GIS Application in Sabah Sarawak Gas Pipeline

Group -9 Anshu, Abhishek, Vineet AIIM

Overview
2

Problem Statement Old Way, New Way Route Influences Least-Cost Path

AIIM

Problem
3

Select alignment alternatives for optimal cross-country pipeline construction that meet project requirements.
Summarize alignment alternatives to facilitate real dollar cost estimation for early concept development (+/- 50%)

AIIM

Old Problem, Old Solution


4

The Manual Method


Small Scale Paper Maps (State Regulatory Dept, etc) Hand Delineation(marking out) Terrain Evaluation from Aerial Photographs

AIIM

Old Problem, New Solution


5

The GIS Method


Digital Maps Spatial Database (retrieval & storage) Data Manipulation Raster Analysis (Map Algebra, LCP, etc.)

Used properly, GIS methods are faster, more efficient, more comprehensive, and less expensive than traditional methods.
AIIM

Route Influences
6

Engineering/Cost

Socioeconomic

Biophysical

AIIM

AIIM

What is Least-Cost Path?


8

COST SURFACE

LEAST-COST SURFACE

LEAST-COST PATH (VECTOR)

Land Cover
COST SURFACE COST SURFACE LEAST-COST Surface LEAST-COST PATH (VECTOR)

+
Land Cover

=
Terrain-Slope AIIM

Cost-Weighted Surface
9

Influence

LEAST-COST/WEIGHTED

*
Land Cover

.60

*
Terrain-Slope

.40

AIIM

Inserting Dollar Costs


10

Pipe Summary Length Geometry

Crossing Report Type Subtype Frequency Length

Productivity
-

Construction Summary Labor Crew Equipment

Cost Estimate Spread Sheet

GIS

Cost Estimating Manual

AIIM

SSGP Status
11

Social objections Completion extended from 2011 to 2013.