,000.00
6 G.I TIE WIRES 3 RL 1000 3,000.00
7 PLYWOOD ¼"thk x 6M 25 PC 350 8,750.00
8 COCO LUMBER 2" x 3" x 8' 50 PC 105 5,250.00
9 C.W.N #3 10 KG 45 450.00
10 C.W.N #2 10 KG 40 400.00
303,220.00
LABOR
1 LABOR COST 274 LN.M 600 164,400.00
SUB-TOTAL 303,220.00
TOTAL COST 467,620.00
COST PER LN.M 1,706.64
187,048.00
Prepared by: 280,572.00
ROLANDO G. SARMIENTO
Jr. Supervisor-Eng'g/Mntce
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : MODIFICATION OF QA/LABORATORY PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1. MATERIALS PREPARATION, HAULING & STAGING 1 1 500
2.FABTN/INSTLN OF TEMP. WALL ALONG INSTRUMENTATION ROOM 4 1 500
3. DEMOLITION WORKS 3 1 500
4HAULING OF RECOVERED DEBRIS 1 1 500
5. INSTALLATION OF WOODEN FRAMING 1 1 500
6. MODIFICATION/ INSTALLATION OF DOOR JAMBS- 3 SETS 2 1 500
7. REPAIR OF AFFECTED CEILING , FLOORING & CHB WALLS 2 1 500
8. PAINTING WORKS ON AFFECTED PORTIONS 2 1 500
9. DISMANTLIN & RE-INSTALLATION OF ELECTRICALS 1 1 500
10. GHK / SITE CLEARING 1 1 500
11 500
12 500
13 500
14 500
TOTAL DURATION 18 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding machine 0 0 500
2. Plainer 1 4 150
3. Grinding Machine 1 5 100
4. Scaffolding 1 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : REHABILITATION OF BIKES PARKING ENCLOSURE PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1.LAY-OUT 0.5 1 500
2.FABTN/INSTLN OF B.I PIPE FOR STEEL POST & FRAMING 2.5 2 500
3.INSTALLATION OF PURLINS 1 2 500
4.INSTALLATION OF G.I CORRUGATED SHEETS 1.5 2 500
5.FABTN/INST INSTALLATION OF STEEL RAILINGS FOR PARKING 3 1 500
6.PAINTING WORKS 1 1 500
7. SPREADING OF USED BRICKS @ FLOORING 2 1 500
8. GHK/SITE CLEARING 0.5 1 500
9 500
10 500
11 500
12 500
13 500
14 500
TOTAL DURATION 12 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding machine 1 7 500
2. Cutting Machine 1 7 150
3. Grinding Machine 1 2 100
4. Scaffolding 1 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : Filterpress platform extension 2ft. width extension
PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1.PLATFORMS & STAGING 0.5 1 500
2.CUTTING OF CHANNELS FOR MAIN MEMBERS 1 2 500
3.CUTTING OF ANGLE BARS @ EXISTING FILTER PRESS PLATFORM 1 2 500
4.INSTALLATION OF SECONDARY FRAMING 3 2 500
5.INSTALLATION OF CHECKERED PLATE FLOORING 3 2 500
6.INSTALLATION OF BRACING/FULLWELDING 2 2 500
7. PAINTING WORKS 2 2 500
8. GHK/SITE CLEARING 0.5 1 500
9 500
10 500
11 500
12 500
13 500
14 500
TOTAL DURATION 13 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding machine 8 0 500
2. Cutting Machine 8 1 150
3. Grinding Machine 5 0 100
4. Scaffolding 8 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : Filterpress platform extension 2ft. width extension
PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1.PLATFORMS & STAGING 0.5 1 500
2.CUTTING OF CHANNELS FOR MAIN MEMBERS 1 2 500
3.CUTTING OF ANGLE BARS @ EXISTING FILTER PRESS PLATFORM 1 2 500
4.INSTALLATION OF SECONDARY FRAMING 3 2 500
5.INSTALLATION OF CHECKERED PLATE FLOORING 3 2 500
6.INSTALLATION OF BRACING/FULLWELDING 2 2 500
7. PAINTING WORKS 2 2 500
8. GHK/SITE CLEARING 0.5 1 500
9 500
10 500
11 500
12 500
13 500
14 500
TOTAL DURATION 13 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding machine 8 0 500
2. Cutting Machine 8 1 150
3. Grinding Machine 5 0 100
4. Scaffolding 8 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : MISC.WORKS - ADMIN,SCM,HRM,ISO,ENG'G WHSE (JULY 2007)
PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1.FABTN/INSTLN OF CABINET FOR SCM-PURCHASING 2 1 500
2.FABTN/INSTLN OF CABINET FOR ISO OFFICE 2 1 500
3.FABTN/INSTLN OF CABINET FOR ENG'G WHSE OFFICE 2 1 500
4.REPAIR OF CANVASS TENT ALONG SCM-MC WAREHOUSE 1 1 500
5. REPAIR OF GENSET/AIR COMPRESSOR ENCLOSURE STAIRWELL 2 1 500
6. INSTALLATION OF "SSS" NUMBER PLATE ALONG R & F LOCKER FRONTING
0.5 PRI- 1 500
PARKING 500
7 500
8 500
9 500
10 500
11 500
12 500
13 500
TOTAL DURATION 9.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Electric Jackhammer 0 0 500
2. Planner 0 1 150
3. Grinding Machine 0 0 100
4. Scaffolding-GONDOLLA 0 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : REPAIR OF DAMAGE DRIVEWAY ALONG BATT.FEEDING-RIGHT SIDE PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1. MATERIALS,EQUIPMENT PREPARATION 0.25 1 500
2. LAYOUT 0.25 1 500
3. BREAKING OF ASPHALT,CONCRETE PAVEMENT USING PRI-JACKHAMMER3 2 500
4. EXCAVATION 2.5 2 500
5. HAULING OF ASPHALT & CONCRETE DEBRIS 1 1 500
5. FABTN/INSTLN OF REBARS/FORMWORKS 0.5 2 500
6. COMPACTION/GRAVEL BEDDING 1 2 500
7. CONCRETING WORKS USING READYMIX 1 2 500
8. SITE CLEARING/GHK 0.5 1 500
9 500
10 500
11 500
12 500
13 500
TOTAL DURATION 10 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Electric Jackhammer 0 0 500
2. Planner 0 1 150
3. Grinding Machine 0 0 100
4. Scaffolding-GONDOLLA 0 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : REPAINTING OF SIDINGS ALONG BLAST BH CANOPY PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1.DISMANTLING OF END FLASHING 1 2 500
2.INSTALLATION OF PLATFORM (GONDOLLA TYPE) 0.5 2 500
3.CLEANING OF SIDINGS SURFACE 1 1 500
4. PAINTING OF SIDINGS USING SOMAR BEIGE 2 2 500
5. INSTALLATION OF NEW END FLASHING W/ CRYSTAL BLUE IN COLOR 1 1 500
6. DISMANTLING OF GONDOLLA PLATFORMS 0.5 2 500
7. SITE CLEARING/GHK 0.5 1 500
8 500
9 500
10 500
11 500
12 500
13 500
14 500
TOTAL DURATION 6.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Electric Jackhammer 0 0 500
2. Planner 7 1 150
3. Grinding Machine 0 0 100
4. Scaffolding-GONDOLLA 6 4 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : MEETING ROOM FOR ADMIN.PRODUCTION OFFICE PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT 0.5 1 500
2. REMOVAL OF EXISTING WOODEN PARTITION 1 1 500
4. INSTALLATION OF WOODEN FRAMING 1.5 1 500
5. INSTALLATION OF PLYWOOD 1 1 500
6. INSTALLATION OF DOOR 1 1 500
7 INSTALLATION OF CEILING CORNICE 0.5 1 500
9 PAINTING WORKS 2 1 500
10 GHK/SITE CLEARING 0.5 1 500
11 500
12 500
13 500
14 500
15 500
16 500
TOTAL DURATION 8 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Electric Jackhammer 0 0 500
2. Planner 7 1 150
3. Grinding Machine 0 0 100
4. Scaffolding 0 0 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : MODIFICATION OF ADMIN.PRODUCTION OFFICE PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT 0.5 1 500
2. REMOVAL OF EXISTING WOODEN PARTITION 1 1 500
3. MODIFICATION OF ENTRANCE DOOR - RELOCATION 2 1 500
4. INSTALLATION OF WOODEN FRAMING 2 2 500
5. INSTALLATION OF PLYWOOD 1 2 500
6. INSTALLATION OF DOORS,JAMBS & WINDOWS 2 2 500
7 INSTALLATION OF CEILING CORNICE 1 1 500
8 MODIFICATION OF ALUMINUM WINDOW ALONG AVP-SUPPORT AREA 2 1 500
9 PAINTING WORKS 2.5 1 500
10 GHK/SITE CLEARING 0.5 1 500
11 500
12 500
13 500
14 500
15 500
16 500
TOTAL DURATION 14.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Electric Jackhammer 0 0 500
2. Planner 7 1 150
3. Grinding Machine 0 0 100
4. Scaffolding 0 0 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
TOTAL PROJECT COSTPhp
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : REPAIR OF PERIMETER FENCE-PILOT NEAR SLAGPIT2 PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT 0.25 1 500
2. MATERIALS PREPARATION 0.5 1 500
3.REMOVAL OF DAMAGE CORRIGATED SHEET,FENCE & FRAMING 1 1 500
4. PAINTING WORKS 1 1 500
5. INSTALLATION OF NEW CORRUGATED FENCE 1 1 500
6. GHK/SITE CLEARING 0.5 1 500
7 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 4.25 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 5 300
2. Cutting Machine 1 5 150
3. Grinding Machine 1 5 100
4. Scaffolding 2 5 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : RENOVATION OF PRI-BOARDROOM PR#:
Item Scope of Works # of Skilled Rate per
Days Day
1. PREPARATION OF AREA / CLEARING WORKS 1 2 500
2. DEMOLITION OF EXISTING WALL 3 2 500
3. HAULING OF DEBRIS 1 1 500
4. WOOD SANDING 1 2 500
5. HAULING OF MATERIALS 2 1 500
6. LAYOUT 0.5 1 500
7 CONSTRUCTION OF WOODEN PARTITION-JUT/AVT 5 2 500
8 CONSTRUCTION OF MASONRY WALL-BOARDROOM 6 2 500
9 REPAIR OF CEILING 4 2 500
10 DOORS & WINDOWS JAMB 2 2 500
11 RELOCATION OF AIRCON 2 1 500
12 INSTALLATION OF TILES /CUTTING/CEMENT GROUTING 6 2 500
13 PAINTING WORKS 3 2 500
14 500
15 500
16 500
TOTAL DURATION 36.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Electric Jackhammer 1 3 500
2. Planner 1 6 150
3. Grinding Machine 1 6 100
4. Scaffolding 2 3 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : LANDSCAPPING OF WALL @BLAST SCRUBBER PR#:
OPTION II - SLAG CHB W/ REINFORCED COLUMN/FOOTING
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT 0.5 1 500
2. FABTN/INSTLN OF CONCRETE PRECAST MOULDING FOR PLANTS 2.5 1 500
3. FABTN/INSTLN OF CONCRETE PRECAST MOULDING -FOUNTAIN 2.5 1 500
4. PLASTERING WORKS 2 1 500
5. PAINTING WORKS 3 1 500
6. PLANTING WORKS 1 1 500
7 SITE CLEARING / GHK 0.5 1 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 12 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 4 300
2. Cutting Machine 4 150
3. Grinding Machine 4 100
4. Scaffolding 3 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : CONSTRUCTION OF RETAINING WALL BET SLAGPIT2 & WTP2 PR#:
OPTION II - SLAG CHB W/ REINFORCED COLUMN/FOOTING
Item Scope of Works # of Skilled Rate per
Days Day
1. EXCAVATION 8 1 500
2. REINFORCEMENT 6 3 500
3. CONCRETING WORKS 4 2 500
4. FORMWORKS 4 2 500
5. SLAG CHB LAYING 7 2 500
6. PLASTERING 4 2 500
7 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 33 DAYS
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE : SAFETY BARRIER FOR SMELTING WALL CHAMBER FRONTING DRIER PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT 0.25 1 500
2. CUTTING OF MS PLATE & B.I PIPES 0.5 2 500
3. REPAIR OF DAMAGE PAVEMENT OF RC WALLS 3 2 500
4. INSTALLATION OF MS PLATE W/ EXPANSION BOLT 7 FULLWELDING 3 2 500
5. BREAKING OF CONCRETE PAVEMENT 3 1 500
6. INSTALLATION OF PIPE BARRICADE 3 2 500
7. PAINTING WORKS (LEMON YELOW W/ BLACK STRIPES) 2 1 500
8. GHK/SITE CLEARING 0.5 1 500
9. 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 15.25 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 12 300
2. Cutting Machine 1 12 150
3. Grinding Machine 1 12 100
4. Scaffolding 2 7 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE :FABTN/INSTLN OF BOXSTRUTT SME-PRODTN BLDG PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT/CUTTING OF MS ANGLE BARS 0.25 1 500
2. FABRICATION OF 4-SETS BOX STRUTT 3 2 500
3. INSTALLATION OF 4-SETS OF BOXSTRUTT 3 2 500
4. REMOVAL OF EXISTING 2-UNITS BOXSTRUTT OF REC.PRODTN BLDG 1 2 500
5. PAINTING WORKS 2 1 500
6. GHK/SITE CLEARING 0.5 2 500
7 500
8 500
9. 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 9.75 DAYS
Skilled @ Php 500.00/day Sub Total
Unskilled @ Php 300.00/day % Supervision
% mark-up
% VAT
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 5 300
2. Cutting Machine 1 5 150
3. Grinding Machine 1 5 100
4. Scaffolding 2 8 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE :REHABTN.OF PILOT STAFFHOUSE 2ND FLR RM2 PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. MATERIALS/TOOLS PREPARATION 0.25 1 500
2. PLATFORMS & STAGING 0.25 1 500
3. REMOVAL OF ENTIRE CEILING PANELS 1 1 500
4. HAULING OF RECOVERED DEBRIS 1 1 500
5. INSTALLATION OF CEILING JOIST & HANGER 2 1 500
6. INSTALLATION OF NEW CEILING 2 1 500
7. REPAIR OF WOODEN PARTITIONS 1 1 500
8. PAINTING WORKS 2 1 500
9. GHK / SITE CLEARING 0.5 1 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 10 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 300
2. Cutting Machine 150
3. Grinding Machine 100
4. Scaffolding 2 6 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE :FABTN/INSTLN OF SAFETY BARRIER @ PRODTN-
SME2 BLDG PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT/CUTTING OF MS PLATE 1 2 500
2. INSTALLATION OF CUT MS PLATES 4 2 500
3. FULLWELDING 0.5 2 500
4. APPLICATION OF RUST CONVERTER & PRIMER 1 1 500
5. FINAL COAT USING LEMON YELLOW W/ BLACK STRIPES 2 1 500
6. GHK/SITE CLEARING 0.5 1 500
7 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 9 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 5 300
2. Cutting Machine 1 5 150
3. Grinding Machine 1 5 100
4. Scaffolding 2 5 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE REPLACEMENT OF ROOF-SME.PRDTN DRIER BH
AREA PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. HAULING OF LONG SPAN ROOFING 1 1 500
2. DISMANTLING OF DAMAGED ROOFING & PURLINS 1 2 500
3. INSTALLATION OF NEW PURLINS 1 2 500
4. PAINTING WORKS 1 2 500
5. INSTALLATION OF LONG SPAN ROOFING, RIDGEROLL & FLASHING 1 2 500
6. GHK/SITE CLEARING 0.5 1 500
7 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 5.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 3 300
2. Cutting Machine 1 3 150
3. Grinding Machine 1 3 100
4. Scaffolding 3 3 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE STRENGTHENING OF WWTF BLDG COLUMNS-9
UNITS PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. INSTALL ADDITIONAL STIFFENER PLATE @ WEB & FLANGE MEMBERS 4 2 500
@ BOTTOM PART OF DETERIORATED COLUMN 500
2. INSTALLATION OF FORMWORKS 2 2 500
3. CONCRETING WORKS INCLUDING PLASTERING 4 2 500
4. PAINTING WORKS W/ STRIPES LEMON YELLOW 2 1 500
5. GHK/SITE CLEARING 0.5 1 500
7 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 12.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 8 300
2. Cutting Machine 1 8 150
3. Grinding Machine 1 8 100
4. Scaffolding 2 3 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
IN-HOUSE ESTIMATE
PROJECT TITLE FABTN/INSTLN OF SAFETY BARRIER @ PRODTN-
SME2 BLDG PR#:
LABOR COST
Item Scope of Works # of Skilled Rate per
Days Day
1. LAY-OUT/CUTTING OF MS PLATE 1 1 500
2. INSTALLATION OF CUT MS PLATES 2 2 500
3. FULLWELDING 1 2 500
4. APPLICATION OF RUST CONVERTER & PRIMER 1 2 500
5. FINAL COAT USING LEMON YELLOW W/ BLACK STRIPES 1 2 500
6. GHK/SITE CLEARING 0.5 1 500
7 500
8 500
9 500
10. 500
11. 500
12. 500
13. 500
14. 500
15. 500
TOTAL DURATION 6.5 DAYS
EQUIPMENT RENTAL
# of Days Rate per
Item EQUIPMENT Qty
Used Day
1. Welding Machine 1 4 300
2. Cutting Machine 1 4 150
3. Grinding Machine 1 4 100
4. Scaffolding 2 3 100
EQUIPMENT COST
LABOR COST
MATERIAL COST
Prepared by:
PCW PLANNER
_______
Noted by:
HENRY L. COPAWAY
Facilities Manager
Unskilled Rate per Cost
Day
3 300 1400
3 300 5600
3 300 4200
3 300 1400
2 300 1100
2 300 2200
2 300 2200
2 300 2200
1 300 800
3 300 1400
300 0
300 0
300 0
300 0
12.86
Php 22,500.00 81
Php 3,375.00 13.5
Php 2,250.00
Php 2,700.00
Cost
0
600
500
400
Php 1,500.00
Php 30,825.00
Php
32,325.00
Unskilled Rate per Cost
Day
2 300 550
4 300 5500
4 300 2200
4 300 3300
2 300 3300
2 300 1100
4 300 3400
4 300 850
300 0
300 0
300 0
300 0
300 0
300 0
Php 20,200.00
Php 3,030.00
Php 2,020.00
Php 2,424.00
Cost
3500
1050
200
400
Php 5,150.00
Php 27,674.00
Php
32,824.00
1100579515
Unskilled Rate per Cost
Day
4 300 850
4 300 2200
4 300 2200
4 300 6600
4 300 6600
4 300 4400
4 300 4400
4 300 850
300 0
300 0
300 0
300 0
300 0
300 0
Php 28,100.00
Php 4,215.00
Php 2,810.00
Php 3,372.00
Cost
0
1200
0
3200
Php 4,400.00
Php 38,497.00
Php
42,897.00
1100579515
Unskilled Rate per Cost
Day
4 300 850
4 300 2200
4 300 2200
4 300 6600
4 300 6600
4 300 4400
4 300 4400
4 300 850
300 0
300 0
300 0
300 0
300 0
300 0
Php 28,100.00
Php 4,215.00
Php 2,810.00
Php 3,372.00
Cost
0
1200
0
3200
Php 4,400.00
Php 38,497.00
Php
42,897.00
Unskilled Rate per Cost
Day
1 300 1600
1 300 1600
2 300 2200
2 300 1100
2 300 2200
1 300 400
4 300 0
6 300 0
4 300 0
300 0
300 0
300 0
300 0
300 0
Php 9,100.00
Php 1,365.00
Php 910.00
Php 1,092.00
Cost
0
0
0
0
Php -
Php 12,467.00
Php
12,467.00
Unskilled Rate per Cost
Day
4 300 425
2 300 275
4 300 6600
4 300 5500
6 300 2300
4 300 1100
4 300 2200
6 300 2800
4 300 850
300 0
300 0
300 0
300 0
300 0
Php 22,050.00
Php 3,307.50
Php 2,205.00
Php 2,646.00
Cost
0
0
0
0
Php -
Php 30,208.50
Php
30,208.50
Unskilled Rate per Cost
Day
4 300 2200
4 300 1100
6 300 2300
4 300 4400
2 300 1100
4 300 1100
4 300 850
300 0
300 0
300 0
300 0
300 0
300 0
300 0
Php 13,050.00
Php 1,957.50
Php 1,305.00
Php 1,566.00
Cost
0
1050
0
2400
Php 3,450.00
Php 17,878.50
Php
21,328.50
Unskilled Rate per Cost
Day
2 300 550
2 300 1100
2 300 1650
2 300 1100
2 300 1100
2 300 550
2 300 2200
3 300 700
300 0
300 0
300 0
300 0
300 0
300 0
Php 8,950.00
Php 1,342.50
Php 895.00
Php 1,074.00
Cost
0
1050
0
0
Php 1,050.00
Php 12,261.50
Php
13,311.50
Unskilled Rate per Cost
Day
2 300 550
2 300 1100
3 300 2800
3 300 3800
3 300 1900
3 300 3800
2 300 1100
2 300 2200
2 300 2750
3 300 700
300 0
300 0
300 0
300 0
300 0
300 0
Php 20,700.00
Php 3,105.00
Php 2,070.00
Php 2,484.00
Cost
0
1050
0
0
Php 1,050.00
Php 28,359.00
Php
29,409.00
Php 5,950.00
Php 892.50
Php 595.00
Php 714.00
Cost
1500
750
500
1000
Php 3,750.00
Php 8,151.50
Php
11,901.50
Php 78,150.00
Php 11,722.50
Php 7,815.00
Php 9,378.00
Cost
1500
900
600
600
Php 3,600.00
Php 107,065.50
Php
110,665.50
Php 20,400.00
Php 3,060.00
Php 2,040.00
Php 2,448.00
Cost
0
0
0
0
Php -
Php 27,948.00
Php
27,948.00
Php 96,800.00
Php 14,520.00
Php 9,680.00
Php 11,616.00
Cost
0
0
0
0
Php -
Php 132,616.00
Php
132,616.00
1100570746
Php 28,125.00
Php 4,218.75
Php 2,812.50
Php 3,375.00
Cost
3600
1800
1200
1400
Php 8,000.00
Php 38,531.25
Php
46,531.25
1100569998
Cost
1500
750
500
1600
Php 4,350.00
Php 25,584.75
Php
29,934.75
1100567332
Php 12,200.00
Php 1,830.00
Php 1,220.00
Php 1,464.00
Cost
0
0
0
1200
Php 1,200.00
Php 16,714.00
Php
17,914.00
1100570745
Php 17,750.00
Php 2,662.50
Php 1,775.00
Php 2,130.00
Cost
1500
750
500
1000
Php 3,750.00
Php 24,317.50
Php
28,067.50
1100567340
Php 13,750.00
Php 2,062.50
Php 1,375.00
Php 1,650.00
Cost
900
450
300
900
Php 2,550.00
Php 18,837.50
Php
21,387.50
1100565690
Php 25,050.00
Php 3,757.50
Php 2,505.00
Php 3,006.00
Cost
2400
1200
800
600
Php 5,000.00
Php 34,318.50
Php
39,318.50
1100570745
Unskilled Rate per Cost
Day
4 300 1700
4 300 4400
4 300 2200
4 300 2200
4 300 2200
4 300 850
300 0
300 0
300 0
300 0
300 0
300 0
300 0
300 0
300 0
Php 13,550.00
Php 2,032.50
Php 1,355.00
Php 1,626.00
Cost
1200
600
400
600
Php 2,800.00
Php 18,563.50
Php
21,363.50