THE STRUCTURE

THE ANSWER IS: D2 IN THE FIFTH WEEK THE PROCESS: 1. The dimensions of the structure can be used to work out that it contains 50,000 cubic units of materials. 2. The stone blocks are 1 cubic unit in size therefore 50,000 are needed.

3. Each worker lays 50 blocks per hour. There are 7 working hours per shift. There are 3 shifts in each working day. There are 3 workers on 2 shifts and 2 on the other shift. Therefore 2,800 blocks can be laid in a day.

4. D5 is a maintenance day. 5. Block number 50,000 is therefore laid on D2 of week 5.

NOTE: The information given on card numbers 5, 9, 16, 23 and 24 is irrelevant.

THE STRUCTURE
1. The task is essentially one of team problem solving that is totally reliant on good communication. 2. To achieve this TASK the team must:(a) Understand what is required. (b) Share the information that is available. (c) Communicate effectively. (d) Make sure that the language that is used is clearly understood. (e) Analyze the information in order to arrive at the correct solution within the time allowed.

Signs of Successful Team - Work


1. 2. 3. 4. 5. Degree of Cooperation. Necessary Actions without being asked. Team members willingly help each other. Leader involved rather than Policing. Team members Enjoying Work even when work is Boring, Dirty or Unpleasant.