WEEKS / PERIOD
SET DESIGN
SETS DEPARTMENT
COSTUME DESIGN
COSTUME DEPARTMENT
PROPERTIES DESIGN
PROPERTIES DEPARTMENT
LIGHTING DEPARTMENT
SOUND DEPARTMENT
AV DEPARTMENT
STAGE MANAGEMENT
DIRECTOR
PRIOR
READ SCRIPT + HAVE DISCUSSIONS WITH THE DIRECTOR + THE REST OF THE CREATIVE TEAM
READ SCRIPT + HAVE DISCUSSIONS WITH THE DIRECTOR + THE REST OF THE CREATIVE TEAM
READ SCRIPT + HAVE DISCUSSIONS WITH THE DIRECTOR + THE REST OF THE CREATIVE TEAM
WK -18
DEVELOP CONCEPT
DEVELOP CONCEPT
WK -17
PRESENT CONCEPT
PRESENT CONCEPT
WK -16
COMMENCE DISCUSSIONS WITH HEAD OF SCENERY CONSTRUCTION WITH COMMENCE COSTUME DRAWINGS REGARD TO BUILDS, SPECIAL EFFECTSOR TRICK PROPS
COMMENCE PROP DESIGNS AND DISCUSSIONS WITH HOD PROPERTIES WITH REGARDTO BUILDS, SPECIAL EFFECTS OR TRICK PROPS
WK -15
PRE-PRODUCTION
HEAD OF COSTUME VIEW ROUGH COSTUME RENDERINGS HAVE NUMBERS AND BREAKDOWNS
WK -14
WK -13
WK -12
DESIGN DELIVERY: PRESENT FINSHED PRE-PRODUCTION MODEL AT THE BEGINNING OF THIS WEEK+ LX design discussions WEEK 6 COMPLETE FULL DOCUMENATION
DESIGN DELIVERY: PRESENT FINSHED DESIGN DELIVERY: PRESENT FINSHED PROP DRAWINGS AT THE BEGINNING COSTUME DRAWINGS AT THE DESIGN DELIVERY TO HEAD OF PRESENT TO HEAD OF COSTUME AND OF THIS WEEK+ LX design discussions . BEGINNING OF THIS WEEK+ LX design PROPERTIES, PROPERTIES DISCUSS DOCUMENTATION PRESENT TO HEAD OF PROPS AND discussions SUPERVISOR ALLOCATED. DISCUSS DOCUMENTATION COMPLETE FULL DOCUMENATION COMPLETE FULL DOCUMENATION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
COSTINGS
WK -9
PRE-PRODUCTION
DISCUSS DESIGN WITH HODS TO FACILITAE COSTING PROCESS. DESIGN TO BE AGREED TO BY THE END OF THIS WEEK.
DISCUSS DESIGN WITH HODS TO FACILITAE COSTING PROCESS. DESIGN TO BE AGREED TO BY THE END OF THIS WEEK.
DESIGN PRESENTATION TO SUPERVISOR. DOCUMENTATION DELIVERY TO CREW SUPERVISOR .DOCUMENTATION TO CLASS TEACHERS
DISCUSS DESIGN WITH HODS/SUPERVISOR TO FACILITAE COSTING PROCESS. DESIGN TO BE AGREED TO BY THE END OF THIS WEEK.
holiday
WK -8
Start of week-DESIGN PRESENTATION TO PRODUCTION CREW AND SIGN OFF . START BUILD. CREW STARTS.
Start of week-DESIGN PRESENTATION TO CREW AND SIGN OFF. COMMENCE PRODUCTION. MEASUREMENTS TAKEN. BUDGET FINALISED.
DESIGN PRESENTATION -3RD AND 2ND DESIGN PRESENTATION -3RD AND 2ND DESIGN PRESENTATION -3RD AND 2ND DESIGN PRESENTATION -3RD AND 2ND YEAR CREW YEAR CREW YEAR CREW YEAR CREW
WK -7
WORKSHOP
PRE PRODUCTION
WK -6
REHEARSAL WEEK 1
MEET AND GREET . DESIGN PRESENTATION. PRE FOR WORKSHOP FULL CREW COMMENCE. WORKSHOP ASSIST IN BUILD + SUPERVISION OF FULL WORKSHOP
MEET AND GREET . DESIGN PRESENTATION.FULL CREW COMMENCE. ASSIST IN BUILD + SUPERVISION OF FULL WORKSHOP
MEET AND GREET. DESIN PRESENTATIION (RUN BY THE STAGE MANAGEMENT TEAM)
MEET AND GREET. DESIN PRESENTATIION (RUN BY THE STAGE MANAGEMENT TEAM)
MEET AND GREET. DESIN PRESENTATIION (RUN BY THE STAGE MANAGEMENT TEAM)
MEET AND GREET. DESIN PRESENTATIION (RUN BY THE STAGE MANAGEMENT TEAM)
WK -5
REHEARSAL WEEK 2
WORKSHOP
WK -4
REHEARSAL WEEK 3
WORKSHOP
CUE SYNOPSIS
WK -3
REHEARSAL WEEK 4
WORKSHOP
FINAL DRAWINGS
FINAL DRAWINGS
APRA, COMPANY COMP REQUESTS AND FOH INFO DUE. MEET WITH VENUE COORDINATOR AND PRODUCTION COORDINATOR
WK -2
BUMP IN (DELIVERY)
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WK -1
TECH WEEK
NOTES
BUILD/CREW
NOTES
NOTES
BUILD/CREW
PLOT/TECH
PLOT/TECH
PLOT/TECH
PLOT/TECH
WK 0
PERFORMANCE
N/A
NOTES
N/A
CREW NOTES
CREW NOTES
CREW NOTES
BUMP OUT
RETURNS/ RECONCILIATION
RETURNS/ RECONCILIATION
RETURNS/ RECONCILIATION
RETURNS/ RECONCILIATIONS
RETURNS/ RECONCILIATION
RETURNS/ RECONCILIATION
RETURNS/ RECONCILIATION
RETURNS/ RECONCILIATION
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
SET DESIGN
PRIOR
READ THE SCRIPT A NUMBER OF TIMES, HAVE INITIAL CONVERSATIONS WITH THE DIRECTOR, COSTUME DESIGNER & LIGHTING DESIGNER & COMMENCE SCENE & PROP BREAKDOWNS (ALL RELIVANT EXTRACTIONS).
WK -20
PRE-PRODUCTION
CONTINUE DISCUSSIONS WITH THE DIRECTOR & THE REST OF THE CREATIVE TEAM, DEVELOP THE CONCEPT & CONTINUE ON ALL EXTRCATIONS.
WK -19
PRE-PRODUCTION
PRESENT THE CONCEPT THROUGH REFERENCES, SKETCHES & SKETCH MODELS + PRESENT ALL EXTRACTIONS
WK -18
PRE-PRODUCTION
COMMENCE WHITE CARD MODELLING + CONTINUE DISCUSSIONS WITH THE DIRECTOR, COSTUME DESIGNER & LIGHTING DESIGNER. CONSULT WITH NIDA HODs AS NEEDS BE. THIS SHOULD INCLUDE DISCUSSIONS WITH REGARD TO O,H & S WITH ALLAN MORGAN.
WK -17
PRE-PRODUCTION
PRESENT THE WHITE CARD MODEL & REFERENCES TO HEAD OF DESIGN, HEAD OF PRODUCTION & THE PRODUCTION MANAGER. CONTINUE CONSULATION WITH HEADS OF SET & PROP WORKSHOPS.
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
PRESENT THE FINSHED FULLY RENDERED SET MODEL AT THE BEGINNIG OF THIS WEEK.
WK -14 PRE-PRODUCTION WEEK 6
TO HEAD OF DESIGN (MSM), HEAD OF PRODUCTION (MM), THE PRODUCTION MANAGER (ND), HEAD OF SET CONSTRUCTION (TP), HEAD OF PROPS (TA), DIRECTOR-BUILDING SERVISES (AM) & TECHNICAL MANAGER (MK). THE DIRECTOR & OTHER MEMBERS OF THE CREATIVE TEAM & CREW SHOULD BE PRESENT FOR THIS PRESENTATION. AT THE CONCLUSION OF THIS PRESENTATION CONTINUE WITH THE FULL DOCUMNATION PACKAGE FOR SET & PROPS WHILST MAINTAINING ON-GOING DISCUSSIONS WITH WORKSHOPS WITH A PARTICULAR REFERNCE TO TECHNAICAL CONSIDERATIONS & BUDGET.
WK -13
PRE-PRODUCTION
COMPLETE THE FULL DOCUMENATION PACKAGE & PRESENT THIS AT THE END OF THIS WEEK . AT THE CONCLUSION OF THIS PRESENTATION CONTINUE MAINTAIN ON-GOING DISCUSSIONS WITH WORKSHOPS, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL CONSIDERATIONS & BUDGET.
WK -12
PRE-PRODUCTION
MAINTAIN ON-GOING DISCUSSIONS WITH WORKSHOPS, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL CONSIDERATIONS & BUDGET. RESOLVE WITH THE DIRECTOR ANY MATTERS PERTAINING TO DESIGN REVISIONS.
MAINTAIN ON-GOING DISCUSSIONS WITH WORKSHOPS, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL WK -11 PRE-PRODUCTION CONSIDERATIONS & BUDGET.RESOLVE WITH THE DIRECTOR ANY MATTERS PERTAINING TO DESIGN REVISIONS. BY
THE
10
END OF THIS WEEK THE DESIGN SHOULD BE SIGNED OFF AS THE AGREED PRODUCTION.
BREAK :READ THE SCRIPT OF YOU R FORTH TERM PRODUCTION A NUMBER OF TIMES, HAVE INITIAL CONVERSATIONS
WK -10 PRE-PRODUCTION WITH THE DIRECTOR, COSTUME DESIGNER & LIGHTING DESIGNER & COMMENCE SCENE & PROP BREAKDOWNS (ALL RELIVANT EXTRACTIONS). 11
WK -9
PRE-PRODUCTION
BREAK: RESEARCH & COMPILE REFERENCES FOR THE FORTH TERM PRODUCTION. CONTINUE DISCUSSIONS WITH THE
REST OF THE CREATIVE TEAM.
12
WK -8
PRE-PRODUCTION WEEK 5
PRESENT THE SET DESIGN TO THE CAST & CREW WITH THE REST OF THE CREATIVE TEAM. COMMENCE
WORKSHOP INCLUDING PROP FOR FULL CREW.PREP.
13
WK -7
PRE-PRODUCTION WEEK 6
14
WK -6
REHEARSAL WEEK 1
15
WK -5
REHEARSAL WEEK 2
BUILD : ASSIST IN THE FABRICATION OF THE SET WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW TO ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN.
16
WK -4
REHEARSAL WEEK 3
BUILD : ASSIST IN THE FABRICATION OF THE SET WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW TO ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN.
17
WK -3
REHEARSAL WEEK 4
BUILD : ASSIST IN THE FABRICATION OF THE SET WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW TO ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN.
18
WK -2
19
WK -1
TECH WEEK
WORK IN CONJUNCTION WITH THE DIRECTOR & THE REST OF THE CREATIVE TEAM & CREW TO REALISE THE PRODUCTION.
20
WK 0
PERFORMANCE
ATTEND PERFORMANCES
21
BUMP OUT
ASSIST IN RETURNING THE VENUE TO ITS ORIGINAL STATE + ENSURE THAT RETURNS ARE COMPLETED.
22
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
SETS WORKSHOP
PRIOR
WK -20
PRE-PRODUCTION
WK -19
PRE-PRODUCTION
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
WK -4
REHEARSAL WEEK 3
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
WK 0
PERFORMANCE
BUMP OUT
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
COSTUME DESIGN
PRIOR
READ THE SCRIPT A NUMBER OF TIMES, HAVE INITIAL CONVERSATIONS WITH THE DIRECTOR, SET DESIGNER & LIGHTING DESIGNER & COMMENCE SCENE & PROP BREAKDOWNS (ALL RELIVANT EXTRACTIONS).
WK -20
PRE-PRODUCTION
CONTINUE DISCUSSIONS WITH THE DIRECTOR & THE REST OF THE CREATIVE TEAM, DEVELOP THE CONCEPT & CONTINUE ON ALL EXTRCATIONS.
WK -19
PRE-PRODUCTION
PRESENT THE CONCEPT THROUGH REFERENCES & SKETCHES + PRESENT ALL EXTRACTIONS
WK -18
PRE-PRODUCTION
COMMENCE UNRENEDERD COSTUME DRAWINGS + CONTINUE DISCUSSIONS WITH THE DIRECTOR, SET & PROPS DESIGNER & LIGHTING DESIGNER. CONSULT WITH NIDA HODs AS NEEDS BE.
WK -17
PRE-PRODUCTION
PRESENT THE UNRENDERED COSTUME DRAWINGS REFERENCES TO HEAD OF DESIGN, HEAD OF PRODUCTION & THE PRODUCTION MANAGER. CONTINUE CONSULATION WITH THE HEAD OF COSTUME.
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
PRESENT THE FINSHED RENDERED COSTUME DRAWINGS AT THE BEGINNIG OF THIS WEEK.
WK -14 PRE-PRODUCTION WEEK 6 TO HEAD OF DESIGN (MSM), HEAD OF PRODUCTION (MM), THE PRODUCTION MANAGER (ND), HEAD OF COSTUME (FR). THE DIRECTOR & OTHER MEMBERS OF THE CREATIVE TEAM & CREW SHOULD BE PRESENT FOR THIS PRESENTATION. AT THE CONCLUSION OF THIS PRESENTATION, CONTINUE WITH THE FULL DOCUMNATION PACKAGE FOR COSTUME WHILST MAINTAINING ON-GOING DISCUSSIONS WITH WARDROBE GIVIING PARTICULAR FOCUS TO TECHNAICAL CONSIDERATIONS & BUDGET.
WK -13
PRE-PRODUCTION
COMPLETE THE FULL DOCUMENATION PACKAGE & PRESENT THIS AT THE END OF THIS WEEK . AT THE CONCLUSION OF THIS PRESENTATION CONTINUE TO MAINTAIN ON-GOING DISCUSSIONS WITH WARDROBE, AGAIN WITH A PARTICULAR FOCUS TO BUDGET, CHECKING STOCK & SOURCEING FABRIC SAMPLES.
WK -12
PRE-PRODUCTION
MAINTAIN ON-GOING DISCUSSIONS WITH WARDROBE, AGAIN WITH A PARTICULAR REFERNCE TO TECHNICAL CONSIDERATIONS & BUDGET. RESOLVE WITH THE DIRECTOR ANY MATTERS PERTAINING TO DESIGN REVISIONS.
MAINTAIN ON-GOING DISCUSSIONS WITH WORKSHOPS, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL WK -11 PRE-PRODUCTION CONSIDERATIONS & BUDGET.RESOLVE WITH THE DIRECTOR ANY MATTERS PERTAINING TO DESIGN REVISIONS.
BY
THE END OF THIS WEEK THE DESIGN SHOULD BE SIGNED OFF AS THE AGREED PRODUCTION.
BREAK :READ THE SCRIPT OF YOUR FORTH TERM PRODUCTION A NUMBER OF TIMES, HAVE INITIAL CONVERSATIONS WITH
WK -10 PRE-PRODUCTION THE DIRECTOR, SET/PROPS DESIGNER & LIGHTING DESIGNER + COMMENCE ALL RELIVANT EXTRACTIONS & COMMENCE RESEARCH.
WK -9
PRE-PRODUCTION
BREAK: COMPILE RESEARCH REFERENCES FOR THE FORTH TERM PRODUCTION. CONTINUE DISCUSSIONS WITH THE
REST OF THE CREATIVE TEAM.
WK -8
PRE-PRODUCTION WEEK 5
PRESENT THE COSTUME DESIGN TO THE CAST & CREW WITH THE REST OF THE CREATIVE TEAM.
COMMENCE WORKSHOP INCLUDING PROP FOR FULL CREW.PREP.
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
BUILD : ASSIST IN THE FABRICATION OF THE COSTUMES WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW TO ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN.
WK -4
REHEARSAL WEEK 3
BUILD : ASSIST IN THE FABRICATION OF THE COSTUMES WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW TO ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN.
WK -3
REHEARSAL WEEK 4
BUILD : ASSIST IN THE FABRICATION OF THE COSTUMES WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW TO ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN.
WK -2
BUMP IN WEEK REHEARSAL WEEK BUILD: ASSIST IN THE BUMP-IN WHERE REQUIRED WHILST CONTINUEING TO SUPERVSE THE WORKSHOP 5
WK -1
TECH WEEK
WORK IN CONJUNCTION WITH THE DIRECTOR & THE REST OF THE CREATIVE TEAM & CREW TO REALISE THE PRODUCTION.
WK 0
PERFORMANCE
ATTEND PERFORMANCES
BUMP OUT
ASSIST IN RETURNING THE VENUE TO ITS ORIGINAL STATE + ENSURE THAT RETURNS ARE COMPLETED.
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
COSTUME WORKSHOP
PRIOR
WK -20
PRE-PRODUCTION
WK -19
PRE-PRODUCTION
ProdProc ess
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
WK -4
REHEARSAL WEEK 3
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
WK 0
PERFORMANCE
BUMP OUT
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
PROPERTIES DESIGN
PRIOR
READ THE SCRIPT A NUMBER OF TIMES, HAVE INITIAL CONVERSATIONS WITH THE DIRECTOR, COSTUME DESIGNER & LIGHTING DESIGNER & COMMENCE SCENE/PROP BREAKDOWNS (ALL RELIVANT EXTRACTIONS).
WK -20
PRE-PRODUCTION
CONTINUE DISCUSSIONS WITH THE DIRECTOR & THE REST OF THE CREATIVE TEAM, DEVELOP THE CONCEPT & CONTINUE ON ALL EXTRCATIONS.
WK -19
PRE-PRODUCTION
PRESENT THE DESIGN CONCEPT THROUGH REFERENCES & SKETCHES + PRESENT ALL EXTRACTIONS
WK -18
START TO RESOLVE THE PROP DESIGNS WHILST CONTINUING DISCUSSIONS WITH THE DIRECTOR, COSTUME DESIGNER & PRE-PRODUCTION LIGHTING DESIGNER. CONSULT WITH NIDA HEAD OF PROPS (TA) AS NEEDS BE. THIS SHOULD INCLUDE DISCUSSIONS WITH REGARD TO O,H & S WITH ALLAN MORGAN WHERE REQUIRED.
WK -17
PRE-PRODUCTION
PRESENT THE DEVELOPED PROP DRAWINGS & REFERENCES TO HEAD OF DESIGN, HEAD OF PRODUCTION & THE PRODUCTION MANAGER. CONTINUE CONSULATION WITH HEAD OF PROPS.
WK -16
WK -15
WK -14
PRESENT THE PROP DESIGNS AT THE BEGINNIG OF THIS WEEK TO HEAD OF DESIGN (MSM), HEAD OF PRODUCTION (MM), THE PRODUCTION MANAGER (ND), HEAD OF PROPS (TA). THE DIRECTOR & OTHER MEMBERS OF THE PRE-PRODUCTION CREATIVE TEAM & CREW SHOULD BE PRESENT FOR THIS PRESENTATION. WEEK 6 AT THE CONCLUSION OF THIS PRESENTATION CONTINUE WITH THE FULL DOCUMNATION PACKAGE FOR PROPS WHILST MAINTAINING ON-GOING DISCUSSIONS WITH WORKSHOP WITH A PARTICULAR REFERNCE TO TECHNAICAL CONSIDERATIONS & BUDGET.
WK -13
COMPLETE THE FULL DOCUMENATION PACKAGE & PRESENT THIS AT THE END OF THIS WEEK . PRE-PRODUCTION AT THE CONCLUSION OF THIS PRESENTATION MAINTAIN ON-GOING DISCUSSIONS WITH THE PROPS WORKSHOP, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL CONSIDERATIONS & BUDGET.
WK -12
PRE-PRODUCTION
MAINTAIN ON-GOING DISCUSSIONS WITH WORKSHOPS, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL CONSIDERATIONS & BUDGET. RESOLVE WITH THE DIRECTOR ANY MATTERS PERTAINING TO DESIGN REVISIONS.
WK -11
MAINTAIN ON-GOING DISCUSSIONS WITH WORKSHOPS, AGAIN WITH A PARTICULAR REFERNCE TO TECHNAICAL PRE-PRODUCTION CONSIDERATIONS & BUDGET.RESOLVE WITH THE DIRECTOR ANY MATTERS PERTAINING TO DESIGN REVISIONS. BY THE
END OF THIS WEEK THE DESIGN SHOULD BE SIGNED OFF AS THE AGREED PRODUCTION.
WK -10
PRE-PRODUCTION
BREAK :READ THE SCRIPT OF YOUR FORTH TERM PRODUCTION A NUMBER OF TIMES, HAVE INITIAL CONVERSATIONS
WITH THE DIRECTOR, COSTUME DESIGNER & LIGHTING DESIGNER & COMMENCE ALL RELIVANT EXTRACTIONS.
WK -9
PRE-PRODUCTION
BREAK: RESEARCH & COMPILE REFERENCES FOR THE FORTH TERM PRODUCTION. CONTINUE DISCUSSIONS WITH THE
REST OF THE CREATIVE TEAM.
WK -8
PRE-PRODUCTION PRESENT THE PROP DESIGNS TO THE CAST & CREW WITH THE REST OF THE CREATIVE TEAM. COMMENCE WEEK 5 WORKSHOP INCLUDING PROP FOR FULL CREW.PREP.
WK -7
WK -6
REHEARSAL WEEK 1
FULL CREW COMMENCES.BUILD : ASSIST IN THE FABRICATION OF PROPS WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW. ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN. MEET WITH PROPERTIES SUPERVISOR ON A REGULAR BASIS TO ENSURE ALL QUERIES ARE ADDRESSED AND CHECK THE REALISATION OF DESIGNS.
WK -5
REHEARSAL WEEK 2
BUILD : ASSIST IN THE FABRICATION OF PROPS WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW. ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN. MEET WITH PROPERTIES SUPERVISOR ON A REGULAR BASIS TO ENSURE ALL QUERIES ARE ADDRESSED AND CHECK THE REALISATION OF DESIGNS.
WK -4
REHEARSAL WEEK 3
BUILD : ASSIST IN THE FABRICATION OF PROPS WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW. ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN. MEET WITH PROPERTIES SUPERVISOR ON A REGULAR BASIS TO ENSURE ALL QUERIES ARE ADDRESSED AND CHECK THE REALISATION OF DESIGNS.
WK -3
REHEARSAL WEEK 4
BUILD : ASSIST IN THE FABRICATION OF PROPS WHERE APPROPRIATE & SUPERVISE THE WORK OF YOUR CREW. ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN. MEET WITH PROPERTIES SUPERVISOR ON A REGULAR BASIS TO ENSURE ALL QUERIES ARE ADDRESSED AND CHECK THE REALISATION OF DESIGNS.
WK -2
BUILD: SUPERVISE BUMP-IN BUILD : ASSIST IN THE FABRICATION OF PROPS WHERE APPROPRIATE & SUPERVISE THE BUMP IN WEEK WORK OF YOUR CREW. ENSURE THAT THEY HAVE ALL THE INFORMATION REQUIRED TO REALISE THE DESIGN. MEET REHEARSAL WEEK WITH PROPERTIES SUPERVISOR ON A REGULAR BASIS TO ENSURE ALL QUERIES ARE ADDRESSED AND CHECK THE 5 REALISATION OF DESIGNS.
WK -1
TECH WEEK
WORK IN CONJUNCTION WITH THE DIRECTOR & THE REST OF THE CREATIVE TEAM & CREW TO REALISE THE PRODUCTION. PROVIDE NOTES TO THE PSM TO BE DISTRIBUTED TO PROPS SUPERVISOR AT THE CONCLUSION OF EACH SESSION.
WK 0
PERFORMANCE
ATTEND PERFORMANCES. Bump out planning. All new props to be reveiwed by HOD properties/store supervisor for NIDA collection. All new props to be reveiwed by Designer and propmaker for expo, storage to be arranged as required.
BUMP OUT
ASSIST IN RETURNING THE VENUE TO ITS ORIGINAL STATE + ENSURE THAT RETURNS ARE COMPLETED.
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
PROPERTIES WORKSHOP
PRIOR
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
Design delivery to head of properties. Props list, Props referance bible all construction drawings. Properties supervisor allocated.
WK -11
PRE-PRODUCTION
Design delivery to Properties Supervisor for costing; Props list, Props referance bible all construction drawings.
WK -10
PRE-PRODUCTION
Costing / negotiations Props super visor to estimate materials/sourcing costs of entire build. This shall be compared to available budget (from Production Manager, Nick Day) and discrepancies shall be discussed with HOD properties. Meetings with Designer
WK -9
PRE-PRODUCTION
Costing and Construction Sign off by Head of Properties. Costing and labour MUST be within show budgets before this approval will be given. Design delivery to Production crew.
HOLIDAY
WK -8
PRE-PRODUCTION WEEK 5
Properties supervisor pre production. All large materials ordered(e.g. Steel and timber, such that they might be ordered in conjunctiuon with sets and properties for production season, saving delivery costs). All specials to be ordered (e.g. Foams plastic
WK -7
PRE-PRODUCTION WEEK 6
Properties supervisor pre production see above. Production planning time budgeting and allocation. Schedules devised and published.
WK -6
REHEARSAL WEEK 1
Crew starts. Construction commences. Read, and respond to rehearsal reports as required. Meet daily with designer to address and queries and review the realisation of designs.
WK -5
REHEARSAL WEEK 2
Designer, Director and ASM to comence discussion of changes to props bible as a result of rehearsal room developments. Read, and respond to rehearsal reports as required. Meet daily with designer to address and queries and review the realisation of desi
WK -4
REHEARSAL WEEK 3
Final props list as per directors sign off, detailed and documented, with approval of HOD properties, delivered to Properties supervisor for construction, by end of week. Read, and respond to rehearsal reports as required. Meet daily with designer to ad
WK -3
REHEARSAL WEEK 4
Work shop to produce any alterations to prop bible. Read, and respond to rehearsal reports as required. Meet daily with designer to address and queries and review the realisation of designs.
WK -2
BUMP IN WEEK Show props delivered to rehearsal room. Set dressing commences on stage. ASM to confirm to HOD properties that all properties listed in REHEARSAL WEEK final props list approved by Director in WK -5 have been delivered. Read, and respond to rehearsal reports as required 5
WK -1
TECH WEEK
Crew finished in construction and shift to show crew roles allocated by PSM. Supervisor will check and respond apropriatley to Rehearsal /tech reports. Supervisor to attend at least one tech session, and any session where props issues are arrising or likl
WK 0
PERFORMANCE
Bump out planning. All new props to be reveiwed by HOD properties/store supervisor for NIDA collection. All new props to be reveiwed by Designer and propmaker for expo, storage to be arranged as required. Supervisor will check and respond apropriatley to
BUMP OUT
All props to be removed from venue. All loans to be returned. All new props to be returned to store and/or disposed of. PSM and props supervisor to seek signoff from HOD properties that all resources are made good and accounted for.
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
LIGHTING DEPARTMENT
PRIOR
WK -20
PRE-PRODUCTION
WK -19
PRE-PRODUCTION
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
WK -4
REHEARSAL WEEK 3
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
WK 0
PERFORMANCE
BUMP OUT
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
SOUND DEPARTMENT
PRIOR
WK -20
PRE-PRODUCTION
WK -19
PRE-PRODUCTION
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
WK -4
REHEARSAL WEEK 3
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
WK 0
PERFORMANCE
BUMP OUT
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
AV DEPARTMENT
PRIOR
WK -20
PRE-PRODUCTION
WK -19
PRE-PRODUCTION
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
WK -4
REHEARSAL WEEK 3
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
WK 0
PERFORMANCE
BUMP OUT
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
STAGE MANAGEMENT
PRIOR
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
HOLIDAY
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
Designer, Director and ASM to comence discussion of changes to props bible as a result of rehearsal room developments.
WK -4
REHEARSAL WEEK 3
Final props list as per directors sign off, detailed and documented, with approval of HOD properties, delivered to Properties supervisor for construction, by end of week.
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
Crew finished in construction and shift to show crew roles allocated by PSM. DESIGNER TO PROVIDE NOTES TO THE PSM TO BE DISTRIBUTED TO WORKSHOP SUPERVISORS AT THE CONCLUSION OF EACH SESSION.
WK 0
PERFORMANCE
Bump out planning. All new props to be reveiwed by HOD properties/store supervisor for NIDA collection. All new props to be reveiwed by Designer and propmaker for expo, storage to be arranged as required.
BUMP OUT
All props to be removed from venue. All loans to be returned. All new props to be returned to store and/or disposed of. PSM and props supervisor to seek signoff from HOD properties that all resources are made good and accounted for.
Updated 5/10/2012
NIDA
PRODUCTION DESIGN AND PRODUCTION PROCESS
WEEKS / PERIOD
DIRECTOR
PRIOR
WK -18
PRE-PRODUCTION
WK -17
PRE-PRODUCTION
WK -16
PRE-PRODUCTION
WK -15
PRE-PRODUCTION WEEK 5
WK -14
PRE-PRODUCTION WEEK 6
WK -13
PRE-PRODUCTION
WK -12
PRE-PRODUCTION
WK -11
PRE-PRODUCTION
WK -10
PRE-PRODUCTION
WK -9
PRE-PRODUCTION
HOLIDAY
WK -8
PRE-PRODUCTION WEEK 5
WK -7
PRE-PRODUCTION WEEK 6
WK -6
REHEARSAL WEEK 1
WK -5
REHEARSAL WEEK 2
Designer, Director and ASM to comence discussion of changes to props bible as a result of rehearsal room developments.
WK -4
REHEARSAL WEEK 3
Final props list as per directors sign off, detailed and documented, with approval of HOD properties, delivered to Properties supervisor for construction, by end of week.
WK -3
REHEARSAL WEEK 4
WK -2
WK -1
TECH WEEK
WK 0
PERFORMANCE
BUMP OUT
Updated 5/10/2012