Project Name: SALESBOOM

Poject Code: SB
Location Hyderbad
Start Date 18-Aug-08
End Date 28-Oct-08
Team Details
Test Lead Karna Ganapathi
Test Engineers 1.D.SivaramaRaju     
2.B.Shekar            
3.Vishnuvardhan.K     
4.B.Spandana            
5.Sairabano            
6.Vinod Kumar            
7.R.veena             
Team Details
Project Name Type of Testing Phase Step Duration
SALESBOOM Functional KT Team Formation and Project Kickoff 1
Understanding 3
KT 2
Clarifications 3
Planning Test Condition Preparation 5
Test Condition Review 2
Test Case 8
Test Case Review 2
Test scenario 4
Test Scenario Review 2

Execution Comprehensive 15
DRM 2
Closure Test Summary Report Preparation 3
Planned Start Date Actual Start Date Planned End Date Actual End Date Status
18-Aug-08 18-Aug-08
19-Aug-08 21-Aug-08
22-Aug-08 25-Aug-08
26-Aug-08 28-Aug-08
29-Aug-08 4-Sep-08
5-Sep-08 8-Sep-08
9-Sep-08 18-Sep-08
19-Sep-08 22-Sep-08
23-Sep-08 26-Sep-08
29-Sep-08 30-Sep-08

1-Oct-08 21-Oct-08
22-Oct-08 23-Oct-08
24-Oct-08 28-Oct-08