O Enyenra-3a appraisal well (original wellbore) was drilled by the Deepwater Millennium

with 6 5/8`` drill pipe.


The 12 / section was competed with the data below. This is 2.13 days or 55 ahead oI
the AFE.

AFE Days Actual Days NPT Days
Upper channel 0.76 0.22 0.00
Lower Channel 0.55 0.58 0.00
Total Days


O At 41 m/hr and 15 m/hr over the Upper and Lower Mahogany intervals respectively, this
is more than double the previous Iastest section interval (J-13). See data summary in the
table below (see also Appendix H Ior oIIset well comparisons). This represents an
improvement oI 41 hours over the net AFE time or 15 hours saving iI J-13 ROPS were to
be assumed over the same interval.

Previous(Owo-1) (m/hr) Enyenra-3a(m/hr)
16`` hole Overburden 22.5

12 /`` hole
Overburden 13.56 15
Upper Channel 5.04 31.24
Lower Channel 2.95 7.14